Академический Документы
Профессиональный Документы
Культура Документы
CSP at a
crossroads
The first solar electric power plants are
still proving their worth after three
decades, so why aren’t we seeing more
CSP reach the development stage?
T
HE FIRST major concentrating solar But it wasn’t until after SEGS III
that the projects were finally able to
power (CSP) plants were built in the
attract investors - including multiple
Mojave Desert, U.S. in 1984 and have eastern U.S. utilities.
been producing over 330 MW since then.
Boom and bust cycles
A well-publicised slump hit the industry Although successful by most
in the nineties, but recently there has metrics, the original company which
been a major upswing in installations, developed the project – Luz – had
to declare bankruptcy. Oil prices fell
and an even bigger increase in project announcements. and remained low through the 1990’s
– construction of new solar plants
However, before we break out The origins stalled. The regressive energy policy
the champagne, as another article The first CSP (parabolic trough) starting with the Reagan administra-
in this issue points out (see ‘Smoke plant came online in 1985 as Solar tion, along with the vagaries of prop-
and mirrors’, page 42), announce- Energy Generating System #1 (SEGS erty taxes, forced the company to close
ments are one thing, what they are I) with a capacity of 13.8 MW. Eight down. However, the investor groups
not is data: everything always takes other SEGS plants were subse- continued to sell electricity to utilities.
longer than the optimistic announce- quently built in the same region of It wasn’t until the mid-noughties
ments indicate, and Projects (and the Mojave Desert, with the last one that new companies again began
even Contracts), are often cancelled. coming online in 1991. looking at innovative ways to gener-
There have been some recent notable The total output of the collective ate large scale solar power, and a
examples of this. set of parabolic trough plants is 354 second cycle of CSP activity began in
One tale of woe is that of a 92 MW. According to Hank Price, one of 2004. Luz Founder, Arnold Goldman,
MW CSP facility that El Paso Elec- the original engineers working on the regrouped his old team, and founded
tric Co. had planned for Santa project, this early work offered BrightSource Energy. In addition,
Teresa in New Mexico. The project the chance not just for technology Silicon Valley venture capitalists gave
collapsed because of difficulties with evaluation, but also the opportunity some substantial funding to new com-
securing financing. to study costs and possibilities for ers such as Ausra and encouraged the
The utility now plans to build a 20 cost reduction. Indeed the cost of renaissance in CSP.
MW PV facility instead. wholesale solar thermal electricity
So the immediate challenge for from the SEGS plants has halved What’s happening now?
CSP is to avoid another bust by turn- from its initial cost of US$0.24kWh. There are now almost 8 GW of
ing the GWs announced into actual Indeed, the original project has CSP projects in the pipeline, com-
GWh of electricity. In other words, been generating electricity for three pared with the 500 MW that will
prove the technology’s bankability decades and has provided 14 TWh of be installed by the end of 2010. This
and capability. energy. project pipeline sits in stark contrast
Small is beautiful
Despite the challenges, there are
some developing trends which could
provide a path to viability: Getting
the ‘bad luck’ of the global economic All this means there is a very bigger by going smaller.
squeeze, which has made access to significant question about bank- There are emerging market oppor-
capital very restricted. ability, which has become a common tunities in developing countries with
The second element is the increas- buzz word on the solar arena. This a poor or non-existent grid and power
ing drop in the prices of solar PV and is a legitimate concern as investors infrastructure. In these countries,
the ever-expanding track record for don’t want to take on risk for less- such as India, the need for local power
large-scale PV installations. than-fully proven technologies. When is great, but the regional demand is
The third element is that CSP you couple that uncertainty with the only on the scale of a few MW’s.
projects are typically large-scale, and large investments needed for CSP, the This application is a relatively hid-
require major amounts of not just result is major hesitation. The case of den market but could be on a par with
money; but time for building; and El Paso Electric illustrates perfectly the nominal ‘grid-connected’ market.
regulatory review. Although there is this developing storm on the open In some regards, this market is similar
the ‘economies of scale’ positive ben- desert planes. to the cell phone mode, where the
efit for larger builds, there are other David Knox of NRG Energy Inc, landline infrastructure is not in place,
costs and barriers which increase which El Paso Electric contracted but local service can be provided by
with size. Permitting is more complex, to develop the CSP plant, explains towers. The demand here is great, and
labour rates can go up, and the need the situation in simple terms. NRG there is a need for viable energy which
for grid upgrade or transmission can sought a Loan Guarantee from DoE to provides both immediate needs - as
be substantial. build the facility, but its request was well as some storage.