PROJECT: 8.

4MW UPPER MALADUGAO HYDROELECTRIC POWER PLANT Thursday, March 7, 2019


LOCATION: BRGY. LAMPANUSAN, KALILANGAN BUKIDNON
CONTRACTOR: PHESCO INC.
OWNER: UHPC

DAILY PRODUCTION REPORT DATE:

QUANTITY
NO. OF WORKERS REQUIRED REMAINING
ITEM STRUCTURE ACTIVITIES DONE TO REMARKS
TO DATE QUANTITY QUANTITY
DATE

Excavation

Rebar Works
1 POWER HOUSE
Form Works

Concrete works

Bed preparation & lean


concrete

Laying of Rebar -
Foundation
Concrete works for
foundation
2 HEADRACE Laying of Wall Rebar for
second lift
Concrete works for
foundation
Laying of Wall Rebar for
final lift

Concrete works for final lift

Bed preparation & lean


concrete
Laying of Rebar -
Foundation
Concrete works for
foundation
Laying of Wall Rebar for
3 RETAINING WALL
second lift
Concrete works for
foundation
Laying of Wall Rebar for
final lift

Concrete works for final lift

4 SLUICEWAY

5 WEIR INTAKE F&C

6 WEIR INTAKE RCW