ROUTINE TEST PLAN

Customer: CÔNG TY CỔ PHẦN TẬP ĐOÀN TOJI


Project: TỦ MÁY CẮT HỢP BỘ 24KV - GÓI THẦU 17TBT-G36
Substation: TRẠM 110KV ĐỒN PHÓ

Table of Contents
1. ROUTINE TEST …………………………………………………………………………….. 2

1.1 PURPOSE ………………………………………………………………………………. 2


1.2 OBJECTIVE……………………………………………………………………………… 2
1.3 GENERAL RULES……………………………………………………………………… 2
2. ROUTINE TEST PLAN …………………………………………………………………….. 2

2.1 VISUAL INSPECTION………………………………………………………………….. 2


2.2 DIELECTRIC TESTS ON THE MAIN CIRCUIT……………………………………… 3
2.3 TESTS FOR VOLTAGE PRESENCE INDICATION………………………………… 3
2.4 TESTS ON THE AUXILIARY AND CONTROL CIRCUITS ………………………… 4
2.4.1 Inspection of auxiliary and control circuits and verification of conformity to the
circuit and wiring diagrams …………………………………………………… 4
2.4.2 Functional tests………………………………………………………………… 4
2.4.3 Dielectric test……………………………………………………………………. 4

2.5 MEASUREMENT OF THE RESISTANCE OF THE MAIN CIRCUIT (BY PASS CTs) 4
2.6 CURRENT TRANSFORMER PRIMARY INJECTION TESTING………………….. 5
2.7 MECHANICAL OPERATION TESTS………………..………………………………… 5

3. CUBICLE INSPECTION…………………………………………………………………… 5
4. TESTING TOOLS…………………………………………………………………………… 7
5. APPENDIX…………………………………………………………………………………… 8

1
1. ROUTINE TEST
1.1 PURPOSE: The purpose of this instruction is to define the methods used in performing Factory
Acceptance Test on medium voltage electrical switchgear.
1.2 OBJECTIVE: To verify that the products manufactured conform to the requirements specified in
IEC 62271-200 and IEC 60694.
1.3 GENERAL RULES
- The objective is to verify the general operation of the product after assembly and in-line
inspection of an assembly or sub-assembly.
- The in-line inspection points are to be defined by the partner according to their process
- The test reports and values to be recorded and retained are specified in the traceability
requirements.

2. ROUTINE TEST PLAN

2.1 VISUAL INSPECTION: Before commencement of routine testing, the equipment fitted to the cubicles
should be checked against the requirements of the specifications, data sheets and drawings.

Typical checks should include:

- Overall size of panels


- CT ratios and class
- Instrument and meter scales
- Protection relays types and configurations
- Label designations
- Auxiliary voltages
- Painting color

2
2.2 DIELECTRIC TESTS ON THE MAIN CIRCUIT

Clause 7.1 of IEC62271-200 refers.

Generally, the following test voltages will apply:

Rated Voltage Rated short-duration power frequency


withstand voltage
Ud
Ur
kV (rms value) 1 minute
kV (rms value)
24 50

The high voltage test should be performed:


- On each phase and earth in turn, with all other conductors connected to earth
- The equipment will have successfully passed the tests if at any time during the 1 minute period there
has been no disruptive discharge.
- An Insulation Resistance check (minimum 2.5kV Megger) should be done before and after the
Dielectric Tests to verify that there has been no deterioration of the insulation during the test.
An acceptable insulation resistance figure is 100GΩ or greater for each panel.

2.3 TESTS FOR VOLTAGE PRESENCE INDICATION

Clause 5.2 of IEC61958 refers: This test should be carried out during the HV tests described in Clause 2.2
above to avoid repeated HV tests on the equipment insulation.
Phase concurrence between main conductors and the VPIS should also be checked at this time.

The indication corresponding to “voltage present”


shall appear shall not appear
when the actual line-to-earth when the actual line-to-earth
voltage is between 45% of the voltage is less than 10% of the
in three phase systems
nominal voltage and the rated nominal voltage
voltage
VPIS V>8.1kV V<2.5kV
Unmin 10kV Unmax 24kV

Note: VPIS…..Voltage Presence Indicating System

3
2.4 TESTS ON THE AUXILIARY AND CONTROL CIRCUITS

Clause 7.2 of IEC62217-200 refers.

2.4.1 Inspection of auxiliary and control circuits and verification of conformity to the circuit
and wiring diagrams

- A visual inspection of all actuators, interlocks etc should be made.


- Components shall be checked for correct mounting.
- Checks shall be made to ensure that there is sufficient space for external wiring to be
accommodated, fitted and terminated
- Wiring shall be checked for correct routing, support and protection from mechanical
damage
- Identification of all devices, terminals and wires shall be checked against the diagrams
2.4.2 Functional tests: Functional tests of all low voltage circuits shall be made to verify the
correct functioning of auxiliary and control circuits in conjunction with the other parts of the
equipment.

- Each line of the schematic diagram must be function checked to ensure correct wiring has
been carried out during production phase.
- These tests should be carried out at the upper and lower values of the supply voltage.

2.4.3 Dielectric test: The test voltage will be 2kV/ 1minute AC 50Hz.

- Test: between the auxiliary and control circuits connected together, as a whole, and the
frame of the cubicle.
- The equipment will have successfully passed the tests if at any time during the 1minute
period there has been no disruptive discharge.

2.5 MEASUREMENT OF THE RESISTANCE OF THE MAIN CIRCUIT (BY PASS CTs)

Clause 7.3 of IEC62271-200 refers.

The complete cubicle with circuit breaker closed should be subject to resistance check with a 100A DC test set.
Typical maximum values as below:

mV drop
NEX24 cubicles with EVOLIS CB micro-ohm
Busbar riser to cable flag 100A DC
630A – 1250A <120 <12
2000 <60 <6

4
2.6 CURRENT TRANSFORMER PRIMARY INJECTION TESTING

Current transformer primary injection tests are performed in order to ensure that the correct CTs have been
fitted, that no damage has occurred to these during assembly, and to confirm that all the secondary
wiring has been correctly installed and terminated
The current transformers are each tested at 100% of rated primary current and to verify:
- Polarity
- Secondary current

2.7 MECHANICAL OPERATION TESTS

Clause 7.102 of IEC62271-200 refers.


In addition, the following checks should be made to verify the correct operation of interlocks and
equipment.

3. CUBICLE INSPECTION

FUNCTION AIM OF TEST ACTION RESULT OF TEST


Plug in the CB Closing of earthswitch
impossible. Impossible to
turn the earth switch selector.
Earth switch operating hole
To guarantee covered
Earthing switch /CB circuit earthed during CB unplugged, selector in Closing of earthswitch
Interlocking- maintenance and ensure racking position impossible. Impossible to
Operation-Indication that the CB is unplugged. turn the earthswitch selector.
Earthswitch operating hole
covered
CB unplugged, selector in Closing of the earthswitch
test position possible. Subsequently, CB
Racking handle hole covered,
impossible to rack in CB
Open/Close To guarantee opening and Open and close the Verify position of the knife
Earthswitch closing of the earthswitch earthswitch with low switches, earthswitch closed
operating torque.

Earthswitch To check position of Earthswitch open →


mechanical earthswitch Open symbol
indicaton Earthswitch closed→
Closed symbol
To check CB is indexed to CB unplugged Verify position of locking pins
the cubicle Turn racking selector visually.
from isolated position Closing of CB and earthswitch
to racking position. impossible.
Impossible to move earthswitch
Indexing of CB selector to operating position.
CB red pushbutton depressed
CB unplugged. Verify position of locking pins
Turn racking selector visually.
from racking position PAF contact closes.
to test position. Possible to close CB.
To prohibit extraction of a CB is closed, attempt to Impossible to move selector to
closed CB move the selector from racking position unless CB is

5
service position to racking open
Interlocking position. Push red trip
Racking in/racking button.
out To verify it is not possible to Partially rack in the CB. Impossible to move selector.
close the CB unless it is Attempt to move selector Impossible to close the CB
either in the test or service from racking position to
position service or test position

To verify that it is Rack in the CB. Attempt Impossible to close the


impossible to close the to turn the racking earthswitch.
earthswitch with the CB selector to racking Earthswitch selector locked with
racked in and racking position. access hole covered
selector in racking position Attempt to close the
Earthswitch or service position earthswitch
To verify that it is not With CB in the racked out Impossible to put handle into
possible to rack in the CB position, close the racking access hole.
with the earthswitch closed earthswitch. Attempt to Impossible to rack in
rack in the CB.

To verify that it is not Attempt to move the Impossible to move selector


possible to rack in the CB selector from isolated from isolated to racking position.
LV plug unless the LV plug is fitted position to racking Impossible to rack in CB
position without the LV
being plug fitted
To verify it is not Open the CB Impossible to rotate the selector
possible to rack in the CB compartment door.
with the door open Attempt to rotate the
selector from isolated to
racking position
Front door interlock To verify it is not CB door closed. Impossible to rotate
possible to open the Selector in racking door handle,
CB compartment door with position or service/test impossible to open
the selector in racking position. Attempt to door
position or test open the CB
position. compartment door
To verify that it is With CB in the racked Impossible to put
impossible to rack in out position, lock the handle into racking
CB racking interlock the withdrawable part interlock. Attempt to access hole.
with the interlock rack in the CB Impossible to rack in
locked
To verify operation of CB unplugged Unplugged contacts
Electrical Indication position indication contacts indicating correctly
of CB position
CB plugged Plugged contacts
indicating correctly
To prohibit fitting of Verify cubicle interlocks
CB rating interlock incorrect CB rating into a match that of the CB of
cubicle the same rating
VT unit VT plugging and Verify operation of
unplugging shutters
Earthswitch open Impossible to remove
front panel

VT front panel VT plugged in or during Impossible to remove


interlock operation. front panel

Front panel removed Plugging in of VT


impossible

6
ELECTRICAL Increase the test
FUNCTIONS voltage until the
“voltage presence” Illumination above
To check correct appears. Record the 45% Unmin
Voltage indication operation of applied line-to earth No-illumination below
potential indicators voltage value. Increase 10%Unmax
the line-to-earth voltage
to the rated voltage.
Decrease the line-toearth
voltage until the voltage
presence disappears.
Record the value
To check tightness
Voltage drop and electrical continuity of Measure resistance of
primary circuit main circuit
50Hz medium To verify integrity of NEX24 -50kV AC
voltage insulation the medium voltage 1minute No disruptive discharge
test insulation.

50Hz low voltage To verify the integrity 2kV AC 1 minute (or 1 No disruptive
insulation test of the secondary wiring and second with customer discharge
equipment. agreement).
To verify conformity Verify transformation ratio
CT and VT of connections and and polarity
transformers fitted
Conformance of
connections to relays,
Verification of To verify the CTs, VTs etc. All devices
schematics electrical functionality Conformance of Function electrically as
of the equipment operation as per designed.
schematic diagrams and
wiring diagrams.

Earth continuity
To verify IP ratings of
CB, LV compartment, VT
Degree of protection compartment, Test finger IP41 external
Bus chamber,
Cable compartment,
Front panels,
shutters

4. TESTING TOOLS:

- Portable AC HIPOT TEST SET 0-50kVAC (PFT-503CMF): dielectric testing for Main Circuit.
- Relay Test Unit (Sverker 750): for protection relay testing.
- Contact resistance meter (CRM 100): for check contact resistance.
- Digital Transformer ratio meter (DTR8510): for current transformer ratio testing.
- High voltage Insulation Tester 0-2500VDC (Kyoritsu 3121B): for check insulation resistance
- AC HIPOT/INSULATION RESISTANCE TESTER 0-2kVAC (AN9632H): dielectric testing for
control circuit.
- Main current Injector
7
5. APPENDIX:
- Form: Factory inspection report
- Form: Witness test report - MV
- Form: Measurement of insulation resistance and Dielectric test records on the Main Circuit
- Form: Current transformer ratio index testing.
- Form: Voltage transformer ratio index testing.
- Form: Multi meter index testing.
- Form: Protective relay test report
- Form: Contact resistance test report