Process Industry 1 of 7
WL-PI022
Work Instruction
Supersedes: Revision: 0
Piping Isometric Lifecycle Issue Date:
01-Apr-2011
Issuing Department: Function or Process Owner: Previous Rev. & Issue Date: Effective Date:
Piping Design Piping Department 01-Apr-2011
Management Team
1.0 PURPOSE
This Work Instruction establishes a standard workflow and defines the minimum requirements, roles
and responsibilities for managing piping isometrics on projects in Phase 4. This Work Instruction
may be supplemented with additional office specific Work Instructions and Technical Guidelines as
required.
3.0 DEFINITIONS
3.1 ABBREVIATIONS
CAD Computer Aided Design
DQS Design Quality Surveillance
DTS Design Technology Services
FEL Front End Loading
FEED Front End Engineering Design
HO Home Office
IFC Issued for Construction
IFD Issued for Design
JMMS Jacobs Material Management System
JPI Jacobs Project Information System
P&ID Piping and Instrument Diagram
PMTO Piping Material Take Off (a module in JMMS)
RDB Reference Data Base
SO Support Office
TG Technical Guideline
WBS Work Breakdown Structure (Shown in workflow diagram for reference only)
WI Work Instruction
The applicable version of this document resides in the Business Practices section of http://JNet.jacobs.com. All copies are considered to be
uncontrolled.
File Name: WL-PI022.doc
WL-PI022 Page 2 of 7
Piping Isometric Lifecycle Rev. 0, 01-Apr-2-11
Inter-Discipline Review)
TR-5 Iso Coordinator Prints & Distributes Isometrics (for Inter-
Discipline Review)
TR-6 Home Office Iso Coordinator Logs in Iso Tracking System
(from Inter-Discipline Review)
TR-7 Home Office Iso Coordinator Logs in Iso Tracking System
(Review Comments)
TR-8 Home Office Iso Coordinator Loads into JPI (Comment
copies)
TR-9 Workshare Iso Coordinator Logs in Iso Tracking System if
Applicable (Comment copies)
TR-10 Iso Coordinator Logs in Iso Tracking System (to Checker)
TR-11 Iso Coordinator Logs in Iso Tracking System (from Checker)
TR-12 Iso Coordinator Logs in Iso Tracking System (comments
from Signoff Cycle)
TR-13 Iso Coordinator Logs in Iso Tracking System (Rev. 0 for
Signoff)
TR-14 Home Office Iso Coordinator Prints Isometric for IFC Signoff
TR-15 Home Office Iso Coordinator Logs in Iso Tracking System
(for Home Office Signoff)
TR-16 Home Office Iso Coordinator Logs in Iso Tracking System
(Signoff comment copies)
TR-17 Home Office Iso Coordinator Groups Isometrics into Issue
Packages by destination &, verifies that Extraction Number &
Date on electronic Iso matches signed copy
TR-18 Home Office Iso Coordinator transmits Package to JPI
TR-19 Home Office Iso Coordinator verifies that Isos were loaded
into JPI & JPI Card attributes are populated
TR-20 Home Office Iso Coordinator gives hard copy package of
isos to Document Management or Project Engineer
SA-1A Piping Engineer performs Stress Analysis & loads docs into
JPI for Review (for Stress Group 1 / Level 1 Lines or
SA Piping Stress Engineer
equivalent)
SA-1B Piping Engineer performs Stress Analysis (for Stress Level
2 Lines or equivalent)
SA-1C Piping Engineer performs Stress Review & loads Docs into
JPI (for Stress Group 2 / Level 3 Lines or equivalent)
SA-2 Home Office Reviews Stress Calcs & posts Comments in JPI
SA-3 Home Office Stress in consultation with Home Office Piping
Design Notifies Workshare about Comments
SA-4A Stress Calculations are Reviewed / Checked & Comments
Posted on JPI (for Stress Level 1 Lines or equivalent)
SA-4B Stress Calculations are Reviewed /Checked & loads Docs
4.2 3D MODELING
4.2.1 Modeling and Isometric Production Philosophy
The design and isometric production philosophy will be to use the 3D model as the master
source of information from which isometric drawings are extracted. The Piping Design
discipline must initiate and maintain the piping design in the 3D model then extract the
isometric drawings as required. Piping Design must not modify isometric drawings in 2D
after extraction as this will lead to conflicting data and a duplication of effort (No manual
annotation outside of the 3D Model).
4.2.2 Equipment Layout Model / Preliminary Piping Layout Model
Prior to commencement of Phase 4, it is anticipated that the status of the existing 3D
piping model could vary depending on the project, but at a minimum shall contain plot
determining piping with respect to process, stress, material and / or size, modeled to
confirm equipment and structure locations. The primary purpose of this review was to
confirm equipment locations based on major / critical line routing and to review platform
access and egress and maintenance spacing.
conducted and reconciled as design progresses and just prior to model reviews, and
extraction of isometrics for check and issue.
6.0RECORDS
The current applicable version of this publication resides on Jacobs’ Intranet. All copies are
considered to be uncontrolled.