Академический Документы
Профессиональный Документы
Культура Документы
UNIT
Item QTY. UNIT QUOTATION
COST
A. GROUND FLOOR
B. SECOND FLOOR
FLOOR TOPPING 88.76 m2 100.00 8,876.00
STAIR TOPPING 3.10 m2 100.00 309.60
PLASTERING 13.86 m2 100.00 1,386.00
INSTALLATION OF DOORS 6.00 PCS 700.00 4,200.00
CUBICLE DOOR INSTALLATION 3.00 PCS 700.00 2,100.00
INSTALLATION OF FLOOR AND WALL TILES 56.50 m2 150.00 8,475.00
INSTALLATION OF CEILING @ CR 11.50 m2 160.00 1,840.00
CONST. OF COUNTER SINK WITH TILES 2.00 UNITS 1,500.00 3,000.00
CONST. OF URINAL WITH TILES 1.00 UNITS 800.00 800.00
C. THIRD FLOOR
FLOOR TOPPING 88.76 m2 100.00 8,876.00
STAIR TOPPING 15.48 m2 100.00 1,548.00
INSTALLATION OF DOORS 6.00 PCS 700.00 4,200.00
CUBICLE DOOR INSTALLATION 3.00 PCS 700.00 2,100.00
INSTALLATION OF FLOOR AND WALL TILES 36.73 m2 150.00 5,509.50
INSTALLATION OF CEILING @ CR 11.50 m2 160.00 1,840.00
CONST. OF COUNTER SINK WITH TILES 2.00 UNITS 1,500.00 750.00
CONST. OF URINAL WITH TILES 1.00 UNITS 800.00 150.00
D. FOURTH FLOOR
FLOOR TOPPING 209.00 m2 100.00 20,900.00
STAIR TOPPING TO ROOF DECK 9.00 m2 100.00 900.00
INSTALLATION OF DOORS 7.00 PCS 700.00 4,900.00
CUBICLE DOOR INSTALLATION 3.00 PCS 700.00 2,100.00
INSTALLATION OF FLOOR AND WALL TILES 56.50 m2 150.00 8,475.00
CEILING WORKS 60.70 m2 160.00 9,712.00
CONST. OF COUNTER SINK WITH TILES 2.00 UNITS 1,500.00 3,000.00
CONST. OF URINAL WITH TILES 1.00 UNITS 800.00 800.00
PLASTERING
4TH FLOOR 36.70 m2 100.00 3,670.00
ROOF BEAM LEVEL 4.90 m2 100.00 490.00
WALL @ SIDE OF STAIRS TO RD 4.80 m2 100.00 480.00
CHB LAYING 26.90 m2 90.00 2,421.00
E. ADDITIONAL WORKS
DOUBLE HANDLING 1.00 LOT 5,000.00
INSTALLATION/REMOVAL OF SCAFFOLDINGS 1.00 LOT 4,500.00
CLEARING AND DISPOSAL 1.00 LOT 10,000.00
CONSTRUCTION OF ZOCALO ON HALLWAY 1.00 LOT 20,000.00
ALIGNMENT OF FRONT COLUMNS AND BEAMS 6.00 COL. 40,000.00
REPAIR OF CR DOOR JAMBS 3.00 PCS 1,500.00
CHB LAYING BELOW TIE BEAM M2 7,000.00
INSTALLATION OF DRY WALL 1.00 UNIT 2,500.00
F. RETAINING WALL
REBARS 1.00 LOT -
FORMWORK 1.00 LOT 6,615.00
CONCRETE (MANUAL POURING) 1.00 LOT 43,385.00
0% - - -
0% - - -
100% 100% 1,386.00 - 1,386.00
70% 10% 80% 2,940.00 420.00 3,360.00
30% 30% 630.00 - 630.00
90% 90% 7,627.50 - 7,627.50
0% - - -
0% - - -
0% - - - 30,986.60
0% - - -
0% - - -
70% 70% 3,430.00 - 3,430.00
30% 30% 630.00 - 630.00
0% - - -
50% 10% 60% 4,856.00 971.20 5,827.20
0% - - -
0% - - - 50,787.00
0% - - -
50% 50% 2,250.00 - 2,250.00
50% 50% 5,000.00 5,000.00
30% 30% 6,000.00 - 6,000.00
45% 26% 71% 18,000.00 10,400.00 28,400.00
100% 100% 1,500.00 - 1,500.00
100% 100% 7,000.00 - 7,000.00
95% 95% - 2,375.00 2,375.00
90,500.00
0% - - -
40% 10% 50% 2,646.00 661.50 3,307.50
63% 7% 70% 27,332.55 3,036.95 30,369.50 50,000.00
Total 157,023.67
Less: 5 % Retention 7,851.18
PERCENTAGE
UNIT TOTAL
Item QTY. UNIT THIS
COST AMOUNT PREVIOUS
PERIOD
A. WATER PROOFING WORKS -
Second Floor CR (2 units) 25.00 m2 150.00 3,750.00
Third Floor CR (2 units) 25.00 m2 150.00 3,750.00
Fourth Floor CR (2 units) 25.00 m2 150.00 3,750.00
ROOFDECK 9.00 m2 150.00 1,350.00
- m2 - -
CONTRACT AMOUNT 12,600.00 0.00% 0.00%
0.00%
GREEMENT
OFING (CR)
PERCENTAGE AMOUNT
THIS APPROVED
TO DATE PREVIOUS TO DATE
PERIOD AMOUNT
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0.00% - - -
Total 0.00
Less: 5 % Retention 0.00
REQUESTED AMOUNT
Project: CONST. OF 4-STOREY 8CL at INDANG CENTRAL SCHOOL
Location : INDANG, CAVITE
Contractor: RANDY UNO
CONTRACT AGREEMENT
PAINTING WORKS
PERCENTAGE
UNIT TOTAL
Item QTY. UNIT
COST AMOUNT PREVIOUS
A. WALLS
Exterior Walls
Ground Floor 30.60 m2 60.00 1,836.00 40%
Second Floor 20.92 m2 60.00 1,255.20 40%
Third Floor 20.92 m2 60.00 1,255.20 50%
Fourth Floor 21.50 m2 60.00 1,290.00 50%
Roof beam level- A fr 49.00 m2 60.00 2,940.00
Interior Walls -
Ground Floor 56.40 m2 60.00 3,384.00
Second Floor 23.90 m2 60.00 1,434.00
Third Floor 23.90 m2 60.00 1,434.00
Fourth Floor 24.00 m2 60.00 1,440.00
Drywall Partition included m2
Blackboard 76.00 m2 60.00 4,560.00
COLUMNS -
Exterior Columns -
Ground Floor 39.60 m2 60.00 2,376.00 27%
Second Floor 19.50 m2 60.00 1,170.00 27%
Third Floor 19.50 m2 60.00 1,170.00 40%
Fourth Floor 19.50 m2 60.00 1,170.00 40%
Interior Columns -
Ground Floor 17.60 m2 60.00 1,056.00
Second Floor 24.00 m2 60.00 1,440.00
Third Floor 24.00 m2 60.00 1,440.00
Fourth Floor 20.00 m2 60.00 1,200.00
C. BEAMS -
Exterior Beams -
Second Floor 21.20 m2 60.00 1,272.00 20%
Third Floor 21.20 m2 60.00 1,272.00 20%
Fourth Floor 11.20 m2 60.00 672.00 20%
Roof beam level 16.80 m2 60.00 1,008.00
Interior Beams -
Second Floor 15.20 m2 60.00 912.00
Third Floor 15.20 m2 60.00 912.00
Fourth Floor 15.20 m2 60.00 912.00
Roof beam level n/a m2 60.00
D. CEILING -
Concrete Slab soffit -
Ground Floor 9.95 m2 60.00 597.00
Second Floor 9.95 m2 60.00 597.00
Third Floor 9.95 m2 60.00 597.00 100%
Stair soffit 5.40 m2 60.00 324.00
Sunbreaker/wdo cano 58.00 m2 60.00 3,480.00
Hardiflex Ceiling Board -
Ground Floor-cr 12.00 m2 75.00 900.00
Second Floor-cr 11.50 m2 75.00 862.50
Third Floor-cr 11.50 m2 75.00 862.50
Fourth Floor -cr,room 43.70 m2 75.00 3,277.50
Ceiling eaves 85.00 m2 75.00 6,375.00
Ceiling vent n/a pcs
E. DOORS AND WINDOWS -
Panel and flush Doors -
D-1 90 X 210cm-room 64.00 m2 75.00 4,800.00
D-2 80 x 210cm - cr d 4.00 m2 75.00 300.00
D-3 70 x 210cm - stor 32.00 m2 75.00 2,400.00
D-4 60 x 120cm - cr cu 16.00 m2 75.00 1,200.00
D-5 90 x 210cm - pwd 4.00 m2 75.00 300.00
Door jamb -
D-1 90 X 240cm-room 42.40 l.m. 40.00 1,696.00 72%
D-2 80 x 210cm - cr d 5.00 l.m. 40.00 200.00
D-3 70 x 210cm - stor 40.00 l.m. 40.00 1,600.00
D-4 60 x 120cm - cr cu 26.00 l.m. 40.00 1,040.00
D-5 90 x 210cm - pwd 5.00 l.m. 40.00 200.00
Window wooden jamb -
W2-140 x 150cm-roo 16.00 pcs 200.00 3,200.00 90%
W3-635 x 180cm- cr n/a pcs
W4-635 x 60cm- cr 12.00 pcs 100.00 1,200.00
F. STEEL -
Stair and railing -
Ground Floor 39.00 m2 75.00 2,925.00 60%
Second Floor 39.00 m2 75.00 2,925.00 60%
Third Floor 41.00 m2 75.00 3,075.00
Steel wdo & wdo grilles -
W1-170 X 360cm-room 196.00 m2 75.00 14,700.00 90%
W2-170 x 160cm-rooms 16.00 pcs 100.00 1,600.00
PAGE 2/2 (INDANG-FINISHING-PAINTING)
Hallway Pipe Railing
Ground Floor 6.00 pcs 150.00 900.00
Second Floor 6.00 pcs 150.00 900.00
Third Floor 6.00 pcs 150.00 900.00
Fourth Floor 5.00 pcs 150.00 750.00
Flourescent hanger 24.00 pcs 40.00 960.00
Down spout pvc 121.50 l.m. 33.46 4,065.39
Fire pro b.i. pipe ri 13.00 l.m. 40.00 520.00
Water tank stair 1.00 units 1,200.00 1,200.00
Ramp Railing 2.00 units 1,200.00 2,400.00
Fire Exit Stair 125.00 m2 60.00 7,500.00
CONTRACT AMOUNT 120,139.29 10.59%
Checked by:
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0% - - - 20,095.39
2.16% 26.53% 26,483.82 5,389.98 31,873.80 120,139.29
Total 31,873.80
Less: 5 % Retention 1,593.69