Вы находитесь на странице: 1из 11

SHT 1 OF 1

Customer Document Title :

EMK PAINTING INSPECTION REPORT

Date : Client Measurement Equipment


Location : Job No ELCOMETER INSTRUMENT LIMITED
Drawing No :
Project :
Serial No.
Layer Coat Spec. Type Brand Colour Object Painted Direction
Flat Vertical-Down
Primer
Convex Vertical-Up
Intermediate Concave Horizontal
Top Dwg No.
Surface Prep. Rev
System Applied

PAINTING THICKNESS RECORD ( µ )


Inspection of Painting
Primer Intermediate Top Coat
Date, Time Date, Time Date, Time
Date of Inspection
Humidity (%), Temperature (⁰C) Humidity (%), Temperature (⁰C) Humidity (%) , Temperature (°C)

Location : Item

SAMPLE
1
2
3
4
5
6
Results
7
8
9
10
Min
Max

Prepared by, Reviewed By, Verified by,

Coating Inspector QA/QC Inspector Client Reps


Company Document Title :

EMK
Page
RECEIVING MATERIAL INSPECTION REPORT
1 of 1

Date of Inspection : Client :


Location : Job No. :
Drawing No :

Project :

CERTIFICATE VISUAL
NO. DESCRIPTION QTY BRAND HEAT NUMBER REMARKS
NO. DATE RESULT DATE

PL E
SA M
Prepared by Inspected by, Reviewed by,

QA Admin QA/QC Inspector Client Reps


EMK
Company Document Title :
FIT UP & WELDING INSPECTION REPORT

Date : Client :
Location : Job No :
Drawing :
Project :
Welding
Non Destructive Examination
Joint No.
SPOOL

Fit Up Welder Stamp Visual Inspection


Material To Be Joint WPS No. Welding Remarks
Date Result Date Root Filler Caping Result Date Method Report No. Date Result Defect

P LE
SA M

Prepared by, Inspected by, Reviewed/Approved by


EMK
Company Document Title :
FIT UP & WELDING INSPECTION REPORT

Date : Client :
Location : Job No :
Drawing :
Project :
Welding
Non Destructive Examination
Joint No.
SPOOL

Fit Up Welder Stamp Visual Inspection


Material To Be Joint WPS No. Welding Remarks
Date Result Date Root Filler Caping Result Date Method Report No. Date Result Defect

QA Admin QA/QC Inspector Client Reps


EMK
Company : Document Title :
FINAL DIMENSIONAL INSPECTION
REPORT

Date : Client :

Location : Job No. :

Drawing No :

Project :
DIMENSION ( INCH )
JOINT/POINT DEVIATION STANDARD
NO. DRAWING NO. SPOOL/ITEM REFERENCE RECOMMENDED
NO. ACTUAL ( mm ) (mm)
DRAWING

Acceptable

Acceptable

L E
Acceptable

P
Acceptable

M
Acceptable

SA
Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

Prepared by, Inspected by, Reviewed by,

QA Admin QA/QC Inspector Client Reps


QAC-01.6

EMK
Document Title :

HYDROSTATIC TEST REPORT

Date of Test : Test Pressure :


Job No. : Design Pressure :
Description : Pressure Gauge ID No. :
Drawing No. : Range :
Pressure Recorder ID No. :
Client : Range :
Report No : Temp. Indicator ID No. :

Pressure (Psig) Temperature

E
No. Time DESCRIPTION Results
Recorder Gauge Ambient (ºF)

L
1

P
2

M
3

SA
4

10

12

Tested by, Inspected by by,

Technician QA/QC Inspector

Reviewed by

Client Reps
Company Document Title

EMK FIT UP & WELDING INSPECTION REPORT

Date : Client :
Location : Job No :
Drawing No :
Project :
Welding
Joint No.
SPOOL

Material To Be Joint WPS No. Fit Up Welder Stamp Remarks


Welding Date Result
Date Result Root Filler Caping

P L E
SA M
Prepared by, Inspected by, Reviewed by,

QA Admin QA/QC Inspector Client Reps


REPORT NO :

EMK POST - TEST CHECK LIST JOB NO :


PIPING FABRICATION & INSTALLATION DATE :

( AFTER HYDROSTATIC TEST ) REVISION NO :

Project Name : P & ID No. :


Area / Location : Dwg. No. :
Line No. : Test Pack No. :
ITEM / DESCRIPTION OF CHECKS
1. CHECK THAT FLUSHING AND HYDROSTATIC TESTING HAVE BEEN SATISFACTORILY
COMPLETED AND RECORDED, CHECK DRYING OF LINE COMPLETE.

2. CHECK THAT CORRECT BOLTS AND GASKETS ARE INSTALLED AT ALL MECHANICAL JOINTS.

3. CHECK THAT ALL VENTS AND DRAINS ARE CORRECTLY INSTALLED AND ALL TEMPORARY
VENTS / DRAINS REMOVED.
4. CHECK THAT ALL PROCESS BLINDS AND SPADES HAVE BEEN CORRECTLY INSTALLED AS
INDICATED ON P. & I.D. AND SPECTACL BINDS ARE IN THE CORRECT FLOW POSITION.

5. CHECK THAT CONTROL VALVES HAVE BEEN INSTALLED IN THE CORRECT 'FLOW' POSITION.

6. CHECK THAT SPECIFIED BLOCK VALVES HAVE LOCKING DEVICES / CHAIN WHEELS
CORRECTLY INSTALLED AS INDICATED ON P & ID.
7. CHECK THAT ALL VALVES ARE FUNCTIONING PROPERLY AND THAT EXTENDED SPINDLES
ARE FITTED AS REQUIRED AND HAVE BEEN COATED WITH 'COPA-SLIP' OR EQUAL
WHERE SPECIFIED.
8. CHECK THAT ALL RELIEF VALVES HAVE BEEN CORRECTLY INSTALLED.

9. CHECK THAT ALL THERMO WELLS HAVE BEEN CORRECTLY INSTALLED.

10. CHECK THAT RESTRICTION AND ORIFICE PLATES HAVE BEEN CORRECTLY INSTALLED.

11. CHECK THAT PUMPS SUCTION STRAINERS HAVE BEEN CORRECTLY INSTALLED.

12. CHECK FOR CORRECT FLOW THROUGH FILTERS AND STRAINERS, TRAPS,
CHECK VALVES AND GLOVE VALVES.
13. CHECK THAT ALL GAGS HAVE BEEN REMOVED FROM SPRING-LOADED PIPE SUPPORTS
AND EXPANSION BELLOWS AND ALL TEMPORARY SUPPORTS REMOVED.

14. CHECK PAINTING IS COMPLETE.

15. CHECK ELECTRICAL HEAT TRACING IS COMPLETE.

16. CHECK INSULATION IS COMPLETE.

17. ENSURE CHECKS CARRIED OUT ON PRE - TEST CHECKLIST REMAIN VALID FOR
AS - BUILT STATUS.
WITNESS BY NAME / SIGNATURE DATE

PT. APECO

ADARO
EPORT NO :
OB NO :
ATE :
EVISION NO :

YES NO N/A

REMARKS
REPORT NO

EMK PRE - TEST CHECK LIST JOB NO


PIPING FABRICATION & INSTALLATION DATE
( BEFORE HYDROSTATIC TEST ) REVISION NO

Project Name : P & ID No. :


Area / Location : Dwg. No :
Line No. : Test Pack No. :
ITEM / DESCRIPTION OF CHECKS
1. CHECK SYSTEM COMPLIES WITH P & I.D'S AND ISOMETRICS.
2. CHECK THAT ALL NDT / STRESS RELIEVING REQUIREMENTS AS PER SPECIFICATION
HAVE BEEN MET AND RECORDED AND ALL WELDED ATTACHMENTS INSTALLED.
3. CHECK THAT CORRECT BOLTS AND GASKETS ARE INSTALLED AT ALL
MECHANICAL JOINTS.
4. CHECK THAT ALL VENTS AND DRAINS ARE INSTALLED ( ADD TEMPORARY VENTS
AND DRAINS FOR TESTING AS REQUIRED ).
5. CHECK PIPING FOR CORRECT SCHEDULE AND TYPE AND RATINGS OF FORGED
STEEL FITTINGS AND REINFORCEMENT IS CORRECT.
6. CHECK VALVE MATERIALS, USE SPEC. REF. IN PIPING MATERIAL SPECIFICATION,
TAGS AND NAMEPLATES.
10. CHECK THAT ALL PRESSURE CONNECTIONS ARE INSTALLED CORRECTLY AS PER
SPECIFICATION AND ALL THERMOWELLS ARE INSTALLED.
11. CHECK FOR CORRECT DIRECTION OF FLOW THROUGH FILTERS AND STRAINERS
TRAPS, CHECK VALVES, GLOBE VALVES AND CONTROL VALVES.
12. CHECK ORIFICE VALVE TAP ORIENTATION AND THAT TAPS AND PLUGS HAVE
BEEN SEAL WELDED AND UNUSED TAPPED HOLES AREA PLUGGED AND WELDED.
14. CHECK THAT INSTRUMENT CONNECTIONS INSTALLED AND ANY DELICATE IN
LINE INSTRUMENTATION EXCLUDED FROM TEST.
15. CHECK ALL PIPE SUPPORTS ARE CORRECTLY INSTALLED - ALL TEMPORARY
PIPE SUPPORTS REMOVED AND ANY ADDITIONAL SUPPORTS FITTED.
16. CHECK ALL RELIEF VALVES, BURSTING DISCS AND SPECIFIED CONTROL
VALVES HAVE BEEN REMOVED.
17. CHECK THAT GAGS ON SPRING SUPPORTS AND EXPANSION JOINTS ARE IN POSITION.

18. CHECK THAT ALL CHAINWHEELS AND EXTENDED SPINDLES AND LOCKING DEVICIES
REQUIRED FOR SPECIFIED VALVES HAVE BEEN INSTALLED.

19. CHECK THAT THERE IS NO SPRING IN PIPEWORK AFFECTING PUMPS OR VESSEL.

20. CHECK THAT ALL SPRINKLER HEADS, ROSETTES AND NOZZLES HAVE BEEN REMOVED
AND CONNECTIONS PLUGGED.
WITNESS BY NAME / SIGNATURE DATE
PT EMK

ADARO
:
:
:
:

YES NO N/A

REMARKS

Вам также может понравиться