Вы находитесь на странице: 1из 4

About: Dr.

Andy Skumanich is the ceo and


founder of SolarVision Consulting. He has previously
worked for Innovalight and Applied Materials’ Solar
Division.
Feature article

CSP at a
crossroads
The first solar electric power plants are
still proving their worth after three
decades, so why aren’t we seeing more
CSP reach the development stage?

T
HE FIRST major concentrating solar But it wasn’t until after SEGS III
that the projects were finally able to
power (CSP) plants were built in the
attract investors - including multiple
Mojave Desert, U.S. in 1984 and have eastern U.S. utilities.
been producing over 330 MW since then.
Boom and bust cycles
A well-publicised slump hit the industry Although successful by most
in the nineties, but recently there has metrics, the original company which
been a major upswing in installations, developed the project – Luz – had
to declare bankruptcy. Oil prices fell
and an even bigger increase in project announcements. and remained low through the 1990’s
– construction of new solar plants
However, before we break out The origins stalled. The regressive energy policy
the champagne, as another article The first CSP (parabolic trough) starting with the Reagan administra-
in this issue points out (see ‘Smoke plant came online in 1985 as Solar tion, along with the vagaries of prop-
and mirrors’, page 42), announce- Energy Generating System #1 (SEGS erty taxes, forced the company to close
ments are one thing, what they are I) with a capacity of 13.8 MW. Eight down. However, the investor groups
not is data: everything always takes other SEGS plants were subse- continued to sell electricity to utilities.
longer than the optimistic announce- quently built in the same region of It wasn’t until the mid-noughties
ments indicate, and Projects (and the Mojave Desert, with the last one that new companies again began
even Contracts), are often cancelled. coming online in 1991. looking at innovative ways to gener-
There have been some recent notable The total output of the collective ate large scale solar power, and a
examples of this. set of parabolic trough plants is 354 second cycle of CSP activity began in
One tale of woe is that of a 92 MW. According to Hank Price, one of 2004. Luz Founder, Arnold Goldman,
MW CSP facility that El Paso Elec- the original engineers working on the regrouped his old team, and founded
tric Co. had planned for Santa project, this early work offered BrightSource Energy. In addition,
Teresa in New Mexico. The project the chance not just for technology Silicon Valley venture capitalists gave
collapsed because of difficulties with evaluation, but also the opportunity some substantial funding to new com-
securing financing. to study costs and possibilities for ers such as Ausra and encouraged the
The utility now plans to build a 20 cost reduction. Indeed the cost of renaissance in CSP.
MW PV facility instead. wholesale solar thermal electricity
So the immediate challenge for from the SEGS plants has halved What’s happening now?
CSP is to avoid another bust by turn- from its initial cost of US$0.24kWh. There are now almost 8 GW of
ing the GWs announced into actual Indeed, the original project has CSP projects in the pipeline, com-
GWh of electricity. In other words, been generating electricity for three pared with the 500 MW that will
prove the technology’s bankability decades and has provided 14 TWh of be installed by the end of 2010. This
and capability. energy. project pipeline sits in stark contrast

52 January/February 2011 | Renewable Energy Focus


Feature article

to recent cancellations of CSP power


plants. So why is so much of this
Silver bullet for
planned capacity taking so long to
CSP? Sopogy
develop? The CSP industry appears at
micro-CSP installa-
a crucial turning point. tion in Hawaii
The “potential” of CSP is an oft-
heard term, and it is true that there
are some very attractive aspects of
CSP – in principle. CSP has two key
positive aspects: It can provide good
energy dispatchability, and it has an
ability for hybridisation. The two ele-
ments are interrelated. CSP can be
configured to have thermal storage
(at a price) and can provide up to 6 or
even 8 hours of post-sun-down energy.
And hybridisation allows the power
plant to have both solar and standard leveraging both industry partners and balance various competing require-
energy for heating. the national laboratories. DoE’s goals ments from both an engineering, envi-
In principle, this capability would include increasing the use of CSP in ronmental impact, and advanced design
allow for 100% capacity – where the the U.S., making CSP competitive in perspective. Because of legitimate con-
power plant is providing electricity the intermediate power market by cerns about environmental disruption,
over the full 24 hour cycle, turning the 2015, and developing advanced tech- the engineers designed a system which
plant into a tunable base load resource nologies that will reduce systems and minimised impact by almost eliminat-
- the Holy Grail for renewables. storage costs, enabling CSP to be ing the need for extensive land grading
competitive in the base load power and concrete foot pads. By placing indi-
Storing CSP power arena by 2020. In addition, there are vidual mirrors on poles directly into the
Because of this, there is a signifi- numerous support programs at the ground, the system allows vegetation to
cant amount of research going into National Renewable Energy Labora- co-exist within the project and avoids
CSP storage, and efforts are underway tory (NREL) for storage projects. impacting sensitive habitats. Also, to
to find a low-cost and flexible solu- conserve scarce desert water, the tower
tion. But in the near term at least, Luz/BrightSource shines again uses air-cooling, which compared with
the market doesn’t provide a value for More good news is that Bright- conventional water-cooling results in
this storage. Source has broken ground on another 90% less water usage, although with
The ability of hybridisation is project in the desert at Ivanpah, 40 some loss in overall efficiency. The
important too, because hybridisation miles south west of Las Vegas, NE. water that is used is part of a closed
improves the intermittency factor, The facility, scheduled to come online loop system within the boiler segment.
the shaping of the electricity, and the in 2012, will have a capacity of almost In this regards, the Ivanpah
capacity factor. 400 MW, making it the world’s largest project is a good template for CSP
Again there are some limitations, CSP plant currently under construc- developments as it includes multiple
however. If solar is paired with a tion. The project is a combined effort stakeholders such as the developers,
carbon-based power source it can have between BrightSource and none other utilities, and environmental groups.
two negative effects: Solar projects than Bechtel (the largest engineering
in the U.S. are limited to 2% natural company in the U.S., which built the Cost and bankability
gas in order to remain designated as Hoover Dam in 1933). A key element Despite the upsurge in the CSP
“renewable” - and hence qualify for to this project’s success was securing pipeline, there are some warning signs
support (the SEGS I - IX projects are a US$1 billion Loan Guarantee from that CSP still has the potential to hit
limited to 25%.) Secondly, in some DoE. another bust cycle.
instances the use of a coal-fired plant One of the encouraging aspects The issues are a perfect storm of
being running at less than full capac- to this project is that it was able to three elements: The primary one is
ity (during times of high renewable
generation) can become substantially
less efficient, and actually contribute to Rather than wait for NRG to get
higher air pollution.
Clearly, these issues are much funding, El Paso Electric switched
intertwined. The good news for now
is that the US Department of Energy to solar PV to meet the State’s
(DoE) is ramping up its CSP research,
development, and deployment efforts, renewable energy mandates.

January/February 2011 | Renewable Energy Focus 53


Feature article

rejected. Rather than wait for NRG to


SEGS: CSP success story get funding, El Paso Electric switched
to solar PV to meet the state’s renew-
The SEGS plants (pictured) performance improvements - in able energy mandates.
range in capacity from 13.8MW to fact many of the cost reduction “We can get banks to finance a
80 MW, and they were constructed strategies that can now be applied solar PV project now, but they’re not
to meet Southern California Edison to other CSP technologies and the yet ready to finance a solar thermal
Company’s periods of peak power industry in general. The com- project,” Knox says. “That’s why we
demand. The plants operate for 80% bined efforts developed capabili- need to rely on Loan Guarantees to do
of the summer mid-peak hours, ties for reducing O&M costs by a it, but we won’t get that in the time
and 66% of the winter mid-peak third. O&M is a substantial part frame that El Paso Electric needs it.”
hours. A natural gas backup system of CSP running costs, unlike fixed Jason Marks of the New Mexico PUC
supplements the solar capacity and panel solar photovoltaics (PV), says “the problem is not just timing
contributes up to 25% of the plants’ where the O&M costs are a small – it’s an endemic situation facing the
annual output. fraction. CSP industry”.
Learning from the early SIGS In addition, the plants were able In addition, there have been other
plants has been extensive. During to perform to exceptional stan- recent cancellations of projects where
the 1990’s the SEGS’s technical dards and achieved a record output the utilities switched from CSP to
team worked with the Depart- for single-day generation of over solar PV - citing costs. The learn-
ment of Energy’s (DoE) Sandia 2 GWh, and established a world ing curve of PV is much steeper and
National Lab to develop cost- record solar thermal-to-electric advanced than that of CSP, and stor-
reduction strategies for O&M efficiency of 18%. The SEGS 1-9 age complicates things further.
planning optimisation; subsystem configuration is a true success story This situation becomes a reinforc-
automation; mechanical and reli- in the annals of CSP (image courtesy ing cycle: Cheaper PV leads to more
ability improvements; and overall of Warren Gretz – DoE/NREL). installations, which in turn leads to
increasingly cheaper PV. This is the
essence of the solar market, getting
the cost down and moving along the
learning curve as quickly as pos-
sible. Great for PV. Not so great for
CSP. And Levelised Cost of Electricity
(LCOE), which is often used to pro-
mote CSP, is becoming lower for PV
and is projected to continue on this
trajectory.

Small is beautiful
Despite the challenges, there are
some developing trends which could
provide a path to viability: Getting
the ‘bad luck’ of the global economic All this means there is a very bigger by going smaller.
squeeze, which has made access to significant question about bank- There are emerging market oppor-
capital very restricted. ability, which has become a common tunities in developing countries with
The second element is the increas- buzz word on the solar arena. This a poor or non-existent grid and power
ing drop in the prices of solar PV and is a legitimate concern as investors infrastructure. In these countries,
the ever-expanding track record for don’t want to take on risk for less- such as India, the need for local power
large-scale PV installations. than-fully proven technologies. When is great, but the regional demand is
The third element is that CSP you couple that uncertainty with the only on the scale of a few MW’s.
projects are typically large-scale, and large investments needed for CSP, the This application is a relatively hid-
require major amounts of not just result is major hesitation. The case of den market but could be on a par with
money; but time for building; and El Paso Electric illustrates perfectly the nominal ‘grid-connected’ market.
regulatory review. Although there is this developing storm on the open In some regards, this market is similar
the ‘economies of scale’ positive ben- desert planes. to the cell phone mode, where the
efit for larger builds, there are other David Knox of NRG Energy Inc, landline infrastructure is not in place,
costs and barriers which increase which El Paso Electric contracted but local service can be provided by
with size. Permitting is more complex, to develop the CSP plant, explains towers. The demand here is great, and
labour rates can go up, and the need the situation in simple terms. NRG there is a need for viable energy which
for grid upgrade or transmission can sought a Loan Guarantee from DoE to provides both immediate needs - as
be substantial. build the facility, but its request was well as some storage.

54 January/February 2011 | Renewable Energy Focus


It would be ironic if the iconic
origins of terrestrial solar
power, the SEGS plants,
remain just an image of a
CSP boom-bust cycle in the
Mojave Desert…
Conclusion
The ability of CSP to provide both hybrid power (as well
as storage) gives it an edge for the time being. However,
there is a big caveat, which is the necessity for micro-CSP.
Typical CSP installations need to be large-scale to amortise
the balance of plant (BOP), and O&M costs. Therefore mini-
mum sizes tend to be in the multiple 10s of MWs, much too
large for micro-grid requirements.
However, two companies are addressing this requirement:
One is Aora, and the other is Sopogy. They are both striving
to provide sub-MW CSP solutions. Sopogy is based in the
U.S., has been around since 2002, and already has a 2MW
project operating in Hawaii - with new micro-grid contracts
underway. Aora is based in Israel, and is targeting a 100kW
demonstration unit in Spain by mid-2011.
CSP has gone through some boom and bust cycles in its
30-year history. It is poised to make a comeback but there
are some significant clouds gathering on the horizon. For
CSP there is the urgent need to prove its future capability
(i.e. its potential) now. The CSP providers need to achieve
significant momentum. In an unfortunate storm of market
conditions, CSP is getting squeezed between tighter capital
and the plummeting costs of PV.
It would be ironic if the iconic origins of terrestrial solar
power, the SEGS plants, remain just an image of a CSP
boom-bust cycle in the Mojave Desert, still cranking away
on a tumble weed-blown plane, but left behind because of
market forces and the dynamics of technology.
Of course one answer to averting a bust-cycle is simple:
Deliver on some of the projects currently in the pipeline.
There are some leaders in the CSP segment who recognise
the urgency and are pushing for a re-focusing of energy
into execution and co-operation. Stephen Mullinnex of US
Renewables group, which is backing the CSP installer Solar-
Reserve would say that his competition (e.g. BrightSource) is
not really the competition – because the more CSP installed,
the better for everyone in the industry.
As he puts it: “It’s now more about MWh than about
‘bragga-watts’.” In other words, there is a need to act swiftly
to execute projects in the pipeline rather than bringing more
volume to the pipeline, because time may well catch up with
the industry.
First published in the November/December issue of Renewable
Energy Focus U.S. magazine. See http://www.renewableenergyfo-
cususa.com for more details.
e: askumanich@solarvisionco.com

January/February 2011 | Renewable Energy Focus 55

Вам также может понравиться