CONTRACTOR: SAM LAIN EQUIPMENTS SERVICES PTE LTD DATE: 16 APR 2019
Planned Actual GA
Revision SL Transmittal
Item Drawing Title SL Drawing No. GA Drawing No. submission Submission Respond GA Transmittal No. Status
No No.
Date Date Date
10 May 2019
6 COMPANY PROFILE AND CERTIFICATE OF REGISTERED LAND SURVEYOR SL-TC7-GE-DOC-004 9190112-200-GE-DPR-0006
15 May 2019
9 COMPANY PROFILE OF HOT FORMED BEND SL-TC7-GE-DOC-007 9190112-200-GE-DPR-0009
10 May 2019
10 COMPANY PROFILE FOR BLASTING AND INTERNAL COATING SL-TC7-GE-DOC-008 9190112-200-GE-DPR-0010
1 June 2019
18 NDT PERSONNEL LICENSE AND CERTIFICATES SL-TC7-QA-DOC-003 9190112-200-QA-PRO-0018
14 June 2019
19 PROCEDURE FOR PIPE COLD BENDING SL-TC7-ME-DOC-001 9190112-200-ME-PRO-0019
14 June 2019
20 MANUFACTURING PROCEDURE FOR HOT FORMED BEND SL-TC7-ME-DOC-002 9190112-200-ME-PRO-0020
METHOD STATEMENT FOR HYDROSTATIC TEST TO THE PRODUCTION OF 300MM HOT FORMED TBA
21 SL-TC7-ME-DOC-003 9190112-200-ME-PRO-0021
BENDS
WELDING PROCCEDURE SPECIFICATION - SUBMISSION NO.1 (D > Ø508mm, Pipe/Pipe, Pipe/Fitting, TBA
22 SL-TC7-QA-DOC-004 9190112-200-QA-PRO-0022
and Weld Repair)
WELDING PROCEDURE SPECIFICATION - SUBMISSION NO.2 (Ø60.3mm < D ≤ Ø508mm, Pipe/Pipe, and TBA
23 SL-TC7-QA-DOC-005 9190112-200-QA-PRO-0023
Pipe/Fitting)
TBA
24 WELDING PROCEDURE SPECIFICATION - SUBMISSION NO.3 (D ≤ Ø60.3mm, Pipe/Pipe, and Pipe/Fitting) SL-TC7-QA-DOC-006 9190112-200-QA-PRO-0024
WELDING PROCEDURE SPECIFICATION - SUBMISSION NO.4 (Welding of 3 Way Tee for Hot Tapping TBA
25 SL-TC7-QA-DOC-007 9190112-200-QA-PRO-0025
Operation)
Page 1 of 5
PROJECT TITLE: TERM CONTRACT FOR GAS TRANSMISSION PIPELINES AND FACILITIES PROJECT WORKS
CONTRACT NO: 9190112 REVISION: 0
CONTRACTOR: SAM LAIN EQUIPMENTS SERVICES PTE LTD DATE: 16 APR 2019
Planned Actual GA
Revision SL Transmittal
Item Drawing Title SL Drawing No. GA Drawing No. submission Submission Respond GA Transmittal No. Status
No No.
Date Date Date
TBA
26 WELDING PROCEDURE SPECIFICATION - SUBMISSION NO.5 (Branch Welding) SL-TC7-QA-DOC-008 9190112-200-QA-PRO-0026
TBA
27 WELDING PROCEDURE SPECIFICATION - SUBMISSION NO.6 (Welding for Others) SL-TC7-QA-DOC-009 9190112-200-QA-PRO-0027
TBA
28 QUALIFIED WELDER MATRIX AND QUALIFIED WELDER CERTIFICATES SL-TC7-QA-DOC-010 9190112-200-QA-REP-0028
15 May 2019
29 EXTERNAL PAINTING SPECIFICATIONS FOR ABOVEGROUND PIPELINES SL-TC7-GE-DOC-014 9190112-200-GE-REP-0029
15 May 2019
30 EXTERNAL COATING SPECIFICATIONS FOR UNDERGROUND PIPELINES SL-TC7-GE-DOC-015 9190112-200-GE-REP-0030
15 May 2019
31 COMPANY PROFILE OF PROPOSED MANUFACTURER FOR FORGED FITTINGS SL-TC7-GE-DOC-016 9190112-200-GE-DPR-0031
TBA
32 COMPANY PROFILE OF PIGGING SPECIALIST SL-TC7-GE-DOC-017 9190112-200-GE-DPR-0032
TBA
33 COMPANY PROFILE OF WILLOWGLEN SERVICES PTE LTD SL-TC7-GE-DOC-018 9190112-200-GE-DPR-0033
METHOD STATEMENT AND RISK ASSESSMENT FOR PIPE SHIFTING WORKS AT JALAN LEKAR 25 April 2019
34 SL-TC7-GE-PRO-WOXXX-001 9190112-509-GE-PRO-0034
PIPEYARD(JALAN LEKAR)
8 May 2019
35 METHOD STATEMENT AND RISK ASSESSMENT FOR TRIAL HOLE(LENTOR AVE) SL-TC7-GE-DOC-WOX-001 9190112-501-GE-PRO-0035
3 June 2019
36 METHOD STATEMENT AND RISK ASSESSMENT FOR EXCAVATION AND PIPE LAYING(LENTOR AVE) SL-TC7-ME-DOC-WOX-001 9190112-501-ME-PRO-0036
25 June 2019
37 PROPOSED PIPE ROUTE PLAN FOR LAYING OF GAS TRANSMISSION PIPELINE(LENTOR AVE) SL-TC7-ME-DWG-WOX-002 9190112-501-ME-PLN-0037
METHOD STATEMENT AND RISK ASSESSMENT FOR CONSTRUCTION OF JACKING PIT/RECEIVING 1 July 2019
38 SL-TC7-CI-DOC-WOX-001 9190112-501-CS-PRO-0038
PIT(LENTOR AVE)
METHOD STATEMENT AND RISK ASSESSMENT FOR PIPE JACKING WORKS AND PIPE LAYING 15 July 2019
39 SL-TC7-ME-DWG-WOX-003 9190112-501-ME-PRO-0039
WORK(LENTOR AVE)
10 June 2019
40 ERSS DESIGN FOR OPEN CUT PIPE LAYING(LENTOR AVE) SL-TC7-CI-DOC-WOX-002 9190112-501-CS-CAL-0040
1 July 2019
41 ERSS DESIGN FOR SHAFT CONSTRUCTION(LENTOR AVE) SL-TC7-CI-DOC-WOX-003 9190112-504-CS-CAL-0041
13 May 2019
42 DBC SUBMISSION TO LTA FOR TRIAL TRENCH(LENTOR AVE) SL-TC7-CI-DOC-WOX-004 9190112-504-CS-REP-0042
20 June 2019
43 DBC SUBMISSION TO LTA FOR OPEN CUT PIPE LAYING(LENTOR AVE) SL-TC7-CI-DOC-WOX-005 9190112-504-CS-REP-0043
8 July 2019
44 DBC SUBMISSION TO LTA FOR SHAFT CONTRUCTION(LENTOR AVE) SL-TC7-CI-DOC-WOX-006 9190112-504-CS-REP-0044
METHOD STATEMENT AND RISK ASSESSMENT FOR HYDROSTATIC TEST OF UNDERGROUND 3 February 2020
45 SL-TC7-ME-DOC-WOX-004 9190112-501-ME-PRO-0045
PIPELINE(LENTOR AVE)
TBA
46 GAUGING AND CALIPER PIGGING PROCEDURE(LENTOR AVE) SL-TC7-ME-DOC-WOX-005 9190112-509-ME-PRO-0046
24 April 2020
47 WELDING HISTORY REPORT (LENTOR AVE) SL-TC7-QA-DOC-WOX-001 9190112-501-QA-ITR-0047
24 April 2019
48 PROJECT SCHEDULE (LENTOR AVE) SL-TC7-PM-DOC-WOX-001 9190112-501-PM-SCH-0048
24 April 2020
49 DAILY FIT-UP & WELDING VISUAL INSPECTION REPORT (LENTOR AVE) SL-TC7-QA-DOC-WOX-002 9190112-501-QA-ITR-0049
8 April 2020
50 HYDROSTATIC TEST REPORT(LENTOR AVE) SL-TC7-QA-DOC-WOX-003 9190112-501-QA-ITR-0050
Page 2 of 5
PROJECT TITLE: TERM CONTRACT FOR GAS TRANSMISSION PIPELINES AND FACILITIES PROJECT WORKS
CONTRACT NO: 9190112 REVISION: 0
CONTRACTOR: SAM LAIN EQUIPMENTS SERVICES PTE LTD DATE: 16 APR 2019
Planned Actual GA
Revision SL Transmittal
Item Drawing Title SL Drawing No. GA Drawing No. submission Submission Respond GA Transmittal No. Status
No No.
Date Date Date
24 April 2020
51 NDT INSPECTION REPORTS(LENTOR AVE) SL-TC7-QA-DOC-WOX-004 9190112-501-QA-ITR-0051
24 April 2020
52 FACTORY COATING AND BLASTING REPORT(LENTOR AVE) SL-TC7-QA-DOC-WOX-005 9190112-501-QA-ITR-0052
8 May 2019
53 METHOD STATEMENT AND RISK ASSESSMENT FOR TRIAL HOLE(MITSUI PHENOL) SL-TC7-GE-DOC-WOX-001 9190112-501-GE-PRO-0053
5 August 2019
54 METHOD STATEMENT AND RISK ASSESSMENT FOR EXCAVATION AND PIPE LAYING(MITSUI PHENOL) SL-TC7-ME-DOC-WOXX-001 9190112-501-ME-PRO-0054
Page 3 of 5
PROJECT TITLE: TERM CONTRACT FOR GAS TRANSMISSION PIPELINES AND FACILITIES PROJECT WORKS
CONTRACT NO: 9190112 REVISION: 0
CONTRACTOR: SAM LAIN EQUIPMENTS SERVICES PTE LTD DATE: 16 APR 2019
Planned Actual GA
Revision SL Transmittal
Item Drawing Title SL Drawing No. GA Drawing No. submission Submission Respond GA Transmittal No. Status
No No.
Date Date Date
8 August 2019
55 PROPOSED PIPE ROUTE PLAN FOR LAYING OF GAS TRANSMISSION PIPELINE(MITSUI PHENOL) SL-TC7-ME-DWG-WOXX-002 9190112-501-ME-PLN-0055
15 July 2019
56 ERSS DESIGN FOR OPEN CUT PIPE LAYING(MITSUI PHENOL) SL-TC7-CI-DOC-WOXX-001 9190112-501-CS-CAL-0056
METHOD STATEMENT AND RISK ASSESSMENT FOR HYDROSTATIC TEST OF UNDERGROUND ###
57 SL-TC7-ME-DOC-WOXX-003 9190112-501-ME-PRO-0057
PIPELINE(MITSUI PHENOL)
###
58 WELDING HISTORY REPORT(MITSUI PHENOL) SL-TC7-QA-DOC-WOXX-001 9190112-501-QA-ITR-0058
6 May 2019
59 PROJECT SCHEDULE(MITSUI PHENOL) SL-TC7-PM-DOC-WOXX-001 9190112-501-PM-SCH-0059
###
60 DAILY FIT-UP & WELDING VISUAL INSPECTION REPORT(MITSUI PHENOL) SL-TC7-QA-DOC-WOXX-002 9190112-501-QA-ITR-0060
###
61 HYDROSTATIC TEST REPORT(MITSUI PHENOL) SL-TC7-QA-DOC-WOXX-003 9190112-501-QA-ITR-0061
###
62 NDT INSPECTION REPORTS(MITSUI PHENOL) SL-TC7-QA-DOC-WOXX-004 9190112-501-QA-ITR-0062
###
63 FACTORY COATING AND BLASTING REPORT(MITSUI PHENOL) SL-TC7-QA-DOC-WOXX-005 9190112-501-QA-ITR-0063
30 May 2019
64 MILL CERTIFICATE FOR FITTINGS(MITSUI PHENOL) SL-TC7-QA-DOC-WOXX-006 9190112-501-QA-MTR-0064
6 June 2019
65 P & ID -GAS TRANSMISSION PIPELINE(MITSUI PHENOL) SL-TC7-ME-DWG-WOXX-004 9190112-502-ME-PID-0065
1 October 2019
66 DRAWING AND DESIGN CALCULATION FOR 3-WAY SADDLE TEE(MITSUI PHENOL) SL-TC7-ME-DWG-WOXX-005 9190112-502-ME-CAL-0066
20 May 2019
67 TECHNICAL DATASHEET AND DRAWING FOR BALL VALVE(MITSUI PHENOL) SL-TC7-ME-DWG-WOXX-006 9190112-502-ME-DAS-0067
20 May 2019
68 TECHNICAL PROPOSAL FOR ACTUATOR(MITSUI PHENOL) SL-TC7-IC-DOC-WOXX-001 9190112-504-IC-DAS-0068
1 October 2019
69 TECHNICAL PROPOSAL FOR GATIC ACCESS COVERS(MITSUI PHENOL) SL-TC7-ME-DOC-WOXX-007 9190112-505-ME-PRP-0069
29 July 2019
70 METHOD STATEMENT AND RISK ASSESSMENT FOR VALVE PASSING TEST(MITSUI PHENOL) SL-TC7-ME-DOC-WOXX-008 9190112-505-ME-PRO-0070
Page 4 of 5
LEGEND
PROPOSED LIST OF SUB-CONTRACTORS/SUPPLIERS SL-TC7-GE-DOC-003 9190112-200-GE-LST-0005
SUBMITTED
TO BE SUBMITTED
COMPANY PROFILE AND CERTIFICATE OF REGISTERED LAND SURVEYOR SL-TC7-GE-DOC-004 9190112-200-GE-DPR-0006
NOT RECEIVE
COMPANY PROFILE OF THIRD PARTY INSPECTION AGENCY AND CV OF THIRD PARTY INSPECTOR SL-TC7-GE-DOC-005 9190112-200-GE-DPR-0007
COMPANY PROFILE FOR HOT-TAPPING, LINE STOPPING & PLUGGING SL-TC7-GE-DOC-009 9190112-200-GE-DPR-0011
2 May 2019
NDT PERSONNEL LICENSE AND CERTIFICATES SL-TC7-QA-DOC-003 9190112-200-QA-PRO-0018
6 May 2019
COMPANY PROFILE FOR BLASTING AND INTERNAL COATING SL-TC7-GE-DOC-008 9190112-200-GE-DPR-0010
2 May 2019
COMPANY PROFILE AND CERTIFICATE OF REGISTERED LAND SURVEYOR SL-TC7-GE-DOC-004 9190112-200-GE-DPR-0006