MAJOR MAINTENANCE

ALKI BEACH BATHHOUSE


AND PARK ADA IMPROVEMENTS
Proposed Project
The Seattle Park District and Real Estate Excise Tax provided funding for American’s with Disabilities Act (ADA) accessibility improvements
to the bathhouse building, the 63rd St. Comfort Station and surrounding park paths and paved areas to bring into compliance with
current accessibility requirements and address U.S. Dept. of Justice ADA citations as well as other barriers to accessibility identified.
The planned construction period is September 2019 to January 2020.
Anticipated Impacts
Portions of the park and paths will be temporarily closed. The restrooms will also be temporarily closed and portable toilets will be
provided. .
Schedule Construction Budget
Construction: September 2019 - January 2020 $380,000
Completion: February 2020
For Information Contact mike.schwindeller@seattle.gov 206-615-1165