WBS Code WBS Name 2018 2019 2020 2021


Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
WBS METRO -SAMPLE WBS 04-Oct-18 A 02-Mar-21
WBS.KM KEY MILESTONES 04-Oct-18 A 02-Mar-21
WBS.KM.CM CONTRACT MILESTONES 04-Oct-18 A 02-Mar-21
WBS.KM.KD KEY DATE 03-Feb-19 02-Mar-21
WBS.KM.KD.CKD CONTRACTUAL KEYDATES 03-Feb-19 02-Mar-21
WBS.IM INTERFACE MILESTONE 03-Mar-19 01-Nov-20
WBS.IM.DD DESIGN INTERFACE MILESTONE 03-Mar-19 03-Mar-19
WBS.IM.CN CONSTRUCTION INTERFACE MILESTONE 26-Jul-20 01-Nov-20
WBS.EO EMPLOYER'S OBLIGATION 03-Dec-18 01-Nov-19
WBS.EO.AW ACCESS TO WORK SITE 03-Dec-18 29-May-19
WBS.EO.HT RELOCATION OF ELECTRICAL LINE ABOVE 33 KV 02-Jan-19 16-Jul-19
WBS.EO.TR TREE CUTTING AND RELOCATION 03-Dec-18 01-Nov-19
WBS.PE PRELIMINARIES 03-Dec-18 02-Mar-21
WBS.PE.CS CONTRACTUAL SUBMISSION 03-Dec-18 02-Mar-21
WBS.GS GENERAL SUBMISSION 03-Dec-18 28-Oct-20
WBS.GS.MS METHOD STATEMENT 03-Dec-18 03-Feb-20
WBS.GS.MA MATERIAL SUBMITTAL 02-Jan-19 28-Oct-20
WBS.GS.MD MIX DESIGN 31-Jan-19 13-Aug-19
WBS.GS.SA SUBCONTRACTAPPROVALS 03-Dec-18 04-Apr-19
WBS.GS.PM PLANS AND MANUALS
WBS.GS.GDS GENERAL DESIGN SUBMISSION 03-Dec-18 28-Feb-20
WBS.GS.GDS.TW TEMPORARY WORK/ENABLING WORKS 03-Dec-18 04-Feb-19
WBS.GS.GDS.TW.SB SAFETY BARRICADE DRAWINGS 03-Dec-18 31-Dec-18
WBS.GS.GDS.TW.SP SITE LAYOUT PLAN 03-Dec-18 04-Feb-19
WBS.GS.GDS.TW.FP FOUNDATION DETAILS OF PLANTS 02-Jan-19 27-Jan-19
WBS.GS.GDS.PW PERMANENT WORKS 19-Jan-19 12-Jan-20
WBS.GS.GDS.PW.TS TOPOGRAPHICAL SURVEY DRAWING 17-Feb-19 18-Apr-19
WBS.GS.GDS.PW.LG DRAWINGS FOR LAUNCHING GIRDER 12-Apr-19 07-Jun-19
WBS.GS.GDS.PW.FS DETAILS OF FORMWORKS AND SCAFFOLDING 12-Apr-19 19-Oct-19
WBS.GS.GDS.PW.PM DRAWINGS FOR PRECASTMOULDS 11-Mar-19 18-Jul-19
WBS.GS.GDS.PW.SA DRAWINGS TO BE SUBMITTED FOR STAKEHOLDER'S APPROVALS 25-May-19 05-Nov-19
WBS.GS.GDS.PW.TY TYPICAL DESIGNAND OTHER DESIGN 13-Apr-19 12-Jan-20
WBS.GS.GDS.PW.PC PRECAST (CASTING YARDS) 12-Apr-19 22-Nov-19
WBS.GS.GDS.PW.OS OBLIGATORY SPAN & SPECIAL SPAN 19-Jan-19 05-Dec-19
WBS.GS.PD PRELIMINARY DESIGN & DRAWINGS (DS-1) 04-Feb-19 12-Apr-19
WBS.GS.PD.SI GEOTECHNICAL SITE INVESTIGATION 10-Mar-19 04-Apr-19
WBS.GS.PD.GW GUIDEWAY 04-Feb-19 12-Apr-19
WBS.GS.PD.PC PRECAST SEGMENT 13-Feb-19 12-Apr-19
WBS.GS.MIS MISCELLANEOUS SUBMISSION
WBS.GA GENERAL ACTIVITES/SITE INSTALLATION 03-Dec-18 02-Mar-21
WBS.GA.MOB MOBLIZATION 03-Dec-18 01-Mar-21
WBS.GA.MOB.LL LABOUR LICENSES 03-Dec-18 01-Mar-21
WBS.GA.MOB.MM MOBLIZATION OF MANPOWER 03-Dec-18 01-Mar-21
WBS.GA.MOB.PO PERMITS FOR ESTABLISHMENT OF PLANTS AND OPERATIONS 02-Jan-19 11-Apr-19
WBS.GA.MOB.ME MOBILIZATION OF PLANTS AND EQUIPMENTS 02-Jan-19 21-Aug-19
WBS.GA.MOB.PR PROCUREMENT 04-Mar-19 16-Jan-21
WBS.GA.MOB.PR.LL LONG LEAD ITEMS 07-Jun-19 20-Sep-20
WBS.GA.MOB.PR.FA FABRICATION 18-May-19 15-Jun-20
WBS.GA.SIN SITE INSTALLATION 02-Jan-19 02-Mar-21
WBS.GA.CY CASTING YARD 02-Jan-19 30-Nov-20
WBS.GA.CY.CYS CASTING YARD SET UP 02-Jan-19 28-Oct-19
WBS.GA.CY.BS BOX SEGMENT 25-Aug-19 24-Sep-20
WBS.GA.CY.SBS STACKING OF BOX SEGMENT 17-Sep-19 22-Oct-20
WBS.GA.CY.PP PRECAST PARAPET 18-Nov-19 01-Nov-20
WBS.GA.CY.SPP STACKING OF PRECAST PARAPET 23-Nov-19 30-Nov-20
WBS.GA.CY.MU MOCK UP /TRAILS 11-Mar-19 03-Aug-19
WBS.PRS PROVISIONAL SUM 26-Apr-19 03-Feb-20
WBS.GW GUIDEWAY 04-Oct-18 A 02-Mar-21
WBS.GW.ILT INITIAL LOADTEST 25-Feb-19 19-Oct-19
WBS.GW.011 ELEVATED SECTION 03-Dec-18 02-Mar-21
WBS.GW.011.SC SITE CLEARANCE 11-Mar-19 08-Apr-19
WBS.GW.011.SUR SURVEY 12-Feb-19 04-Mar-19
WBS.GW.011.PMG PERMITS (INTIMATIONAND NOC FROM UTILITY AUTHORITIES 03-Dec-18 10-Apr-19
WBS.GW.011.TT TRAIL TRENCHES/UTILTYIDENTIFICATION 09-Mar-19 10-Apr-19
WBS.GW.011.URD UTILITY DESIGN DRAWINGS/RELOCATION DRAWINGS
WBS.GW.011.URD.CU CHARTED UTILITIES
WBS.GW.011.URD.CU.ELHT ELECTRICAL LINE UPTO 33 KV ( 11 KV & 33 KV)
WBS.GW.011.URD.CU.ELLT ELECTRICAL LINE (LT LINES/440V)
WBS.GW.011.URD.CU.SP STREELIGHT POLES
WBS.GW.011.URD.CU.TS TRAFFIC SIGNALS/CCTV CAMERA POLES
WBS.GW.011.URD.CU.CP CELL PHONE TOWER
WBS.GW.011.URD.CU.UCD UNDERGROUND OFC CABLE AND DUCTS
WBS.GW.011.URD.CU.GP GAS PIPELINES
WBS.GW.011.URD.CU.WL WATER LINES
WBS.GW.011.URD.CU.SL SEWER LINE
WBS.GW.011.URD.CU.DP DRAINAGE PIPES,CATCH BASINS,INLETS

All Projects Summary Page 1 of 3 © Oracle Corporation


WBS Elements below Project
08-Jul-19 11:50
WBS Code WBS Name 2018 2019 2020 2021
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
WBS.GW.011.URD.UU UNCHARTED UTILITIES
WBS.GW.011.URD.UU.ELHT ELECTRICAL LINE UPTO 33 KV ( 11 KV & 33 KV)
WBS.GW.011.URD.UU.ELLT ELECTRICAL LINE (LT LINES/440V)
WBS.GW.011.URD.UU.SP STREELIGHT POLES
WBS.GW.011.URD.UU.TS TRAFFIC SIGNALS/CCTV CAMERA POLES
WBS.GW.011.URD.UU.CP CELL PHONE TOWER
WBS.GW.011.URD.UU.UCD UNDERGROUND OFC CABLE AND DUCTS
WBS.GW.011.URD.UU.GP GAS PIPELINES
WBS.GW.011.URD.UU.WL WATER LINES
WBS.GW.011.URD.UU.SL SEWER LINE
WBS.GW.011.URD.UU.DP DRAINAGE PIPES,CATCH BASINS,INLETS
WBS.GW.011.TTM TRAFFIC MANAGEMENT
WBS.GW.011.TTM.TDP TRAFFIC DIVERSION PLAN
WBS.GW.011.TTM.TD TRAFFIC DIVERSION
WBS.GW.011.TTM.MNT MAINTENANCE OF TRAFFIC DIVERSION
WBS.GW.011.URW UTILITY RELOCATION WORKS
WBS.GW.011.URW.CU CHARTED UTILITIES
WBS.GW.011.URW.CU.ELHT ELECTRICAL LINE UPTO 33 KV ( 11 KV & 33 KV)
WBS.GW.011.URW.CU.ELLT ELECTRICAL LINE (LT LINES/440V)
WBS.GW.011.URW.CU.SP STREELIGHT POLES
WBS.GW.011.URW.CU.TS TRAFFIC SIGNALS/CCTV CAMERA POLES
WBS.GW.011.URW.CU.CP CELL PHONE TOWER
WBS.GW.011.URW.CU.UCD UNDERGROUND OFC CABLE AND DUCTS
WBS.GW.011.URW.CU.GP GAS PIPELINES
WBS.GW.011.URW.CU.WL WATER LINES
WBS.GW.011.URW.CU.SL SEWER LINE
WBS.GW.011.URW.CU.DP DRAINAGE PIPES,CATCH BASINS,INLETS
WBS.GW.011.URW.UU UNCHARTED UTILITIES
WBS.GW.011.URW.UU.ELHT ELECTRICAL LINE UPTO 33 KV ( 11 KV & 33 KV)
WBS.GW.011.URW.UU.ELLT ELECTRICAL LINE (LT LINES/440V)
WBS.GW.011.URW.UU.SP STREELIGHT POLES
WBS.GW.011.URW.UU.TS TRAFFIC SIGNALS/CCTV CAMERA POLES
WBS.GW.011.URW.UU.CP CELL PHONE TOWER
WBS.GW.011.URW.UU.UCD UNDERGROUND OFC CABLE AND DUCTS
WBS.GW.011.URW.UU.GP GAS PIPELINES
WBS.GW.011.URW.UU.WL WATER LINES
WBS.GW.011.URW.UU.SL SEWER LINE
WBS.GW.011.URW.UU.DP DRAINAGE PIPES,CATCH BASINS,INLETS
WBS.GW.011.GSI GEOTECHNICAL SITE INVESTIGATION 24-Mar-19 21-Apr-19
WBS.GW.011.CID CIVIL DESIGN 10-Apr-19 14-Jan-20
WBS.GW.011.CID.PD PRELIMINARY DESIGNS(DS-1) 10-Apr-19 29-Jun-19
WBS.GW.011.CID.PD.GSI GEOTECHNICAL SITE INVESTIGATION 10-Apr-19 08-Jun-19
WBS.GW.011.CID.PD.GW GUIDEWAY 21-Apr-19 29-Jun-19
WBS.GW.011.CID.DD DETAILED DESIGN & DRAWING (DS-2) 04-Jun-19 27-Dec-19
WBS.GW.011.CID.DD.GSI GEOTECHNICAL SITE INVESTIGATION
WBS.GW.011.CID.DD.GW GUIDEWAY 04-Jun-19 27-Dec-19
WBS.GW.011.CID.GFC GOOD FOR CONSTRUCTION/WORKING DRAWINGS 08-Jun-19 14-Jan-20
WBS.GW.011.CID.GFC.GSI GEOTECHNICAL SITE INVESTIGATION 08-Jun-19 18-Jun-19
WBS.GW.011.CID.GFC.GW GUIDEWAY 23-Jul-19 14-Jan-20
WBS.GW.011.CIC CONSTRUCTION OF GUIDEWAY 22-Jul-19 31-Jan-21
WBS.GW.011.CIC.PI PILING/OPEN FOUNDATION 22-Jul-19 11-Apr-20
WBS.GW.011.CIC.PC PILE CAP 07-Aug-19 17-Jun-20
WBS.GW.011.CIC.PR PIER 02-Sep-19 29-Jun-20
WBS.GW.011.CIC.PCE PIER CAP 24-Sep-19 11-Jul-20
WBS.GW.011.CIC.PD PEDESTAL 17-Oct-19 05-Aug-20
WBS.GW.011.CIC.PD.CU CURING 21-Oct-19 05-Aug-20
WBS.GW.011.CIC.SE SPAN ERECTION 14-Jun-20 27-Sep-20
WBS.GW.011.CIC.SE.LG SPAN ERECTION BY LG 13-Jul-20 27-Sep-20
WBS.GW.011.CIC.SE.GS SPAN ERECTION BY GS
WBS.GW.011.CIC.SE.CG SPAN ERECTION OF STEEL GIRDER 14-Jun-20 26-Sep-20
WBS.GW.011.CIC.BEA GROUTING AND BEARING FIXING 02-Sep-20 13-Oct-20
WBS.GW.011.CIC.CB CRASH BARRIER 30-Apr-20 13-Dec-20
WBS.GW.011.CIC.PE PARAPET ERECTION 19-Sep-20 30-Oct-20
WBS.GW.011.CIC.EJ EXPANSION JOINT 12-Oct-20 08-Nov-20
WBS.GW.011.CIC.RH RAIN HARVESTING 31-Oct-20 31-Jan-21
WBS.GW.011.EM E&M 30-Sep-20 16-Dec-20
WBS.GW.011.RE REINSTATEMENT WORK 20-Dec-20 02-Mar-21
04-

WBS.IFC INTERFACE ACTIVITES 26-Jul-20 02-Mar-21


WBS.IFC.DS DESIGN & SUBMISSIONAPPROVAL

All Projects Summary Page 2 of 3 © Oracle Corporation


WBS Elements below Project
08-Jul-19 11:50
WBS Code WBS Name 2018 2019 2020 2021
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
WBS.IFC.DS.UA UTILITYAUTHORITIES/STAKEHOLDER
WBS.IFC.DS.SCA SYSTEM CONTRACTORACCESS
WBS.IFC.CI CONSTRUCTION INTERFACE 26-Jul-20 02-Mar-21
WBS.IFC.CI.UA UTILITYAUTHORITIES/STAKEHOLDER
WBS.IFC.CI.SCA SYSTEM CONTRACTORACCESS 26-Jul-20 02-Mar-21
WBS.FW FINISHING WORK 20-Dec-20 02-Mar-21
WBS.TC TEST & COMMISSIONING 20-Dec-20 02-Mar-21
WBS.TC.OM O & M MANUAL 20-Dec-20 19-Feb-21
WBS.TC.TOC TEST ON COMPLETION 20-Dec-20 02-Mar-21
WBS.AB AS BUILT WORKS 20-Jul-20 28-Feb-21
WBS.HO HANDING OVER 26-Jul-20 02-Mar-21
WBS.HO.SHO SUBSTANISAL HANDING OVER 26-Jul-20 01-Nov-20
WBS.HO.FHO FINAL HANDING OVER 01-Mar-21 02-Mar-21