Ceiling Works

4′ x 8′ x 4.50mm Fiber Cement (ceiling board) sht 425.00

4′ x 8′ x 9mm Gypsum Board (ceiling board) sht 410.00

4′ x 8′ x 9mm Gypsum Board (ceiling board, Moisture Resistant) sht 520.00

Ficem Screw 20mm pc 0.70

Ceiling Vent:

1″x1″x10′ s4s Tanguile or its equivalent pc 65.00

1″x3″x8′ s4s Tanguile or its equivalent pc 65.00

Insect Sreen sht 140.00

0.8mm thk. -12mm x 38mm x 5.00m Double Furring pcs 112.56

0.8mm thk. -12mm x 38mm x 5.00m Single Furring pcs 102.56

0.2mm thk-20mm x 20mm x 2.44m Wall Angle pcs. 36.50

Rod suspension hanger w/adjustment spring set 65.00

Pre-formed wire clip set 3.03

Toks Srew pcs. 0.70

Concreting Works

Concrete

Soil Poisoning – Termicide Liter 325.00

Gravel cu.m 1,010.00

Wash Sand cu.m 1,035.00

Portland Cement, 40kg Bag 260.00

Pozzolan Cement, 40kg Bag 260.00

Steel Bars

10mm Diameter Deformed Bars pc 156.00

12mm Diameter Deformed Bars pc 223.00

16mm Diameter Deformed Bars pc 394.00

20mm Diameter Deformed Bars pc 645.00

1|Page
#16 G.I. Tie Wire kg 16.00

Formworks

2 x 3 x 10′ Coco lumber pc 280.00

2 x 4 x 10 Coco lumber pc 280.00

1/2″ x 4′ x 8′ Plywood pc 660.00

6mm thk. Lawanit board pc 209.00

6mm thk. Ordinary Plywood pc 330.00

1″x2″x8′ Hard wood or its equivalent pc 65.00

2″x2″x8′ Hard wood or its equivalent pc 65.00

2″x2″x8’Hardwood or its equivalent pc 65.00

2″x24″x8′ Hard wood or its equivalent pc 65.00

Deformed Reinforcing Bars Prices

Description Unit Amount (php)

REBAR, Gr 40, 12mm dia x 6m pc 187.13

REBAR, Gr 40, 12mm dia x 7.5m pc 233.92

REBAR, Gr 40, 12mm dia x 9m pc 280.69

REBAR, Gr 40, 12mm dia x 10.5m pc 327.47

REBAR, Gr 40, 12mm dia x 12m pc 374.26

REBAR, Gr 60, 16mm dia x 6m pc 334.42

REBAR, Gr 60, 16mm dia x 7.5m pc 418.02

REBAR, Gr 60, 16mm dia x 9m pc 501.62

REBAR, Gr 60, 16mm dia x 10.5m pc 585.23

REBAR, Gr 60, 16mm x 12m pc 668.83

REBAR, Gr 60, 20mm dia x 6.0m pc 522.60

REBAR, Gr 60, 20mm dia x 10.5m pc 914.56

REBAR, Gr 60, 25mm dia x 6.0m pc 816.55

REBAR, Gr 60, 25mm x 9.0m pc 1,224.82

2|Page
REBAR, Gr 60, 25mm dia x 10.5m pc 1,428.97

REBAR, Gr 60, 25mm dia x 12m pc 1,633.10

Electrical Pipe Prices per Commercial Length

Description Unit Amount (Php)

IMC PIPE 1/2″ (15mm) x 3M w/ COUPLING pc 227.70

IMC PIPE 3/4″ (20mm) x 3M w/ COUPLING pc 294.19

IMC PIPE 1″ (25mm) x 3M w/ COUPLING pc 515.53

IMC PIPE 1-1/4″ (32mm) x 3M w/ COUPLING pc 613.88

IMC PIPE 1-1/2″ (40mm) x 3M w/ COUPLING pc 777.52

IMC PIPE 2″ (50mm) x 3M w/ COUPLING pc 992.70

IMC PIPE 2-1/2″ (65mm) x 3M w/ COUPLING pc 1,685.50

IMC PIPE 3″ (80mm) x 3M w/ COUPLING pc 2,060.26

IMC PIPE 3-1/2″ (90mm) x 3M w/ COUPLING pc 3,091.29

IMC PIPE 4″ (100mm) x 3M w/ COUPLING pc 3,583.05

FMC ORDINARY 1/2″ (15mm) pc 21.59

FMC LT 4″ (100mm) pc 1,841.44

FMC LT 30″ (80mm) pc 1,095.94

FMC LT 2-1/2″ (65mm) pc 924.46

PVC CONDUIT 20MM (1/2″) x 3m pc 58.14

PVC CONDUIT 25MM (3/4″) x 3m pc 76.04

PVC CONDUIT 32MM (1″) x 3m pc 108.09

PVC CONDUIT 40MM (1-1/4″) x 3m pc 137.92

PVC CONDUIT 63MM (2″) x 3m pc 222.17

PVC CONDUIT 110MM (4″) x 3m pc 673.96

ELECTRICAL WORKS

Pipe and Fitting


3|Page
20mmdia UPVC pipe pcs 85.00

20mmdia RSC conduit pcs 216.00

20mmdia RSC coupling pcs 20.00

20mmdia UPVC coupling pcs 5.00

20mmdia UPVC adoptor pcs 7.50

20mm dia. Locknut& bushing pcs 8.00

20mm dia. RSC Locknut& bushing pcs 14.30

Boxes and Gutter

Junction box depth type,metal gauge 16 w/ cover pcs 25.00

Utility box depth type, metal gauge 16 w/cover pcs 25.00

4×4 square box depth, metal gauge 16 w/cover pcs 50.00

Miscellaneous and Consumables

Electrical tape big pcs. 40.00

Rubber tape big pcs. 90.00

Solvent cement 100cc pcs. 240.00

G.I. Wire No. 12 kls. 70.00

Concrete nail no.3 kls. 120.00

CWN no.3 kls. 70.00

Entrance cap pcs. 35.00

Terminal Lugs lot 600.00

Red Led Paint pcs. 429.00

Cable Tie pc 1.00

Secondary Rack pc 540.00

Black Paint gal 610.00

Wires

8.0mm2 THHN m 43.33

5.5mm2 THHN m 36.59

3.5mm2 THHN m 25.00

4|Page
2.0mm2 THHN m 23.33

Wiring Devices

1-gang Switch, 10A, 240V set 110.00

2-gang switch, 10A, 240V set 140.00

2-gang 3 way switch, 10A, 240V set 240.00

1-gang Convenince Outlet, 10A, 240V set 250.00

2-gang Convenience Outlet, 3 prong 10A, 240V set 351.00

Lighting Fixtures

24 Watts light bulb set 285.00

1-18watts Compact flourescent lighting fixtures set 680.00

keyless type,porcelain receptacle

2-36 watts ,220v,Flourescent (box type) set 1,200.00

1 x 18, 230V, Compact Flourescent (Keyless Type Porcelain


Receptacle Outlet) set 680.00

Power Load Center Switch Gear and Panel Board

Main :40AT/50AF,1PCB,240V,18KAIC, BOLT-ON set 12,500.00

Branches

2-15AT/50AF,1PCB,240V,10KAIC,,BOLT-ON PC 315.70

3-20AT/50AF,1PCB,240V,10KAIC,,BOLT-ON PC 315.70

GENERAL REQUIREMENTS / PRELIMINARIES (elevator construction)

Description Qty Unit Amount (Php)

A. Mobilization (Temporary Office (including construction/relocation of


temporaryfacilities)

Contractor’s Office 1 lot 51,750.00

Warehouse 1 lot 51,750.00

B. Cleaning and Disposal of Garbage/Debris 1 lot 17,250.00

C. Premium for Insurance and Bonds (including Renewal Cost up to Project Completion)

Surety Bond (Equivalent to 10% contract amount) 1 lot 21,968.65


5|Page
Performance Bond (Equivalent to 10% contract amount) 1 lot 43,937.29

Guarantee Bond (Equivalent to 10% contract amount) 1 lot 109,814.06

D. Water and Electric Consumption 1 lot 23,000.00

E. Demobilization (Clearing, removal of temporary


facilities, Tools, Debris, Excess Materials, etc.) 1 lot 17,250.00

F. Other Requirements (Pls. specify)

Permits (Incl. Mayor’s City tax, & Other Misc. Permit


charges) 1 lot 88,895.00

Cost of Local Procurement/ Material (Incl. Drawings/


Plotting, PME Sign & Seal materials door safety nettings,
barricades, consumable materials, welding rods, wire, etc. 1 lot 492,200.00

Cable + Conduit (for WTB-Watch Tower Board or


Supervisory Panel 1 lot 34,500.00

Total 952,315.00

ELEVATOR WORKS, TESTING & COMMISSIONING

Description Qty Unit Amount (Php)

Installation of Scaffolding 1 lot 17,503.00

Hoisting 1 lot 26,254.50

Template Setting 1 lot 43,757.50

Marking and Boring of Holes 1 lot 26,254.50

Bracket Setting 1 lot 35,006.00

Rail Setting 1 lot 43,757.50

Sill/Jamb Installation 1 lot 52,509.00

Floor Indicator/Call buttons 1 lot 8,751.50

Machine Room Equipment Setting 1 lot 43,757.50

Machine Room Piping 1 lot 17,503.00

Hoist-way Piping 1 lot 43,757.50

Landing Door Assembly 1 lot 35,006.00

Car Assembly 1 lot 61,260.50

Travelling Cable Lay-out 1 lot 21,878.75

6|Page
CWT Assembly 1 lot 21,878.75

Lay-out of Ropes 1 lot 26,254.50

Wiring (Machine Room/Hoist-way) 1 lot 70,012.00

Initial Test 1 lot 52,509.00

Slow Speed test (Start up) 1 lot 26,254.50

Load Test 1 lot 13,127.25

Drop Test 1 lot 13,127.25

Buffer Test 1 lot 8,751.50

Plate Setting/Slow Switch Installation 1 lot 43,757.50

Rubber Block Setting 1 lot 17,503.00

High Speed Testing 1 lot 61,260.50

Standard/Special Feature Test 1 lot 26,254.50

Others 1 lot 17,503.00

Total 875,150.00

Embankment (per cubic meter)

Common Borrow 384.40

Selected Borrow 392.40

Mixed Sand & Gravel 585.11

Rock 602.56

Aggregate Subbase Course

Aggregate Subbase Course Material 818.13

Aggregate Base Course 934.89

Crushed Grading A 839.13

Uncrushed Grading A 926.00

Crushed Grading B 831.63

Uncrushed Grading B 837.00

Blended Weathered Limestone and Crush Stone 818.22

7|Page
Filler Materials 401.00

Crushed Aggregate Base (per cubic meter)

Crushed Grading A 921.63

Crushed Grading B 875.43

Lime Stabilized Road Mx Base Course (per cubic meter)

Lime Stabilized Mixed Soil Aggregate Base Course Crushed Grading A 693.75

Lime Stabilized Mixed Soil Aggregate Base Course Crushed Grading B 662.78

Lime Stabilized Mixed Soil Aggregate Base Course Uncrushed Grading A 670.00

Lime Stabilized Mixed Soil Aggregate Base Course Uncrushed Grading B 641.11

Aggregate Surface Course (per cubic meter)

Crushed Grading A 878.22

Crushed Grading B 864.33

Crushed Grading C 884.75

Crushed Grading D 856.38

Uncrushed Grading A 826.13

Uncrushed Grading B 817.38

Uncrushed Grading C 812.63

Uncrushed Grading D 793.25

Fire Protection System

B.I. Pipe 100mm dia lm 1,889.00

B.I. Pipe 75mm dia lm 984.00

B.I. Pipe 65mm dia lm 708.00

B.I. Pipe 50mm dia lm 425.00

B.I. Pipe 40mm dia lm 317.00

B.I. Pipe 25mm dia lm 192.00

Fittings (Elbow, Tee, Reducer, etc) l.s. 15,000.00

Pendent 12mm dia pc 503.00

8|Page
Side Wall 12mm dia pc 518.00

Fire Hose Cabinet with Fire Extinguisher set 24,000.00

Fire Extinguisher, 10 lbs Capacity, Wall Mounted, HCFC 123 set 6,825.00

FP-1, Horizontal Split Case Centrifugal Pump with A.C. Motor


& Controller, UL/FM Approved, 350 GPM, 125psi, 40 HP,
230/3/60 assy 1,116,923.00

FP-1, Horizontal Split Case Centrifugal Pump with A.C. Motor


& Controller, UL/FM Approved, 350 GPM, 100psi, 30 HP,
230/3/60 assy 887,692.31

JP-1 Vertical In-Line Centrifugal Pump with AC Motor &


Controller, UL/FM Approved, 10GPM, 5HP, 130psi, 230, 3/60 assy 300,000.00

m. JP-1 Vertical In-Line Centrifugal Pump with AC Motor &


Controller, UL/FM Approved, 10GPM, 3HP, 100psi, 230, 3/60 assy 180,000.00

Gate Valve (OS & Y), 100mm dia unit 31,680.00

Y-Strainer unit 36,118.45

Check Valve unit 17,500.00

Alarm Check Valve Assembly unit 63,360.00

Globe Valve unit 9,114.00

Pressure Reducing Valve unit 104,099.33

Float Valve unit 77,396.68

Water Flow Switch unit 6,468.00

Floor Control Valve unit 8,303.00

Pressure Gauge unit 971.13

FDC Siamese Twin: Two-Way unit 6,500.00

Isolation Valve unit 18,000.00

Water Flow Meter unit 58,084.99

Drain Off Valve unit 19,557.51

Roof Manifold unit 16,199.14

Hangers and Support l.s. 25,000.00

Electrical Works for Pumps from Main Breaker l.s. 15,000.00

9|Page
Miscellaneous and Consumables l.s. 5,000.00

Testing and Commissioning l.s. 167,000.00

Overhead Water Tank 2000 US Gal unit 167,000.00

Fire Reserve Tank 11000 US gal unit 162,962.00

Fire Reserve Tank 7000 US gal unit 103,703.70

Fire Alarm System

Bell, Vibrating Type set 1,300.00

Equipment for Fire Alarm Control Panel set 13,890.00

Manual Pull Switch set 1,250.00

Curtain Walls and Glazing Works Prices

Material Description Unit Price

8mm thk Reflective Tempered Glass Door sq.m. 33,600.00

12mm thk Frameless Glass Door sq.m. 33,000.00

12mm thk Reflective Tempered Glass Door sq.m. 37,000.00

12mm thk Clear Tempered Glass Wall sq.m. 6,700.00

Light Blue Light Reflective Tempered Glass Curtain Wall sq.m. 7,400.00

Aluminum Wall Cladding sq.m. 4,200.00

Aluminum Canopy sq.m. 4,400.00

Railing with 12mm thk Clear Tempered Glass x 0.8m H l.m. 1,008.50

Guide to Cement and Aggregates Factors per Concrete Class Mixture

Handy guide on factors to multiply per cubic on different concrete class mixtures. Just multiply
each factor to the total volume (in cubic meter) and you’ll get the needed amount of cement
(40Kg/bag), sand (cu.m.) and gravel (cu.m.).

Class C (2,000 psi) Gravel 0.898 cu.m.


Cement 5.634 Bags Class B (2,500 psi)
Sand 0.4794 cu.m. Cement 7.399 Bags

10 | P a g e
Sand 0.486 cu.m. Gravel 0.856 cu.m.
Gravel 0.8856 cu.m. Class AA (4,000 psi)
Class A (3,500 psi) Cement 11.729 Bags
Cement 8.799 Bags Sand 0.475 cu.m.
Sand 0.5724 cu.m. Gravel 0.8344 cu.m.

The following factors were already added an average wastage add-ons of around 5% to 8%. This
numbers should help average Filipinos to know draft amount of materials needed for minor
concreting works.

Product and Execution Requirements (hardscape works)

Description QTY Unit Amount (Php)

Product Storage and Handling


(Contractor’s Temporary Warehouse) 1 lot 20,000.00

Construction Layout and Surveying 1 lot 20,000.00

Local Business Permit 1 lot 20,000.00

Cleaning 1 lot 20,000.00

Description QTY Unit Material (Php) Labor (Php)

Dampproofing and Waterproofing

Cementitious and Reactive


Waterproofing 1 SQ.M. 690.00 200.00

Colorless Floor Hardener 1 SQ.M. 135.00 56.25

Tiles, Stampcrete and Accessories

Supply, Delivery and Installation of


Granite (150mm x 150mm) 1 SQ.M. 3,450.00 1,800.00

Supply, Delivery and Installation of


Granite (300mm x 600mm) 1 SQ.M. 4,300.00 1,800.00

Supply, Delivery and Installation of


#10 Crushed Granite (Washout) 1 SQ.M. 3,290.00 350.00

11 | P a g e
Supply, Delivery and Installation of
Homogeneous Tiles (600mm x 600mm) 1 SQ.M. 1,515.00 350.00

Supply, Delivery and Installation of


Homogeneous Tiles (300mm x 300mm) 1 SQ.M. 1,525.00 350.00

Supply, Delivery and Installation of


150mm Wide Stampcrete 1 SQ.M. 1,950.00 300.00

Supply, Delivery and Installation of


Stampcrete 1 SQ.M. 1,950.00 300.00

Lighting Accessories

Supply, Delivery and Installation of


Recessed Steplight (15W Die Cast
Aluminum with Front Panels) 1 pc 6,900.00 3,800.00

Construction Heavy Equipment and Tools Rates in the Philippines

These construction heavy equipment prices should help you do your own estimate. Everything is
in Philippine Peso currency. These prices are taken from “Association of Carriers and Equipment
Lessors, (ACEL) Inc.” presently 2014 ACEL Rates as used in most projects of the government.

HOURLY RATE
DESCRIPTION (PHP)

Earthmoving Equipment

Bulldozer 3,379.00

Payloader 1,733.00

Motorized Road Grader 2,173.00

Compaction Equipment

Plate Compactor 123.00

Lifting Equipment

Crawler Crane 1,522.00

Crawler Crane 1,902.00

Crawler Crane 2,151.00

12 | P a g e
Truck Mounted Crane 1,631.00

Truck Mounted Crane 1,861.00

Truck Mounted Crane 2,606.00

Truck Mounted, Scissor Lift, Terrain 1,386.00

Excavating Equipment

Backhoe 1,537.00

Backhoe w/ Breaker 1,998.10

Backhoe, Wheel Mounted 922.00

Portable Breaker 129.38

Foundation Equipment

Diesel Hammer 1,286.00

Vibro Hammer 2,123.00

Vibro Hammer w/ Hydraulic Power Pack 4,118.00

Vibro Hammer 3,069.00

Drilling Rig 3,932.00

Concreting Equipment

Concrete Screeder 545.00

Concrete Paver 6,765.00

One Bagger Mixer 172.00

Transit Mixer 1,318.00

Hauling Equipment

Dump Truck 1,420.00

Cargo/Service Truck 783.00

Boom Truck 1,017.90

Cargo/Service Truck 1,212.00

Water Truck/Pump 2,450.00

Air Equipment

Air Compressor 965.00

13 | P a g e
Air Compressor 502.00

Air Compressor, Portable 450.00

Air Compressor 205.00

Diamond Drill 201.25

Jackhammer 150.00

Pneumatic Drilling Machine 170.00

Pumping Equipment

Water Pump, 100 mm suction Ø 266.25

Water Pump, 100 mm suction Ø 123.38

Pumpcrete 2,076.00

Power Generating Equipment

Generator Set 872.87

Generator Set 2,147.27

Shop Equipment

Welding Machine 391.00

Welding Machine 371.00

Special Support Equipment

Chainsaw 75.36

Miscellaneous Equipment

Concrete Vibrator 91.25

Bar Cutter 219.75

Bar Bender 351.50

Others

Drop Hammer w/ accessories 5,000.00

1 Air Compressor w/ 2 Jack Hammer 1,265.00

Cutting Outfit 45.45

Pile Integrity Testing (Sonic) & accessories


(includes professional fee of Strcutural Engineer and reports) 65,000.00

14 | P a g e
Pile Integrity Testing & accessories
(includes professional fee of Strcutural Engineer and reports) 37,000.00

Dynamic Pile Testing


(includes professional fee of Structural Engineer) 103,000.00

Lighting System/Tower Lights 543.50

Bentonite Bin 280.00

Bentonite Mixer 173.00

SPT & Desanding Machine 559.00

Tremie Pipe Set 320.00


This data is from ACEL’s booklet 2014. No copyright infringement intended.

Construction Labor Rates

Description Unit Rate

Foreman hourly 70.76

Electrician hourly 64.89

Plumber hourly 64.89

Leadman hourly 64.89

Heavy Equipment Operator hourly 59.02

Highly Skilled Worker hourly 59.02

Light Equipment Operator hourly 55.21

Driver hourly 51.33

Skilled Worker hourly 51.33

Semi-skilled Worker hourly 47.46

Unskilled Worker hourly 39.59

PHILIPPINE PRODUCTIVITY RATIOS (Philippine Manpower and Equipment


Productivity Ratio)

DESCRIPTION MANHOUR/UNIT UNIT

1.STRUCTURAL EXCAVATION

Common excavation
15 | P a g e
Hand 6.00 MH/M3

Machine 0.50 MH/M3

Rock excavation 8.00 MH/M3

Hauling of spoils 1.00 MH/M3

2.STRUCTURAL BACKFILL

By hand 5.00 MH/M3

By machine 2.00 MH/M3

3.TRENCHING

By hand 6.00 MH/M3

By machine 0.50 MH/M3

EXCAVATION- MANUAL

Common earth 8.00 MH/M3

Loam of sand 1.31 MH/M3

Clay or heavy soil 1.64 MH/M3

Rock 2.63 MH/M3

EXCAVATION- MECHANICAL

Common earth 6.67 MH/M3

Rock with jack hammer 16.67 MH/M3

BACKFILLING

Common manual 0.82 MH/M3

Gravel fill manual 5.00 MH/M3

TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION


MATLS MANUAL FROM:

0 – 2m Depth 1.25 MH/LM

2 – 3m Depth 1.67 MH/LM

3 – 4m Depth 2.50 MH/LM

4 – 5m Depth 3.33 MH/LM

Placing binder gravel 0.11 MH/M3

16 | P a g e
Escombro backfilling 0.21 MH/M3

Spreading,tamping & grading 0.48 MH/M2

Mechanical compaction, plate compaction 0.06 MH/M3

MANUAL CLEARING & GRUBBING

Clearing under growth & trees – 12″ 0.05 MH/M2

Clearing under growth & shrubs 0.03 MH/M2

Disposal of soil 1.69 MH/M3

Hauling of soil 1.00 MH/M3

Gravel fill 2.07 MH/M3

EXCAVATION – CRANE & CLAMPSHELL

With 8 men & 2 carpenters 1.07 MH/M3

5.ROOFING AND SIDING

Roofing

Metallic 0.97 MH/m2

Non-Metallic 1.51 MH/m2

Siding

Metallic 1.29 MH/m2

Non-Metallic 1.51 MH/m2

CONCRETE WORKS

4.CONCRETE WORKS

Grade members

Formworks 2.54 MH/M2

Concreting 8.54 MH/M3

Rebar 0.07 MH/kg

Finishing 0.40 MH/M2

Suspended members

Formworks 3.28 MH/M2

Concreting 16.70 MH/M3

17 | P a g e
Rebar 0.08 MH/kg

Finishing 0.80 MH/M2

Embeded metal 0.27 MH/kg

Water proofing 1.82 MH/M2

Joint filler 0.30 MH/lLm

PLACING CONCRETE

Slab on Fill 5.00 MH/M3

Slip Form 25.00 MH/M3

Floor Finish Unhardened 1.00 MH/M3

Concrete finished hardened 1.43 MH/M3

REBAR WORKS

Ground floor installation 0.07 MH/M3

Upper floor installation 0.08 MH/M3

Fabrication 0.10 MH/M3

Mixing manual 16.00 MH/M3

Mixing machine 1.80 MH/M3

MORE THAN 1.8 M3 POUR

Chute from truck 7.00 MH/M3

Crane & bucket 14.00 MH/M3

Wheeling 27.00 MH/M3

Finishing 2.80 MH/M3

FORMWORKS & CARPENTRY WORKS

FORM WORKS INSTALLATION

Wall on ground 2.00 MH/M2

Wall above ground 2.35 MH/M2

Beams 3.08 MH/M2

Columns 2.35 MH/M2

Suspended slab

18 | P a g e
Suspended slab 0 – 18″ 1.67 MH/M2

Suspended slab 10 – 36″ up 3.33 MH/M2

Elevated & shored slab forming

Forming only 8.60 MH/M2

Forming & Shoring 11.00 MH/M2

Wood wall & Partition 0.50 MH/M2

FORM WORKS FABRICATION

Form works fabrication 1.00 MH/M2

STRIPPING OF FORMS

Wall on ground 0.25 MH/M2

Wall above 10″ 1.29 MH/M2

Beams 1.03 MH/M2

Columns 0.85 MH/M2

Suspended slab

Suspended slab 0 – 18″ 0.83 MH/M2

Suspended slab 10 – 36″ up 1.08 MH/M2

Elevated & shored slab forming – strip of forms 3.50 MH/M2

Floor slab at grade – strip of forms 2.80 MH/M2

INSTALLATION OF CARPENTRY WORKS

Plywood partition 1.00 MH/PC

T & G Flooring and Siding 0.14 MH/B.F.

Ceiling & frame work 0.36 MH/B.F.

Siding frame work 0.27 MH/B.F.

Flooring framing 0.97 MH/B.F.

Wooden post errection 0.43 MH/B.F.

Truss Fabrication 0.35 MH/B.F.

Truss Installation 0.80 MH/B.F.

Girt Installation 0.21 MH/B.F.

19 | P a g e
Plates Installation 0.13 MH/B.F.

Purlins Installation 0.27 MH/B.F.

Fascia board Installation 0.46 MH/B.F.

1/4″ or 3/4″ thk. plywood

Cutting by manual 1.00 MH/PC

Assembly 0.42 MH/M2

ARCHITECTURAL SPECIALTIES

DOORS

Wooden 2.37 MH/M2

Steel 7.64 MH/M2

Aluminum 8.07 MH/M2

Cyclone wire 7.64 MH/M2

WINDOWS

Glass 3.23 MH/M2

Louver 4.63 MH/M2

Steel 32.29 MH/M2

PARTITIONS

single wall 2.48 MH/M2

Wooden wall 3.44 MH/M2

Wooden Louver 3.44 MH/M2

cyclone Louver 5.38 MH/M2

PAINTING ( 3 coats )

Equipment 0.24 MH/f2

Pipes 0.30 MH/f2

Miscillaneous 0.24 MH/f2

STRUCTURAL STEEL WORKS

7. STRUCTURAL STEEL

Fabrication

20 | P a g e
Light 110-130 MH/MT

Heavy 60-90 MH/MT

Errection

Light 70-100 MH/MT

Heavy 40-60 MH/MT

WELDING ( one pass only )

1- Welder and 1- Helper ( 16 total mh ) 40-50 Lf/day

G.1 STRUCTURAL STEEL

Fabrication

Heavy weight 50-90 MH/MT

Light weight 100-125 MH/MT

Grating 1 1/4″ x 3/16″ 3.0 – 3.5 MH/SF

Star threat grating 4.0 – 5.0 MH/SF

Errection

Heavy Structural teel 30 – 60 MH/MT

Light Structural steel 60- 90 MH/MT

Stacks ( Inc. full welding ) 250 – 300 MH/MT

Tanks ( Inc. full welding ) 200 – 275 MH/MT

FINISHING AND MASONRY WORKS

H. CHB

4” CHB

Laying 8.0 – 10 m2/day

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day

6” CHB

Laying 7.0 – 9.0 m2/day

Tooling 11 – 14 m2/day

21 | P a g e
Plastering 8.0 – 10 m2/day

8” CHB

Laying 6.0 – 8.0 m2/day

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day

Masonry Works

Concrete Hollow Blocks (CHB) 4″ pc 10.00

Concrete Hollow Blocks (CHB) 6″ pc 16.00

Portland Cement, 40 kg. bag 265.95

Washed sand cu.m. 1,165.00

10 mm. Dia. x 6.0 M. DSB pc. 156.20

Tie Wire #16 kg. 65.00

Stone Masonry

Cement bag 260.00

Sand cu.m. 1,232.05

Gravel Fill cu.m. 1,207.05

Weep Holes (PVC) Lm. 228.33

Filter Cloth sq.m. 280.00

Boulders cu.m. 1,282.05

Screened Sand cu.m. 1,521.00

Screened Gravel cu.m. 1,581.00

Metal Roofing Prices

Corrugated Roofing, Gauge 26 (0.551 mm x 2.44mm) SQ M 420.00

Pre-painted Metal Roofing Sheet GA 26, Long Span SQ M 475.00

Pre-painted Metal Roofing Sheet GA 26, 2.44m SQ M 478.00

Pre-painted Gutter, GA 24(0.701 mm) x 2.44m LN.M 355.00

Ordinary Gutter, GA 24 (0.701 mm) x 2.44m LN.M 312.00

22 | P a g e
Pre-painted Flashing, GA 24 (0.701 mm) x 2.44m LN.M 316.00

Ordinary Flashing, GA 24 (0.701 mm) x 2.44m LN.M 310.00

Pre-painted Ridge Roll, GA 24 (0.701 mm) x 2.44m LN.M 255.00

Ordinary Ridge Roll, GA 24 (0.701 mm) 2.44m LN.M 200.00

Roof Ventilators Set 1,560.00

Occupational Supplies Prices

Boots – Waterproof Pair 1,350.00

LED Flashlight Set 550.00

Heavy Duty Leather Gloves Pair 650.00

Safety Goggles pc 480.00

Heavy Duty Construction Hard


Hat pc 1,280.00

Safety Harness set 1,200.00

Rain Coat pc 900.00

Twisted Rope: (Strength = 44.3kN) set 450.00

Steel Toe Shoes Pair 2,450.00

Dome Type Tent: Two full door


and vestibules, breathable,
lightweight fabrics, water-resistant set 2,750.00

Reflectorized Vest pc 80.00

Duct Tape, 4″ pc 225.00

Duct Tape, 1″ pc 165.00

Painting Works

Description / Item Unit Ave. Price

Paint Tinting Color Ltr 182.22

Paint Aluminum gal 661.27

23 | P a g e
Paint Enamel gal 666.82

Paint Latex Gloss gal 642.20

Paint Latex Semi-Gloss gal 652.00

Paint Red Lead gal 597.09

Thinner Paint gal 317.89

Thinner Lacquer gal 481.40

Paint Metal Epoxy gal 776.00

Paint Primer Solvent gal 735.60

Brush Paint (101mm) pc 77.50

Brush Roller (152mm) pc 94.45

Brush Steel (101mm) pc 36.20

Oil Paint Ltr 108.09

Spar Varnish Ltr 1286.91

Lacquer Putty Kg 655.70

Concrete neutralizer gal 429.45

Putty Knife pc 25.00

Roller paint # 9 w/ tray pc 150.00

2″paint brush pc 35.00

Putty Knife pc 25.00

Paint thinner gal 280.00

Sand paper #120 dozen 120.00


For reference, 20 sq.m normally consumes a gallon of paint. All amount in Php.

Reinforced Concrete Pipe Prices

RCP 1200mm x 1m pc 4,116.00

24 | P a g e
RCP 910mm x 1m pc 2,860.00

RCP 750mm x 1m pc 1,607.00

RCP 600mm x 1m pc 1,250.00

RCP 450mm x 1m pc 803.00

RCP 375mm x 1m pc 714.00

RCP 300mm x 1m pc 625.00

Ready Mixed Concrete Prices

Ready Mixed Concrete 3000psi @ 28 Days cu.m 4,503.00

Ready Mixed Concrete 3000psi @ 14 Days cu.m 4,766.00

Ready Mixed Concrete 3000psi @ 7 Days cu.m 4,911.00

Ready Mixed Concrete 3500psi @ 28 Days cu.m 4,754.00

Ready Mixed Concrete 3500psi @ 14 Days cu.m 4,948.00

Ready Mixed Concrete 3500psi @ 7 Days cu.m 5,244.00

Ready Mixed Concrete 4000psi @ 28 Days cu.m 5,151.00

Ready Mixed Concrete 4000psi @ 14 Days cu.m 5,347.00

Ready Mixed Concrete 5000psi @ 28 Days cu.m 5,707.00


These are just average prices. All amount in Php. Normally, RMC and RCP suppliers give clients
huge discounts (10-20% off) if bought in bulk. I am listing down all suppliers list and hope to
share them here in a bit.

Slope Stabilization Mesh System

Description Unit Price (Php)

3mm Ø High Tensile Wire mesh (3.5x30mm) sq.m 6,992.00

10mm Ø Tensile Rope Anchor ln.m 1,012.00

4mm Ø High Tensile Wire Clips pc 138.00

10mm Ø Tensile Wire Rope Anchor pc 4,600.00

Anchor Bolt (32mmØ x 2.5m) pc 966.00

Threading of Bolts w/ nuts pc 1,288.00

Non-Shrink Grout bags 552.00

25 | P a g e
Centralizer pc 230.00

Drill Bit pc 18,400.00

Centrosema Seeds kgs. 294.40

Enzyme ltrs. 13.80

3D Geonet sq.m 598.00

Truss Works

Item Name Unit Price

6mm thk.x 65mm x 65mm x 6.0 Angle bar(T & B Chord) pc 2,248.70

6mm thk. x 50mm x 50mm x 6.0 Angle bar(Web Member) pc 1,704.66

10mm thk. Gusset plate welded to truss sq.m. 4,245.52

150mm x 65mm x 20mm x 2mm LC-Purlins pcs. 1,089.00

255mm x 90mm x 25mm x 5mm thk. LC- Channel beam pcs. 4,057.57

300mmx12mm dia. Plain Bar w/ standard nuts & washers @ both


ends: Sagrod pcs. 74.12

350mmx12mm dia. Plain Bar w/ standard nuts & washers @ both


ends: Sagrod pcs. 76.74

380mmx12mm dia. Plain Bar w/ standard nuts & washers @ both


ends: Sagrod pcs. 78.31

465mmx12mm dia. Plain Bar w/ standard nuts & washers @ both


ends: Sagrod pcs. 82.76

550mmx12mm dia. Plain Bar w/ standard nuts & washers @ both


ends: Sagrod pcs. 87.22

12mm. Thk. Buckle Plate sq.m. 5,100.44

16mm dia. Plain Bar cross bracing pc. 419.10

16 mm dia. Turn buckle pc. 137.50

12mm x 250mm x 300mm Base Plate sq.m. 5,100.44

100 x 100 x 6mm thk. Angular base plate pc. 1,880.00

50 x 50 x 5mm Angular Bar pc. 1,392.12

75 x 75 x 6mm x 130mm Clip Angle to Purlins pc. 2,611.40

26 | P a g e
Welding Rod (Fuji) box 2,330.00

Oxygen(content only) tank 1,575.00

Acetylene(content only) tank 2,000.00

Hacksaw Blade pc. 65.00

Paint brush # 4 pc. 65.00

Paint brush # 2 pc. 35.00

Red Lead Primer gal. 429.45

Paint Thiner gal. 551.25

Construction Heavy Equipment and Engineering Survey Equipment Price List

Description Unit Price

Amphibious Excavator Unit 15,800,000.00

Backhoe Payloader Unit 4,800,000.00

Crack Sealing Applicator, Walk Behind Unit 390,000.00

Cutter Suction Dredge and Support Vessel Unit 300,000,000.00

Dump Truck, 210 Hp, 5.5 cu.m Unit 3,450,000.00

Dump Truck, 150 Ps, 3 cu.m Unit 2,700,000.00

High side Pick-Up with Roof (HSPUR) Unit 920,000.00

Hydraulic Excavator Unit 5,900,000.00

Kneading Machine Unit 960,000.00

Multi-Purpose Amphibious Dredge Unit 37,500,000.00

Multi-Purpose Amphibious Dredge, 10 Unit 41,500,000.00

Multi-purpose Cutter Suction Dredge Unit 54,700,000.00

Pavement Marking Remover Unit 1,180,000.00

Prime Mover, 400 Hp Unit 4,750,000.00

Road Patcher Unit 4,300,000.00

Stake Truck, 210 Hp Unit 3,100,000.00

Vibratory Roller, 15 Hp, 1500 Kgs Unit 1,400,000.00

27 | P a g e
Wheel Loader, 110 Hp, 1.7 cu.m Unit 2,500,000.00

Digital Level Unit 110,000.00

Handheld Global Positioning System (GPS) Unit 44,000.00

Total Station Unit 460,000.00

Plumbing and Sanitary Works

Sanitary Lines Unit Price

100mm dia. PVC pc 753.50

75mm dia. PVC pc 485.00

50mm dia PVC (vp & wp) pc 330.00

PVC Clean Out w/ plug & sealing ring 100mm pc 95.00

PVC Clean Out w/ plug & sealing ring 150mm pc 114.00

PVC P-Trap w/ plug & sealing ring 50mm pc 66.00

PVC Te (150mm) pc 95.00

PVC Tee (100mm) pc 95.00

PVC WYE (100mm) pc 95.00

PVC WYE REDUCER (100mmX50mm) pc 85.00

PVC WYE REDUCER (100mmX75mm) pc 95.00

PVC ELBOW 90° (100mm) pc 95.00

PVC ELBOW 90° (75mm) pc 85.00

PVC Elbow 90° (50mm) pc 66.00

PVC Elbow 45° (100mm) pc 95.00

PVC Elbow 45° (75mm) pc 85.00

PVC Elbow 45° (50mm) pc 66.00

PVC Coupling (100mm) pc 95.00

Vulca Seal pc 440.00

Cold Water Lines Unit Price

20mmØ Polypropylene, Type 3, PN20 pc. 250.00

28 | P a g e
20mmØ Coupling pc. 95.00

20mmØ Tee pc. 95.00

20mmØ Elbow pc. 95.00

Teflon Tape roll 27.50

PLUMBING & EQUIPMENT (Swimming Pool Accessories)

Description Unit Qty Materials Labor Other Total (Php)

Supply and
install
valves,
pipings,
fittings and
other items
as
necessary Lot 1.00 103,700.00 31,110.00 37,746.80 172,556.80

Centrifugal
pump/motor
2HP, 230v Item 1.00 41,480.00 3,050.00 12,468.40 56,998.40

Sand Filter
360T2 w/
Multiport
Valve Item 1.00 73,200.00 3,050.00 21,350.00 97,600.00

Maindrain
Cover Item 1.00 1,830.00 366.00 614.88 2,810.88

Vacum
Fittings Item 2.00 732.00 1,830.00 717.36 6,558.72

Return
Fittings Item 4.00 732.00 152.50 247.66 4,528.64

Vacuum
cleaning set Item 2.00 18,300.00 1,830.00 5,636.40 51,532.80

Hydrostatic
relief valve Item 1.00 1,708.00 366.00 580.72 2,654.72

395,240.96

ELECTRICAL & UNDERWATER LIGHTS

Description Unit Qty Materials Labor Other Total (Php)

29 | P a g e
Underwater
Light 12v Item 8.00 17,080.00 1,464.00 5,192.32 189,890.56

Mounting
Ring Item 8.00 1,708.00 512.40 621.71 22,736.90

Deck Box Item 6.00 1,098.00 244.00 375.76 10,306.56

Transformer
300w / 12-
16 v Item 4.00 3,660.00 610.00 1,195.60 21,862.40

Conduits
3/4″
diameter lot 1.00 18,300.00 5,490.00 6,661.20 30,451.20

#10 Wire lot 1.00 36,600.00 10,980.00 13,322.40 60,902.40

Panel Board Item 1.00 18,300.00 1,830.00 5,636.40 25,766.40

Magnetic
Switch Item 1.00 3,904.00 610.00 1,263.92 5,777.92

Push Botton
Switches Item 4.00 610.00 146.40 211.79 3,872.77

371,567.10

OTHER WORKS

Description Unit Qty Materials Labor Other Total (Php)

Construction of
balancing tank Item 1.00 140,300.00 42,090.00 51,069.20 233,459.20

Construction of
filtration room Item 1.00 140,300.00 42,090.00 51,069.20 233,459.20

Supply of
water line from
sourec to pump
room using
PVC pipes item 1.00 21,960.00 6,588.00 7,993.44 36,541.44

Supply of
power from
source to pump
room. Tapping
not included item 1.00 30,500.00 – – 30,500.00

Testing &
Commissioning item 1.00 18,300.00 5,490.00 6,661.20 30,451.20

30 | P a g e
One month
maintenance item 1.00 12,200.00 6,100.00 5,124.00 23,424.00

587,835.04