Вы находитесь на странице: 1из 10

Society of Petroleum Engineers

SPE 29978

Design and Performance of Chuchupa 14 - First Horizontal Gas Well,


Offshore Colombia
w. s. "Bill" Huang, Mike R. French, Barry N. Markitell
SPE Members

COPYright 1995, Society 01 Petroleum Engineers, Inc.

This paper was prepared lor presentation at the International Meeting on Petroleum Engineering held in Beijing, PR China, 14-17 November 1995.

This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the author(s). Contents althe paper. as presented,
have not been reviewed by the Society 01 Petroleum Engineers and are subjected to correction by the author(s). The material, as presented, does not necessarily rellect any position 01 the
Society 01 Petroleum Engineers, its officers. or members. Papers presented at SPE meetings are subject to publication review by Editorial Committees 01 the Society of Petroleum Engineers.
Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicuous acknowledgment 01 where and by whom
the paper is presented. Write librarian, SPE, P.O. Box 833836. Richardson. TX 75083-3836, U.S.A. (Facsimile 214-952-9435).

ABSTRACT
90% of the gas supply for electricity generation in the
In November 1992, a 2000-ft horizontal well was drilled coastal area. While the Ballena Field is partially onshore,
in the Chuchupa Field, offshore Colombia. Chuchupa is the Chuchupa Field is about 7 miles offshore. The
a major gas field in Colombia, contributing about 90% original gas in place for Ballena and Chuchupa are 1.5
of the gas supply for electricity generation on the and 4.2 TCF, respectively. Gas recovery in both fields is
northern coast of Colombia. This paper documents the 30% and less than 30%, for Ballena and Chuchupa,
selection, planning, reservoir simulation, drilling, respectively.
completion and operation phases of this project. The
horizontal well, Chuchupa 14, was successfully drilled According to a previous reservoir simulation study,
from an offshore platform in 200 ft of water with a total some of the existing wells in the Chuchupa Field may
horizontal displacement of 2000 ft. The entry point of face water breakthrough in a near future, therefore
the horizontal well is 6300 ft away from the platform. replacement wells are needed to insure a continuous
The formation is a semi-consolidated Chuchupa supply of gas from this field. Horizontal wells are one of
sandstone at a depth of 5325 ft sub sea, with average the option to be considered.
thickness of 167 ft, and average permeability of 209
md. Initial production test indicated that the well could BACKGROUND
be produced at 60 MMSCF/day on a 44/64" choke. This
production rate is 4 to 6 times that of a conventional Figure 2 shows the isopach map of the Chuchupa Field
vertical well. Currently, the well is being produced from with its discovery well Chuchupa 1 near the center of the
40 to 60 MMSCF/day. In this application, the horizontal field and the 8 vertical producers drilled from the
well can replace at least four vertical wells. With the platform. When the field was first placed on production
development of horizontal wells, a significant amount of in October 1979, the rate was at about 100 MMSCF/day.
savings can be realized with fewer platforms and wells As of December 1991, 450 BCF of gas had been
needed to develop the remainder of the field. produced from the field with the average production
rate of 104 MMSCF/day or 13 MMSCF/day/well for the
INTRODUCTION 12 year period. Before the horizontal well was drilled,
production from the eight vertical wells was 140
The natural gas in the northern coast of Colombia is MMSCF/day.
primarily supplied by two gas fields jointly operated by
the Texas Petroleum Company and Ecopetrol. The The group of vertical producers are in the eastern
Ballena Gas Field and the Chuchupa Gas Field in the portion of the field where an aquifer is known to exist.
Guajira area, shown in Figure 1, provided more than Figure 3 shows the extent of the aquifer interpreted by

11
2 DESIGN AND PERFORMANCE OF CHUCHUPA 14- SPE 29978
FIRST HORIZONTAL GAS WELL, OFFSHORE COLOMBIA

geologists. As can be seen, the vertical wells have to be production, drilling and geological personnel was
perforated in the upper portion of the formation to formed to manage the project.
delay water coning. According to a previous reservoir
simulation study, water breakthrough will occur soon in 2) An in-depth evaluation of reservoir performance was
several wells. In order to maintain uninterrupted gas initiated concurrently to design the horizontal wells.
production from this field, a reservoir management team Items to be determined would include:
from Texaco Colombia and Texaco Exploration and
Production Technology Department (EPTD) was a) number of horizontal wells to be drilled from
formed in January 1992 to investigate the feasibility of the existing platform,
drilling additional wells. b) orientation and depth of well,
c) deliverability projections which would include
INITIAL SCREENING tubular design,
d) water breakthrough time and critical production
The objective of the initial screening was to determine rate.
the production potential of a horizontal well in this
reservoir. Of the 8 existing producing wells, Wells 2, 7, 8, 3) The drilling program and cost estimates for
12 and 13 have thicknesses ranging from 139 to 196 ft horizontal wells would be commenced as soon as
whereas wells 9, 10 and 11 range from 65 to 87 ft. preliminary well design was established.
A verage information from the five wells in the thicker
pay sands were used for history matches. These wells 4) Modification of the platform for horizontal well
have been producing at an average rate of 13 to 15 drilling would take place with the assistance of
MMSCF/day with pressure drops ranging from 20 to 80 Texaco Central Offshore Engineering.
psig over the 12 year period.
Sufficient lead time was required for ordering and
Joshi's PC based analytical horizontal well model, shipping drilling and production equipment to
JTI.HORIZONT AL was used to history match the Colombia for the horizontal well. In order to complete
vertical well and predict horizontal well production. the drilling of the horizontal well by the end of 1992, a
A verage reservoir parameters input to the model are project flow chart shown in Table 2 was established.
shown in Table 1. By adjusting flowing bottomhole
pressure, skin factor, and decline exponent after the RESERVOIR SIMULATION
pseudo steady state time, average production rates as a
function of time and cumulative gas production for a 12 To facilitate the in-depth study, a reservoir simulation
year period were matched. Results indicated that the study was initiated with the existing geology and
production rates varied from 15 MMSCF/day to 12 production data. A single well model was chosen to
MMSCF/day and the cumulative gas production was 58 conduct a vertical well history match. After a satisfactory
BCF which was close to the 57.2 BCF observed data. history match was made, different operating scenarios
were evaluated. Reservoir pressure support was simulated
With average parameters derived from the vertical well by placing water injectors on the boundary of the
history match, a horizontal well projection was generated drainage area. Injected water volumes were adjusted to
using the same model with different horizontal well maintain the observed reservoir pressure while the
lengths and Kv/Kh ratios. The initial rates and 12 year vertical well was being produced.
cumulative for horizontal well lengths from 1000 to
3000 ft. and Ky!Kh ratios from 0.06 to 1.0 were: Reservoir Model

Rate, MMSCF/day/well 16 to 87 A Western Atlas International black oil simulator, VIP-


Cum, BCF/well 57 to 238 ENCORE, was used for this study. VIP-ENCORE is a
three-phase, three-dimensional, vectorized, fully-implicit
Figures 4 and 5 show the comparisons of these cases. (or IMPES) simulator. The horizontal well option,
They clearly indicate that horizontal wells could HVWELL, was used to predict horizontal well and
improve the deliverability of the reservoir. vertical well prediction performance.

PROJECT PLANNING HVWELL, which was created by Texaco, consists of


three modules: a pre-processor (input panels), a
From the encouraging results, several action items were single/dual porosity model, and a post-processor. The
taken: pre-processor requires minimum reservoir and fluid
1) A multi-disciplined task force consisting of reservoir, information to create a complete input data set, with

12
SPE 29978 W.S."BILL" HUANG, M.R. FRENCH, BARRY MARKITELL 3

PVT and rock correlations, for running a single porosity the gas oil relative permeability curves. Other default
(or dual porosity) simulator. An automatic grid set-up parameters were used for the rest of the relative
option is also built into HVWELL to create correct grid permeability curves.
geometry for modeling various vertical and horizontal
well length and well location relating to GOC/wOC, and Vertical Well History Match
hydraulic fractures perpendicular to the horizontal
wellbore. Well block productivity indices for both Average production rates from the eight wells were input
vertical and horizontal wells are automatically calculated to a single vertical well model. Aquifer support was
using the method of Peace man 1. These features greatly provided by using four water injectors at the periphery
save man-time and cpu-time for the data preparation in of the drainage area. Vertical and horizontal
reservoir simulation. permeabilities in the water table were adjusted so that no
water production was observed at the end of the vertical
Reservoir Grid well history match. Strength of aquifer support was
adjusted so that the predicted reservoir pressure matched
A 3D model was used to represent the symmetric with the observed reservoir pressures. Results of the
element (one-quarter) of 430 ft thick, 3000 acre vertical well history match are shown in Figure 7.
drainage area with a horizontal well in the middle.
Figure 6 illustrates a 3D Cartesian grid case generated Observed tubing head pressures during the vertical well
by HVWELL for a 2,000 ft horizontal well with 130 ft production period were used to run PIPEPHASE so that
of pay and a 300 ft of water table. The drainage area of an appropriate bottomhole flowing pressure history
3000 acres was represented by a square box of 11432 ft could be constructed. The bottomhole flowing pressure
on each side. Due to symmetry, only 114 of the volume history calculated from the tubing head pressure data
was simulated as shown in the figure. The horizontal was compared with the predicted bottomhole pressure
well was placed 20 ft below the top of the formation history. Results indicated that the bottomhole flowing
which was 110ft above the water table to minimize pressures agreed reasonably well.
coning.
Absolute Openhole Flowing Potential (AOFP)
Note that to properly simulate water coning, the
program automatically creates fine grids adjacent to the After the vertical well history was completed, the same
top and bottom of the horizontal well. Eight layers were reservoir parameters were used to set up horizontal well
provided to describe the 130 ft pay sand with the models. Horizontal well length of 250, 500, 1000, 1500,
horizontal well in the second layer. Five layers were 2000 and 3000 ft. were evaluated. A four-point
allocated to represent the 300 ft water table. Half of the production test was simulated by producing the well at
horizontal well was represented by seven grid blocks in 20, 40, 60 and 80 psi pressure drawdown. From the
the y-direction. Fine grid blocks of 10ft each are near calculated flow rates, the AOFP of each horizontal well
the tip of the horizontal well to better simulate water with a different length was established. Figure 8 shows
coning and to monitor the fast pressure drop in the the AOFP for the vertical and horizontal wells in
region. Chuchupa. Note that the AOFP for a 500 ft and 2000 ft
horizontal well would be 3 times and 8 times,
Reservoir and Fluid Properties respectively, that of a vertical well.

To establish a representative scenario in the Chuchupa Inflow/Outflow Curves


field, average properties of the eight existing producing
wells were used for the vertical well history match. PIPEPHASE was used to estimate the flow rate
Properties shown in Table 1 were used except for the deliverability for tubing sizes from 3.5" to 7" at different
average thickness which is 130 ft for the eight wells. tubing head flowing pressures and a specified
Other updated information included permeability of bottomhole flowing pressure. The range of tubing head
210 md and porosity of 22%, as more data became pressures varied from 1800 psig to 1500 psig whereas
available. From core analysis, the vertical permeability the bottomhole flowing pressures varied from 2280 psia
was determined to be 21 md. Many shale stringers were to 2150 psia. These served as outflow parameters
observed in the aquifer. Through history matching of whereas the results from the AOFP calculation served as
the vertical well water production history, the the inflow parameters for the inflow/outflow curves.
permeability of the aquifer were estimated to be 2 md Results of the inflow/outflow curves for tubing head
horizontal and 0.5 md vertical. flowing pressures of 1800, 1700, 1600 and 1500 psig,
and horizontal well length of from 250 ft to 3000 ft
Connate water at 23.5% and residual gas saturation to were obtained. Figure 9 illustrates the inflow/outflow
liquid at 32% were used for establishing end points of curves for a tubing head flowing pressure of 1800 psig

13
4 DESIGN AND PERFORMANCE OF CHUCHUPA 14 - SPE 29978
FIRST HORIZONTAL GAS WELL, OFFSHORE COLOMBIA

case with horizontal well length varies from 300 to 2000 Position
ft.
Results from Table 3 indicate that horizontal wells
Horizontal Well Position in Pay Sand should be placed near the top of the formation to
minimize water coning. Positioning the well 20 ft from
A parametric study was made to investigate the effect of the top of the formation will compensate for
horizontal well position within the pay sand. For a 2000 uncertainties in picking the top of the pay sand and
ft horizontal well case, the well was placed at 20 ft, 40 ft providing a larger target window to facilitate drilling.
or 65 ft from the top of the formation. The reservoir was Reducing the distance from the top of the sand would
allowed to produce at 50 MMSCF/day for 20 years. increase the risk of penetrating above the top of the
Results indicated that for the 20 ft case, water did not formation.
appear until after 19 years of production. When the well
was placed in the center of the pay sand (65 ft), water Location
would have been produced after 15.2 years. The water
breakthrough times and amount of water produced after Ideally the horizontal wells should be placed far away
20 years are shown in Table 3. from the existing wells to minimize interference of
production. Input from the drilling engineers indicated
Selection of the Horizontal Well that a practical distance for a horizontal well to enter the
pay sand would be about 8500 ft. from the platform.
Length From the reservoir point of view, this distance appears to
be adequate. We recommended 8000 ft. so that potential
The criteria in selecting a horizontal well is to have a drilling problems will be minimized.
maximum deliverable production rate with minimum
sand and water production. From Figure 9, it can be Tubing Size
seen that a longer well can provide higher rates.
As mentioned before, large tubing should be used to
We elected to use a 50 psi pressure drawdown, about half handle high flow rates. However, if 7" casing were to be
of the drawdown in a vertical well, as a criteria to select used, extensive platform modification would have been
the horizontal well length. This was chosen to maximize required.
horizontal well productivity and reduce potential Production Rate
problems for high gas production rate such as,
50 MMSCF/day was selected based on the maximum
-turbulent effects erosional velocity of 5.5" tubing. This production rate
-sand production can also be delivered by the horizontal well within the
-tubing erosion tolerance of pressure draw down limits.
-accelerating water coning
DRILLING AND COMPLETION
To minimize extensive platform modification for
drilling, we tried to avoid using 7" casing for The importance of pre-well planning can not be
production. For 5.5" tubing the maximum erosional overemphasized. In order to improve the chances of a
velocity would be about 50 MMSCF/day. With these successful horizontal well application, potential
constraints in mind, a 2000 ft horizontal well can be problems must be identified and contingency plans
selected for the case where the tubing head flowing formulated well ahead of the spud date. Several areas of
pressure is 1800 psig as can be seen in Figure 9. concern were reviewed by a team of experts consisting
of both Texaco Colombia and EPTD personnel. The
Completion following are highlights of the final recommendations.

The existing producers were cemented and perforated. Casing Program


Sand production was minimized, when no significant
perturbation in pressure drawdown was introduced. In 24" drive pipe had been pre-driven to a depth of 366'
the case of using horizontal wells, the pressure (214' below the mud line) when the platform was
drawdown would be smaller. Therefore, the possibility originally drilled. 18 5/8" conductor casing would be set
of producing sand would be even smaller. We at a depth of 590'. 13 3/8" surface casing would be set at
recommended using slotted liners, which is a less 3350' MD (2515' TVD) at an inclination of 60 0 • This
expensive sand control method. point was selected to case off the first build section prior
to drilling the long tangent section. 10 3/4" x 9 5/8"

14
SPE 29978 W.S."BILL" HUANG, M.R. FRENCH, BARRY MARKITELL 5

production casing would be the last string of pipe to be Verification is provided by a real-time resistivity sensor
cemented in place. The shoe would be set at 81 0 , 16' in the MWD package. Once sand penetration is verified,
TVD below the top of the Chuchupa sand. 10 3/4" the final build to horizontal is initiated.
would be run from surface to 600' to permit the
installation of a surface controlled sub sea safety valve at When drilling the well, it would be very important to
± 400' in the 7" production tubing. utilize directional practices which would minimize
torque and drag. EPTD's experience has indicated that
Completion Program significant increases in torque and drag are realized in
build sections when the directional driller uses a "pattern
A 7" liner with 1350' of solid wall casing followed by drilling" technique in conjunction with a steerable
2000' of slotted liner would be used as the production motor. Pattern drilling is the practice of alternately
string. A hydraulic packer would be used to hang the sliding and rotating a steerable motor in order to achieve
liner and isolate the annulus. The top of the liner would the required build rate to follow a design line on a
be placed in the 60 0 tangent section immediately above vertical section plot.
the second kickoff point. This would permit wireline
access to the landing nipple run immediately below the EPTD has developed a directional technique that
packer. A string of 2 7/8" tubing run inside the slotted reduces torque and drag in horizontal wells. The
liner and stung into a seal sub would provide the technique utilizes a "design window" on the vertical
capability to circulate past any bridges while running the section plot as opposed to a design line. Minimum and
liner and would also allow the mud in the annulus to be maximum acceptable build rates are specified as
displaced with completion fluid. A liner tie-back stem opposed to specifying a single design build rate. The
and overshot assembly would be used to tieback 7" minimum and maximum build rates define the lower
tubing to the surface. and upper boundaries of the design window. When the
well is kicked off, as long as the actual build rate is
Directional Program between the minimum and maximum that have been
specified, the steerable motor is oriented the entire build
Directional targets for horizontal wells are three section. Adjustments are made in the tangent angle to
dimensional. In addition to specifying a target area in allow hitting the target. This results in a much smoother
the horizontal plane, a target window must be specified build section and less drag, even though the dogleg
in the vertical plane. The target window in the vertical severities surveyed may be significantly higher than
plane is typically referenced to the top of the reservoir. those reported using a pattern drilling technique.
Since the exact depth at which the reservoir top will be Texaco has used this technique successfully in our Gulf
penetrated is seldom known, the target window is usually Coast horizontal wells. This technique would be used on
a "moving target". A properly designed directional the Chuchupa 14 well.
program must provide adequate contingency to allow
hitting this moving target. Mud Program

With the existing offset well data and seismic Several mud systems were designed to drill specific
interpretation, the geologists could only predict the sections of the well to handle the unique problems
expected sand top, and thus vertical target window, associated with the formations penetrated. The vertical
within + 85' TVD. With such a large sand top section was drilled with two systems, one, a non-
uncertainty, a pilot hole through the reservoir would dispersed, seawater/prehydrated bentonite, through the
usually be required prior to drilling horizontally. The conductor and surface holes, and the second, a
Chuchupa project differed from the norm in that the seawater/drispac to mechanically control the shales.
areal extent of the structure and the thickness of the
reservoir permitted fairly liberal target constraints. This A mixed metal hydroxide (MMH) was used to drill the
generous target window would allow hitting the target horizontal section. It has an excellent carrying capacity
without first drilling a pilot hole, by using a technique for hole cleaning purposes, and it also exhibits high but
developed by Texaco in our Gulf of Mexico horizontal fragile gel systems. Calcium carbonate was used as a
wells. weighing material as well as a bridging agent to
minimize formation damage.
The technique requires approaching the expected sand
top at a relatively high inclination, determined to be 81 0 Formation Evaluation Program
for Chuchupa. The approach angle must be attained by
the shallowest depth at which the sand top may be All formation evaluation data would be gathered via
encountered. This angle is then maintained, using a real-time logging while drilling tools (L WD) and/or
steerable motor, until penetration of the sand is verified. mudlog analyses. No wireline logs were programmed.

15
6 _DESIGN AND PERFORMANCE OF CHUCHUPA 14 - SPE 29978
FIRST HORIZONTAL GAS WELL, OFFSHORE COLOMBIA

No LWD data would be acquired above ± 5000' TVD. of sand and 5.6 barrels of water per day were produced
On a bit trip at or near 5000' TVD, a 2 MHz for the first three days as the well was being cleaned up.
propagation resistivity LWD sub would be added to the As different choke sizes were being tested, production
MWD package. The real-time resistivity measurements stabilized around 28 MMSCF/day on a 35/64" choke at
would be used to correlate and confirm entry within the 2000 psig with 5 barrels of water and 7 grams of sand
Chuchupa sand. per day.

A 2 MHz propagation resistivity sub would be run in the The well was also tested at 60 MMSCF/day on a 44/64"
horizontal section. After drilling approximately 1000' of choke with 1925 psig tubing head flowing pressure.
horizontal section, if hole conditions permitted, a real- Water production was minimal at 7 bbls of water per day
time neutron-density sub would be added to the MWD and no sand was produced. The 60 MMSCF/day test was
package. sustained for 3 days. When the well was brought down to
44 MMSCF/day on a 42/64" choke at 1965 psig, no
IMPLEMENTATION measurable amount of water and sand were observed.
Production was maintained at 20 MMSCF/day because
The well was drilled according to schedule. A 2000' of the limitation of the production facilities at that time.
horizontal section was successfully drilled and The production testing and pressure history from
completed, but not without incident. For examples January 22, 1993 through May 4, 1993 are shown in
Figure 12.
1) During the drilling of the 12 114" hole, sticking
problem occurred as gumbo formation prevented the CURRENT STATUS
down-hole motors from performing as designed. A 9
5/8" casing had to be set at 7154 MD(4615 TVD) and Modification of the platform was completed in late 1993
the 8-112" hole had to be sidetracked. As a result, a 7" to handle higher production rates. Entire production
production liner had to be set in the formation and an history of the well since the inception of the production
unplanned 6" hole had to be drilled in order to is shown in Figure 13. The production rate was set
complete the well. Therefore, a 5" slotted liner instead according to demands. It had been produced for up to
of the originally designed 7" slotted liner had to be 60 MMSCF/day without sand and water production.
used for production.
CONCLUSIONS
2) The top of the sand appeared 96' higher than
expected. However, due to the built-in contingency 1. A multidisciplined team has successfully designed,
plan taking this into consideration in the pre-drill drilled and produced the first horizontal well in
planning program, the horizontal well was offshore Colombia. The observed production
successfully placed 20 ft below the top of the sand as matches closely the predicted production.
designed.
2. It is possible to drill a horizontal well with a large
The final completion of the well is shown in Figure 10. sand top uncertainty without first drilling a pilot hole.
The vertical 24" conductor pipe was set at 366'. 18 5/8", This technique requires a high approach angle, real-
87.5 Ib/ft, K-55 surface casing was set at 590 ft. It was time logging while drilling (LWD) sensors, and fairly
followed by a 13 3/8" 54.5 Ib/ft, J-55, buttress liberal target constraints.
intermediate casing at 3348'. 9 5/8", 43.5 Iblft, N-80
buttress production casing was set at 7154'. The 3. The detailed pre-well contingency planning allowed
production liner is a 7", 26 lblft , N-80 buttress casing the target to successfully be entered, even when the
wilhout slots, set at 8934' followed by a 5" , 15 Iblft, N- sand top was penetrated 96' higher than originally
80 slotted liner with 64 slots per foot. The total estimated.
production length is 1953 feet. The profile of the well is
shown in Figure 11. Note that the horizontal well 4. It is feasible to drill and complete a horizontal well in
entered the pay sand 6000 feet away from the platform unconsolidated sand and produce at high rates
and penetrated another 2000 feet. without sand production.

PRODUCTION TESTING 5. Application of horizontal wells in the Chuchupa field


can reduce the number of required wells and
The initial production testing indicated that 26 platforms in developing this gas field.
MMSCF/day could be produced through a 46/64" choke
at tubing head pressure of 1961 psig. About 400 grams

16
SPE 29978 W.S."BILL" HUANG, M.R. FRENCH, BARRY MARKITELL 7

Table 1
Chuchupa Gas Field
Key Parameters used for PC screening model

Reservoir Pressure, psia 2529


Pay thickness, ft 167
Reservoir Porosity, % 23.9
Reservoir Permeability, md 209
Initial Water Saturation, % 24.8
Reservoir Temperature, of 158
Gas Gravity, fraction 0.563
Total Compressibility, 1/psi 0.000392
Initial Gas Viscosity, cp 0.017
well bore Radius, inches 4.25
Drainage Area, Acres 3000
KvfK h, fraction 0.06

Table 2
Horizontal Drilling at Chuchupa - Preliminary
Flowcharting
January I FabrUlry I Match I April I ""'y I June I July I Auguol ISaplamberi Oclober INovamberl Docamber
111111111 11111111 I 1I]ltjll I "1"111 I "1111!! I II!IIIII I Iljltjll I Iqlljll I 111"111 I 111"1" I l!julll 111111[11
10 20: III 20 ~ 10 20 : IQ 20 : 10 20 : 10 20 : 1(1 20 : 10 20 : 10 20 : 10 20 : 10 20 : 10 20
Reservoir EvalUllion I I I I I I I I I
I I ! I I 1 I I I I I

Orlq. eosi Evaluation By EPTO: : : : : : : : :


I I I I I I 1 I I I J
I I I I I I I I t I I
I I PIaHormMod. ByCOE I I I I I I I I
: : I I Order Drillina Equipment I I : : :
I I I I I I I !
I I Order PrOduction Eauipment 1 1 I
I I I I I I ! I
I J I 1 I ' I [
I I I I t PIa~Mod. J I
t I I I I I I
I I I I I I Ortq.WtlIChu-14 I
I I I I I I I
I I I I I I Dng.WellChu·1

Table 3

Horizontal Well Initial water Cumulative


distance from breakthrough water
top of formation time production
(ft) (years) (MSTB)

20 19.2 19
40 18.2 99
65 15.2 289

17
Figure 1. Guajira joint operation - location map. Figure 2. Chuchupa Field, Colombia - Horizontal well location.

90 ,
,
, ,
------~-------------I--------
80
>- ,, ~,
K'
III , ,
C 70 - - - - - -:- - - - - - -1(11 - - - -,- -
ii:
()
C/) 60 ----- -~ - - - - - - - j-
:E ,
Chuchupa - 5 Chuchupa - 1 Chuchupa - 2 :E 50

-
---I-------------~------
R.T.E.21' R.T.E.76' R.T.E.78' , ,
Gi , ,
I II - - - _ _ _ _ _ _ 1_ _ _ _ _ _ - - - - - - - _____ _
a: 40 ,
,, ,
,
iii
E 30 - - - - - -: - - - - - - -0'.06 - - -, - - - - - - - - - - - : - - - - --
.E , ,
20 -------~-------------,------
,
,
10
1,000 2,000 3,000
Horizontal Well Length, Feet

Figure 3. Chuchupa cross-sections. Figure 4. Chuchupa Field - Preliminary horizontal well evaluation (3,000
acre spacing, H = 167 Ft., Initial Rate vs. Well Length).

240 , ,

220 ---- -- -~, -- -- -b --- --:--


, ----
Formation Thickness = 130 Ft
______ Il-.. _____ ~_-,-- I
Water Column = 300 Ft
200 , ,
, ,
180 ------ ----r-
~-

G:' 160
()

--
m
E
:::I
140
120
,
,
-------------1-------
,
-----~------
() , ,
,
100 ------------,------
,
, NX=11
80 , ------------l------
, NY= 17
NZ = 13
60 -----------~-------------~------
, ,
, ,
(Not To Scale)
40
1,000 2,000 3,000
Horizontal Well Length, Feet

Figure 5. Chuchupa Field - Preliminary horizontal well evaluation (3,000 Figure 6. Horizontal well gridding system - 114 representation.
acre spacing, H = 167 Ft., 12-yr. Cum. vs. Well Length).
18
2,800 1-;---;------:---:-----;-------:--;=:::::;==1 1,000E +07
1\1
'iii
u:Q
I
Q, ----r----r----'T
15
!!! 2,600 ()
:J
1/1 I I
rJ)
:e N 'i 1,000,000
.....no.
1/1
~ 2,400 .
_~ _ _ _ _ J ____
I
~

I
----.-~----~--------
____ ~

I
_ _ _ _ _ I __ _
10 :e no
no
...
'0
I
I I I I
~
a: 100,000 - - --
Cii 2,200· ====~====~====~===~----~----~--.
I
> I I I Simulated Pressue - =:= == 5 ~
I • Measured Pres9ua o
III
Gl _ _ Rate Sch.
I
I u::
a:
2,000 -+---+--+---+---+--+---+---1--' 0 10,000
o 500 1,000 1,500 2,000 2,500 3,000 3,500 10 100 1,000 10,000
Days Gas Rate, MMSCF/D

Figure 7. Chuchupa Gas Field - Horizontal well reservoir study (Vertical Figure 8. Chuchupa Gas Field - Horizontal well reservoir study (Vertical
well history match). and horizontal well flow potential).

IL 366, 24" Conductor

~90'
400' Safety
Valve Surface Casing
.~ 2,350-.-------~----~--~--~----~--~1----~-------. Shoe lS 518",
c.. I I I
730',10314", S7.5 LblFt,
I I I I I I I
K-55, Butt
~.. 2,300 -0 ::.3.S'·i'L~.t.}.L O-=5~'~ - - ~ - - - O=I.o'~ ~- -- ~- ___ ~- -- 4----
51.0 LblFt,
N·SO, Butt
rJ) I I Intermediate Casing
rJ) Shoe 13 3IS",
l!! 54.5 LblFt,
Q, 2,250 - J-5S, Butt
01
C Production Casing
.~ 2,200 Shoe 95/S',
43.5 LblFt,
u: I
Production Liner
7", 26 Lb/Ft,
N-SO, Butt
GI ___ .1 ___ _
'0 2,150 -- - N-80, Butt
~
Without Slot
J: ':
!5
:s2,100·
I -

m 02040 60 80 100 120 140 160 180 200


Flow Rate, MMSCF/D
Slotted Liner 5",
15 LblFt, N-80, Butt
64 Slots per Foot

Figure 9. Chuchupa Gas Field - Horizontal well reservoir study (lnflow/ Figure 10. Chuchupa 14 - Well completion.
Outflow Curves [THFP = 1800 psigJ).

_ Plan View

~
C)
-iii
100 ,------------------------------------------, 2,500 Q,

>- !!!
1\1 80 2,000 ;
Q

I
u:
() ----~
III
~
no
rJ) 60 --------------- 1,500 C)
iI :E ----- THFP, psig c
:E 'i
I
5555' I

I
-Gi
1\1
a:
1/1
.. - - .. - - - Gas Rate, MMSCF/day :- 1,000 o
u::
'C
:g
I 1\1
(!J J:
I C)
c
OmrrrrmmTI~rrmrrmmm~rrmmmmmmmTImTImmmnmTImTIfumm~~O :0

8204'
j 1/22 2121 3/23
Date, 1993
4/22
~

Figure 11. Chuchupa 14 profile. Figure 12. Chuchupa 14 - Production testing and pressure history.
19
60,000~---------------'''----------'

55,000 1=1 0 Ave, Monthly Prod. (MCFD) J


50,000 1=1- Cum. Production (MMCF) r-------l 1------ f~
45,000 ___________ _ _ _ _ _ _ _ _ _ _ r---

c::: 40,000 - ,------ - I--


0
:g 35,000 +---------..:----1 r- I--
t---- -
'"e
"0
30,000 -1-----------1 r- r----
f---- -
WW IH 1--H-1
I--
a..
en 25,000 -1-----------1 r- t---;;-- I--
to I--
(!J
20,000 + - - - i l - l 1--1 1-1 I-- I--
-- r-
15,000 r-
10,000 I--
5,000

M
ri I M
r ftf
M
l-
M
~
~
~
'!'
"
"7 ~
en Iz ~ ~
~
'"
f
~
~
"7
i.,
en
~
z
;;; ;;; 6M 6
M
;;; ;;; ;;; ;;; g g
Figure 13. Chuchupa No. 14 - Average monthly and cumulative gas
production history.

20

Вам также может понравиться