PAN MALAYSIA TRANSPORTATION &

INSTALLATION OF OFFSHORE FACILITIES

QA/QC INSPECTION REPORT

BASIC INFORMATION

Date/Duration : 27 August 2019 Reported by: Amirrul Asyraf

Scope / Location : Bredero Shaw (Kuantan) – SEP CRA Linepipe

Report No : PAN-QA-DPR-BSM-046

Other participants /
: OMS/ BEN LINE
visitors at site

Distribution List : PMT

1.0 SURVEILLANCE ACTIVITIES / PROGRESS


Pipe ready to inspect : 72 CRA pipes
Pipe inspected today : 65 CRA pipes
Cumulative Inspected : 2295 CRA pipes
KPI perday : Minimum 100 CRA pipes/ day

BSM production rate : Average 60 joints / day

2.0 LOOK AHEAD PLAN


 To complete all inspection prior last load out

3.0 CONCERNS (QUALITY CONCERNS, NCR & ETC)


 OMS to increase inspection speed to meet KPI 100 pipes per day. BMD inspector will assist.
 Slow inspection progress is due to unavailability of ready pipe from BSM

4.0 QA/QC MANNING


 BMD : 1 Coating inspector
 OMS : 2 personnel
 Ben Line : 2 riggers

Page 1 of 2