Petroleum Development Oman LLC Effective: October 2013
Document ID CP-196
Security Unrestricted
Owner FPP
Revision 2.0
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this
document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any
means (electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
Page 1 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Page 2 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
i Document Authorisation
Page 3 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
ii Revision History
Page 4 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Policy None
Page 5 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
TABLE OF CONTENTS
Appendix 2 .......................................................................................................................................20
Appendix 3 .......................................................................................................................................21
Appendix 4 .......................................................................................................................................22
Page 7 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
1 Introduction
1.1 Background
Surplus materials are materials left on hand and remain unused after project completion,
cancellation or change in design.
These materials could have been drawn from PDO general stock items (standard stock item),
procured specifically for project use (project material), or procured by contractor on PDO’s behalf.
This code of practice covers management of surplus materials from projects such as EMC/ODC
and other capital projects. The processes covered include: surplus identification, verification,
reconciliation, project to project transfer, return to PDO logistics and surplus re-use.
Management of surplus materials generated from standard PDO stock is covered by a separate
Code of Practice i.e. CP-193.
1.2 Purpose
This Code of Practice and related procedures details the principles on which all surplus material
management activities are to be identified, planned and implemented in an orderly manner so as
to deliver fit for purpose surplus material management services.
1.4 Abbreviations
Abbreviation Description
CoP Code of Practice
MTC Material Test Certificate
MRS Material Reconciliation Sheet
GU Guideline
PR Procedure
WH Warehouse
MAP Moving Average Price
MTO Material Take Off
FFP Finance Focal Point
FCN Field Consignment Note
BI Business Intelligence – SAP reporting tool
QA Quality Assurance
CFDH Corporate Functional Discipline Head
EMC Engineering and Maintenance Contract
ODC Off-plot Delivery Contract
Page 8 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
2.1 Scope
This Code of Practice applies to:
• PDO and Contractors’ units that execute project surplus materials management activities.
• Site locations owners, both PDO and Contractors, where project surplus materials are held
and/or surplus materials management activities are carried out.
2.2 Objectives
The Objectives of the Code of Practice is:
• To ensure that PDO surplus materials are properly identified and managed while under PDO
or Contractor’s custody.
• To ensure adequate and accurate surplus inventory records are maintained at all times at
both PDO and Contractors’ storage facilities.
• To help accelerate the utilization and disposal of surplus materials
• To provide clarity about relevant activities/processes around surplus materials
Page 9 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
• Surplus materials should be properly marked, labeled and preserved at all time in accordance
with PDO’s procedures and guidelines as detailed in GU-707 Project Material Preservation
Guidelines and PR-1858 Procedure for Material Handling, Storage and Preservation
• PDO operates a process which ensures that surplus stock is checked prior to a new order being
placed on the market. This provides the basis for optimising our existing surplus assets thus
allowing PDO to contain project costs. Therefore, any material procurement requests, whether
procurement is to be done by PDO or by our contractors, shall first be screened by a respective
PDO or Contractor’s Project Engineer against surplus stock records in SAP and only approved if
no suitable items are found in stock.
• Compliance owners shall develop annual Compliance Assurance Plan based on Surplus
Management Key Controls Matrix (Appendix 4) and carry out relevant compliance checks as
appropriate.
Page 10 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Page 11 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Investment recovery Responsible for sale/disposing off unwanted materials following the
section approval of write-off (where required) as detailed in Section 4.5 herein.
Stock Checkers Responsible for overall stock checking and reconciliation process
Finance Focal Point Responsible for making manual debit/credit procurement cost transfers
(FFP) for materials transferred between projects in coordination with the
relevant project engineers.
Page 12 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
4 Practices to be followed
The amount of surplus materials generated from PDO operations is perceived to be high and
therefore must be controlled. It is therefore recommended to limit the amount of surplus
materials left behind after project completion to ca 5% of the total material/procurement capex.
CHs are expected to closely monitor inventory levels, track procurement activities, continuously
work to identify and transfer surplus inventories during various stages of the project so that to
ensure the 5% guide is not breached by the end of the project.
4.1.1 General
As a general practise, the contractor shall produce quarterly reports of materials considered as
surplus in their storage facilities and forward to CH review. CH shall review the same and decide
whether to keep the material where is, move to another project or return to PDO.
Within two months of project substantial completion (during the commissioning and initial operate
phase) or cancellation, the contractor shall prepare the final material reconciliation statement of all
PDO owned surplus materials (both PDO supplied and contractors procured) using PDO’s
standard template (see Appendix 2 attached herein). Contractor shall consult relevant PDO staff
to review and sign-off the Material Reconciliation Statement (MRS) prior to arranging material
transfer to relevant site.
Page 13 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
• Electrical items
Cables without marking / Identification information
Small length below 5 meter or so.
Scrape boxes, wooden drums,
Corroded / Damaged fuses.
Old/damaged Fittings & Fixtures.
• Instrumentation items
Cables without marking / Identification information
Small length up to 5 meters.
Corroded/ Damaged gauges & meters.
• Damaged items
These items should first be checked for rectification / correction for potential use, if
possible. If not, then they can be scrapped.
Page 15 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Responsibility
Contract Holder
MM Maintainer
PDO Logistics
N/A – Not Applicable
Contractor
Step # Task Description
Account for all surplus materials, prepare a
1 Material Reconciliation Statement (MRS) and S A N/A N/A N/A
seek PDO approval to move materials to PDO
Carry out physical material verification against the
2 MRS, decide whether to ‘keep’ or ‘scrap’ the A S N/A N/A N/A
material and sign-off the MRS
Prepare coding requests for ‘keep’ materials and
3 S A N/A S N/A
forward to MM Maintainer for coding.
Pack/label materials and keep ready for dispatch.
4 Mobilise transport of materials to PDO Logistics S A N/A N/A S
sites as per the contractual requirements
Receive materials verify details against the MRS.
5 N/A S N/A S A
Sign-off the Field Consignment Note (FCN)
Page 16 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
6.1 Application
This Code of Practice is applicable to all project surplus management related activities and
processes, both under the responsibilities of PDO and contractors.
Page 17 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Appendix 1
Appendix 1: Chart 1 Material Reconciliation for Major and EMC/ODC jobs
Contractor Contractor
Contract Holder Comments
Warehouse QA-QC
Is contractor
No
liable?
Segregate material/list
Yes
Page 18 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Appendix 1 cont’d
Appendix 1: Chart 2 (contd): Material Reconciliation for Major and EMC/ODC jobs)
Chart 2
Return materials to PDO
Yes
Is it required?
No
Store or Scrap No
Yes
Provide material
Yes
specification to Data
Arrange Coding
Management for
coding
Scrap Flag as Scrap
Update Reconciliation
Sheet ‘comment’ field Sign off Final Material
and get PDO final sign Reconciliation Sheet
off
Verify material
against
reconciliation
Ask PDO or Arrange statement
transport as per the
contract
Scrap: Receive
& inform Store: Receive
Transfer material to PDO Upload MTC into
investment & Update SAP
warehouse ‘Doctor’ System
recovery team records
Page 19 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Appendix 2
Page 20 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Appendix 3
Page 21 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Appendix 4
Page 22 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Version 2.0
Petroleum Development Oman LLC Effective: October 2013
Page 23 CP- 196 Surplus Stock Management Code of Practice Printed 10/10/2013
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.