Вы находитесь на странице: 1из 5

Preliminary Design Information

Before starting the water system design, you must assemble


a collection of information. This includes information from
the owner, the local utility, and the architect. Things to
consider in developing this design information include:
• Utility information, such as contact information;
requirements for the meter location (most utilities
require the meter at the property line); requirements
for backflow preventer locations (inside or outside,
at the water meter); submittal requirements for
permitting (some jurisdictions have special fixture-
counting methodologies not included in the model
plumbing codes); and special requirements of the
local utilities (For example, the City of Houston will
not allow direct pump suction from the city water
mains, so you must have a break tank.)
• Water supply flow test
• Applicable plumbing codes, especially local amend-
ments to national or state model codes
• First pass at equipment needs and space require-
ments (While this is only a portion of the entire
plumbing design, the elements included in the water
design are water booster pumps and water heaters.)
A word of caution: If you are working in a new jurisdic-
tion, do not assume that the rules are the same as your
home territory. While I started the bulk of my plumbing
design portfolio in Florida, I designed a project in Ohio,
where for some reason the architect had not provided
the lavatories in the accessible water closet stalls. It was
rather embarrassing when the architect told me that the
Americans with Disabilities Act (ADA) does not require
them. It turns out that Florida has its own ADA rules that
are more stringent than the federal version. (I hate it when
the authority having jurisdiction has to educate me on the
local codes!)

O
ne of the fundamental design elements that every Is a Water Booster Pump Needed?
plumbing engineer faces is the design of domestic To determine whether a water booster pump is required,
water systems. Water is used in just about every the following information is used:
building of every type, and it is necessary for the plumbing • The minimum required water pressure typically is 20
engineer to be able to design and lay out a water system to pounds per square inch gauge (psig) if flush valves are
be as efficient as possible in these days of lower fees and used and 10 psig otherwise. For healthcare, laboratory,
more demand from clients. or industrial projects, you may have equipment that has
This article outlines a methodology plumbing engineers higher minimum pressure requirements.
can use to design an efficient domestic water system. It walks • The elevation difference between the elevation of the
through the design process for a relatively large, multistory water supply flow test and the highest fixture in the
building, which will allow readers to look at all elements of building must be determined. You typically do not have
the design of a domestic water system with the knowledge to worry about hose bibbs in mechanical penthouses.
that smaller projects will not need to address every issue. It is The elevation difference in feet multiplied by 0.454 gives
up to the designer to audit the steps presented for each spe- the pressure drop in psi.
cific type of project. Please note that the scope of this article • The longest run of piping in the building, including fit-
does not allow great depth on the design of water-heating tings, must be determined. This typically is figured at
systems or water booster pump systems. Designers should this stage in the design process by adding the height,
review ASPE design manuals, such as Domestic Water Heat- width, and length of the building and multiplying by 1.5.
ing Design Manual II or the Plumbing Engineering Design • Assume a pressure drop of 1.5 feet per 100 feet (approxi-
Handbooks, for further information on those topics. mately 0.7 psi per 100 feet).

30  Plumbing Systems & Design  SEPTEMBER 2010 WWW.PSDMAGAZINE.ORG


If the sum of the minimum pressure, elevation, and ute water on each floor, and individual branch lines to
friction exceeds the water supply pressure, then a water each toilet room and/or fixture. Shutoff valves should be
booster pump is required. provided for each riser, floor, and toilet room. Normally,
As an example, let’s look at a three-story building, 200 shutoff valves are not included for branch lines serving an
feet long by 100 feet wide by 45 feet tall, with flush valve toi- individual fixture unless the owner has a requirement for
lets and no major equipment. Assuming that the fixtures on such. Since every fixture must have a stop, eliminating the
the top floor are 3 feet above the floor slab, the calculated shutoff valves for single fixture branches can save money,
data is: since most repair or maintenance can be performed with
• Flush valves = 20 psig the stop in lieu of a shutoff valve.
• Elevation difference = 33 feet x 0.454 = 15 psig In today’s design practice, the piping serving a floor
• Pressure drop = (200 feet + 100 feet + 45 feet) x 1.5 = generally is located in the ceiling cavity for that floor. This
517.5 feet x (0.7 psi/100 feet) = 3.6 psig is the simplest layout in terms of minimizing installa-
Thus, the minimum supply pressure is: tion costs and allowing efficient access to shutoff valves. I
20 psig + 15 psig + 3.6 psig = 38.6 psig believe that making maintenance personnel find a valve on
If the water supply flow test does not indicate a residual a different floor in an emergency situation creates potential
pressure of at least 38.6 psig, a water booster pump will trouble for everyone. For example, it has been common
be required. Please note that a safety factor has not been practice in Veterans Health Administration hospitals to
included in this calculation. The designer must pay special locate the DCW and DHW piping in the ceiling of the floor
attention to the friction losses in pipe sizing to determine below the fixture location. While this does allow slightly
an appropriate factor. A safe practice is to add a 10 percent less piping to be used and allows a completely drainable
factor to the minimum. system, every time the water needs to be shut off, mainte-
Some owners prefer water booster pumps to serve only nance has to find the valves on the floor below.
the portions of the building that are higher than the pres- Other design philosophies that have been utilized in the
sure limits of the water service. This can save some operat- past include branch piping on every other floor, with each
ing costs for the pumps, but it also leads to problems with horizontal distribution system serving one floor up and
coordinating water heating. Do you provide two domestic one floor down. This can reduce installation costs, but two
hot water (DHW) systems or attempt to limit pressures to floors must be shut down if major maintenance or renova-
match the domestic cold water (DCW) system? If you are tions are performed.
asked to do this, make sure you carefully examine the pres- A vertical distribution concept makes more sense in
sures in the systems. some projects, such as any type of project that has stacked
toilet rooms as with many hotels and prisons. Using verti-
Locating Water Heaters cal branches for these projects keeps all of the plumbing in
For the purposes of this article, the discussion of water vertical stacks and makes the building more efficient.
heaters will be limited to where to locate them. To avoid the In any case, the primary criterion for selecting a location
potential for large differences in water pressure between for risers, mains, and branches is to minimize the cost of
the hot and cold water systems, it is preferable to locate the the piping installation.
water heaters as close to the service entrance as possible. I
have provided design services for a hospital that requires Pipe Sizing
a check valve in every faucet that does not have an integral Once all of the distribution piping has been laid out, it is
check stop. Due to portions of the building having a 10- to time to start sizing the piping. The following approach to
20-psig difference in pressure between the DHW and DCW sizing piping is based on Hunter’s curve and the fixture
systems, faucets that do not have check valves can allow units included in the various plumbing codes. (Refer to
the hot water to cross over to the DCW system. Tables 1 through 4 for supporting information.)
The fixture units in Table 1 are from the Florida Plumb-
Piping Distribution ing Code. The flow rates are based on the fixture unit to gal-
Once the preliminary design information has been gathered lons per minute (gpm) tables also included in the Florida
and the architect has provided base sheets, you can start Plumbing Code. This information is similar, if not the same,
the layout and design of the systems. The design of the water to the information provided in the International Plumbing
systems should start at the service entrance and proceed to Code, Uniform Plumbing Code, and various state-level
the individual fixtures in the building. Of great importance plumbing codes that are in place around the country.
in the early part of the design is to determine how often and Notice that this spreadsheet has three sections for different
where vertical distribution will be located. types of information. The top section is the water supply flow
For the most part, it is recommended that you use information and the limits for the various calculations for
a layout using primarily horizontal distribution. This pressures and velocities. The middle section calculates the
layout will consist of vertical risers from the water service total number of fixture units. The bottom section includes
entrance to the highest floor, horizontal mains to distrib- adjustments to the available pressure at the entrance.

SEPTEMBER 2010  Plumbing Systems & Design  31


Domestic Water 101

To summarize the process, the specific steps used for flow rate, you don’t need to worry about whether they are
sizing piping are as follows: using hot or cold water.
1. Using the amount of piping in the longest run and the
water supply flow information, the maximum allow- Backflow Preventers
able pressure drop can be determined. This value will Unless you have a break tank in your system, the local util-
be based on the difference between the water supply ity may insist on a reduced-pressure backflow preventer
pressure and the minimum pressure at the fixtures. If (RPBP) on the water service to the building. Even if you are
a water booster pump is used, the available pressure on a campus area that provides a master RPBP to protect
is set at 55 psi, assuming a 75-psig discharge from the the utility, you still should have a building-level RPBP so
booster pump and a minimum of 20 psig at the fixture. that one building does not compromise the campus system.
(Refer to Table 1.) Further, if at all possible, the RPBP should be installed out-
2. For DHW systems, the maximum flow rate is set at 6 feet side or at least in a mechanical room that is above grade.
per second (fps) for most pipe materials, and the flow RPBP vent sections are designed to flow full under some
information for systems with flush tanks is used. (As types of failure conditions. Figure 2 indicates how much
an aside, it is recognized that according to the Copper water can flow from this vent. As you can see, a 6-inch RPBP
Development Association, velocities for hot water installed in a basement level mechanical room with a 50-gpm
piping should not exceed 5 fps. However, based on the sump pump will not work. I speak from personal observation!
DHW system not being a steady flow system and the
actual flow rates based on Hunter’s curve being high Type of Building
with low-flow fixtures, I never have had a problem with Most buildings can be sized safely based on the fixture
erosion in a DHW system sized for 6-fps maximum units and Hunter’s curve flow rates in the plumbing codes.
velocity.) If the maximum allowable pressure drop does However, especially for buildings with large assembly
not allow for a velocity of 6 fps, the limit based on pres- occupancies, you will have to increase the pipe sizes to
sure drop is used. (Refer to Table 4.) get everything to work. For example, when the Tennessee
3. For DCW systems serving group toilets, the volume of Titans opened their new stadium in Nashville, the DCW
water is based on only the maximum flow rate limit of system was designed for all the flush valves in the facility to
8 fps. For the most part, you are not worried about the be actuated at the same time. If there was enough system
pressure drop in the short runs of pipe that make up a pressure to close the diaphragms, the system would work.
toilet room. (Refer to Table 2.) They even brought in the local Boy Scouts and other volun-
4. For the main DCW distribution system, the maxi- teers to test the system. The same can be true for theaters,
mum flow rate is set at 8 fps, and the resultant flow conference centers, and large auditoriums. On the other
is compared to the flow rate based on the maximum end of the scale are building such as hospitals where most
allowable pressure drop. Usually, the maximum pres- rooms have a bathroom. In that case, using Hunter’s curve
sure drop will be the limiting factor in the smaller will drastically oversize the piping system unless you figure
pipe sizes, while the maximum flow rate will be the everything as “private” use.
limiting factor in the larger pipe sizes. The breakpoint
is determined by the actual allowable pressure drop. Temperature Maintenance
(Refer to Table 3.) If a recirculation system is used, the layout of the hot
5. You should walk through the entire building and cal- water system must include circulation legs for any branch
culate the number of fixture units on each section of that exceeds 100 feet in length. In reality, especially for
piping. Refer to Figure 1 for a sample of this method. In branches that serve only public lavatories, the minimum
Figure 1, the blue numbers represent the DCW system branch lengths really need to be evaluated.
fixture units, and the red numbers are the fixture units Further, I recommend using a minimum pipe size of ⅜
for the DHW system. inch in lieu of ½ inch as is normally used. The reasoning for
6. This fixture unit value then is compared to the appro- this change is apparent by looking at the velocity of water in
priate Table (2, 3, or 4) to determine the size of that the various pipe sizes. Table 5 provides some comparison
section of piping. information for ⅜-inch and ½-inch piping.
It is advised to keep your markup drawing as part of your For a lavatory with a maximum flow rate of 0.5 gpm, this
project notebook just in case you have to verify or defend results in a velocity of 44 feet per minute in ½-inch pipe and
your sizing in the future. 76 feet per minute in ⅜-inch pipe. Thus, if you want water
to get to the fixture in a reasonable time, the smaller pipe
Things to Think About is the better choice. Further, using a maximum of 6 fps for
Water Service Sizing hot water systems, a ⅜-inch pipe can carry 3.2 gpm while
The water service should be sized using the total water a ½-inch pipe can carry 5.6 gpm. This means that without
column indicated in Table 1. This value accommodates the diversity, a ⅜-inch pipe could serve seven lavatories while a
fact that while faucets and shower valves have a maximum ½-inch pipe could serve 11 lavatories.

32  Plumbing Systems & Design  SEPTEMBER 2010 WWW.PSDMAGAZINE.ORG


Domestic Water 101

Table 1 Tabulation of fixture units (FU) for a sample project Table 4 DHW sizing
Available Pressure (psi) Maximum Water Velocities (fps) Pipe Flow at
Pipe ID Maximum Maximum FU,
Static 73 Cold water 8 Size Maximum
(in.) Velocity (fps) Flush Tank
Residual 67 Hot water 6 (in.) Velocity (gpm)
Flow rate 1,574 /8
3
0.43 6.00 2.72 1
½ 0.527 6.00 4.08 4
Required pressure: 25 psi Highest elevation: 37 feet ¾ 0.785 6.00 9.05 12
1 1.025 6.00 15.43 21
Hot Water Cold Water Total Water 1¼ 1.265 6.00 23.50 36
Description Number FU Total FU Total FU Total 1½ 1.505 6.00 33.27 60
EWC 5 0 0 0.25 1.25 0.25 1.25 2 1.985 6.00 57.87 160
Lavatory, public 35 1.5 52.5 1.5 52.5 2 70 2½ 2.465 6.00 89.24 321
Sink 11 1.5 16.5 1.5 16.5 2 22 3 2.945 6.00 127.38 517
Shower, public 44 3 132 3 132 4 176 4 3.905 6.00 223.96 1,116
Service receptor 4 2.25 9 2.25 9 3 12
Water closet, valve, public 39 0 0 10 390 10 390 Table 5 Piping comparison
Floor totals (FU) 210 601.25 671.25 3
/8-inch Pipe ½-inch Pipe
Flow rate (gpm) 67 155 165 Inside diameter (inches) 0.402 0.529
Supply pressure @ flow 72.90
Volume of 1 foot of pipe (gallons) 0.0066 0.0114
Length of pipe for 0.5 gallon (feet) 75.8 43.8
Corrections
Elevation 17 Capacity of pipe at 6 fps (gpm) 3.2 5.6
Site piping (ft) 150 0.13 Number of public lavatories at 0.5
6 11
Inside diameter (in.) 6 gpm, undiversified
C value 150
Water meter 6
Backflow preventer 11
Fixture minimum 20
Available pressure 18.77
Longest pipe run – Pipe + Fittings (equivalent length) 100 ft

Table 2 Bathroom group DCW sizing

Pipe Size Pipe ID Maximum Flow at Maximum Maximum FU, Maximum FU,
(in.) (in.) Velocity (fps) Velocity (gpm) Flush Valve Flush Tank

/8 3
0.43 8.00 3.62 0 3
½ 0.545 8.00 5.82 0 6
¾ 0.785 8.00 12.07 0 16
1 1.025 8.00 20.57 0 30
1¼ 1.265 8.00 31.34 14 56
1½ 1.505 8.00 44.36 35 103
2 1.985 8.00 77.16 136 259
2½ 2.465 8.00 118.99 351 470
3 2.945 8.00 169.84 694 743
4 3.905 8.00 298.62 1,738 1,738

Table 3 DCW main sizing

Pipe Size Pipe ID Allowable Allowable Velocity Maximum Flow at Maximum Maximum FU, Maximum FU,
(in.) (in.) Loss (psi) Flow (gpm) (fps) Velocity (fps) Velocity (gpm) Flush Valve Flush Tank

/8
3
0.43 0.188 2.91 6.44 8.00 3.62 0 1
½ 0.545 0.188 5.44 7.48 8.00 5.82 0 6
¾ 0.785 0.188 14.20 9.42 8.00 12.07 0 16
1 1.025 0.188 28.66 11.14 8.00 20.57 0 30
1¼ 1.265 0.188 49.87 12.73 8.00 31.34 14 56
1½ 1.505 0.188 78.78 14.21 8.00 44.36 35 103
2 1.985 0.188 163.25 16.93 8.00 77.16 136 259
2½ 2.465 0.188 288.69 19.41 8.00 118.99 351 470
3 2.945 0.188 461.12 21.72 8.00 169.84 694 743
4 3.905 0.188 969.08 25.96 8.00 298.62 1,738 1,738

SEPTEMBER 2010  Plumbing Systems & Design  33


Domestic Water 101

There is so much more that can be talked about in the


design of domestic water systems. We haven’t touched the
principles behind proper backflow prevention based on the
hazard classification or the impact of laboratory or medi-
cal equipment on water systems. Maybe in a future article.
I often have been told that plumbing design is an art, not a
science.

Raymond F. Parham, PE, is a plumbing/fire protection


engineer with Moses & Associates. He has more than 25 years
of experience in mechanical design and building construction
and has been a registered Professional Mechanical Engineer
since 1986 and a registered Fire Protection Engineer since
1999. For more information or to comment on this article,
e-mail articles@psdmagazine.org.

Figure 2 Maximum water flow from reduced-pressure backflow preventer vents


Source: Watts Regulator Co.

Figure 1 Sample layout with fixture units

34  Plumbing Systems & Design  SEPTEMBER 2010 WWW.PSDMAGAZINE.ORG

Вам также может понравиться