Reference Number Scope Location Description Date issued Date cleared Status NCR canceled Causes
Proposition
Cracks
Other
1 MNC-ACT-BBI-NCR-FON-001 DW-CB P22 to P24 Execution of the guide wall was not according to the proposed sections BSV 11-Jun-08 O 20-Mar-09 7-Apr-09 Closed NCR BBI 001 Method Statement Implementation
3 MC-BBI-Q+-NC-BA-FON-003 DW-CB P26 Un-appropriate excavation during excavation along house No.3 Ham Nghi BSV 12-Jun-08 O 4-Jul-08 Closed Shop drawings conformity
Minimun distance of 4 meters between crane and edge of Guide wall during
5 MC-BBI-Q+-NC-BA-FON-005 DW-CB In front of Panel 1
D-wall excavation not follow MOS
BSV 16-Sep-08 O 10-Mar-08 Closed Method Statement Implementation
6 MNC-ACT-BBI-NCR-FON-002 DW-CB Next to P20-P09-P47 Non-protected Inclinometer and Piezometer Pipes IBST 15-Sep-08 O 20-Mar-09 7-Apr-09 Closed NCR BBI 006 Method Statement Implementation
7 MNC-ACT-BBI-NCR-FON-003 DW-CB Panel P44 Insufficient concrete level BSV 24-Sep-08 C 26-Mar-09 12-Nov-09 Closed NCR BBI 007 Method Statement Implementation
Reinforcement cage (left) floats to Approximately 110mm during concrete Waiting for completion of
8 MNC-ACT-BBI-NCR-FON-004 DW-CB Panels P09
pouring
BSV 30-Sep-08 S 27-Mar-09
the work
Method Statement Implementation
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
Panels P7A BSV 3-Oct-08 26-Mar-09 NCR BBI 010 Undeterminated
statement the work
9 MNC-ACT-BBI-NCR-FON-005 DW-CB Non conformance of Sonic Test results with the ratings Criteria on Method C
Panels P11 BSV 3-Oct-08 26-Mar-09 7-Apr-09 NCR BBI 011
statement
Non conformance of Sonic Test results with the ratings Criteria on Method
Panels P44 BSV 3-Oct-08 26-Mar-09 7-Apr-09 NCR BBI 012
statement
Non conformance of Sonic Test results with the ratings Criteria on Method
Panels P01 BSV 10-Oct-08 26-Mar-09 Closed Undeterminated
statement
10 MNC-ACT-BBI-NCR-FON-006 DW-CB C
Non conformance of Sonic Test results with the ratings Criteria on Method
Panels P18 BSV 10-Oct-08 26-Mar-09
statement
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
11 MNC-ACT-BBI-NCR-FON-007 DW-CB Panels P06
statement
BSV 11-Oct-08 C 26-Mar-09
the work
NCR BBI 013 Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
12 MNC-ACT-BBI-NCR-FON-008 DW-CB Panels P43
statement
BSV 11-Oct-08 C 25-Apr 25-Apr-09 Closed Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
Panels P02 BSV 11-Oct-08 25/4/09 25-Apr-09 Closed Undeterminated
statement
13 MNC-ACT-BBI-NCR-FON-009 DW-CB C
Non conformance of Sonic Test results with the ratings Criteria on Method
Panels P05 BSV 11-Oct-08 26-Mar-09 7-Apr-09
statement
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
14 MNC-ACT-BBI-NCR-FON-010 DW-CB Panels P17
statement
BSV 16-Oct-08 C 26-Mar-09
the work
NCR BBI 014 Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method 3/26/2009 Waiting for completion of
Panels P03 BSV 20-Oct-08 NCR BBI 015 Undeterminated
statement the work
15 MNC-ACT-BBI-NCR-FON-011 DW-CB C
Non conformance of Sonic Test results with the ratings Criteria on Method
Panels P50 BSV 20-Oct-08 25-Apr-09 25-Apr-09 NCR BBI 016
statement
Non conformance of Sonic Test results with the ratings Criteria on Method
16 MNC-ACT-BBI-NCR-FON-012 DW-CB Panels P09
statement
BSV 24-Oct-08 C 26-Mar-09 7-Apr-09 Closed NCR BBI 009 Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
17 MNC-ACT-BBI-NCR-FON-013 DW-CB Panels P10
statement
BSV 24-Oct-08 C 26-Mar-09
the work
NCR BBI 017 Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
Panels P04 BSV 24-Oct-08 26-Mar-09 3-Apr-09 Undeterminated
statement
18 MNC-ACT-BBI-NCR-FON-014 DW-CB C
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
Panels P46 BSV 24-Oct-08 26-Mar-09 NCR BBI 018
statement the work
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
19 MNC-ACT-BBI-NCR-FON-015 DW-CB Panels P21
statement
BSV 28-Oct-08 C 26-Mar-09
the work
NCR BBI 019 Undeterminated
Non conformance of the depth after excavation and depth before casting Waiting for completion of
20 MNC-ACT-BBI-NCR-FON-016 DW-CB Panels P30
concrete
BSV 28-Oct-08 C 26-Mar-09
the work
NCR BBI 008 Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
21 MNC-ACT-BBI-NCR-FON-017 DW-CB Panels P49
statement
BSV 28-Oct-08 C 25-Apr 25-Apr-09 Closed NCR BBI 020 Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
22 MNC-ACT-BBI-NCR-FON-018 DW-CB Panels P15
statement
BSV 28-Oct-08 C 25-Apr-09 25-Apr-09 Closed NCR BBI 021 Undeterminated
P11-P08-P43-P02-P09-
P10-P16-P04-P33-P28-
23 MC-BBI-Q+-NC-BA-FON-022 DW-CB P49-P26-P34-P15-P29- D-wall concrete casting level is higher than required BSV 7-Nov-08 C 10-Mar-09 Closed Method Statement Implementation
P30-P25-P35-P42-P31-
P24-P41-P13-P39-P36
Non conformance of Sonic Test results with the ratings Criteria on Method
24 MNC-ACT-BBI-NCR-FON-019 DW-CB Panels P48
statement
BSV 4-Nov-08 C 25-Apr 25-Apr-09 Closed Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
25 MNC-ACT-BBI-NCR-FON-020 DW-CB Panels P30
statement
BSV 11-Nov-08 C 25-Apr 25-Apr-09 Closed Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
26 MNC-ACT-BBI-NCR-FON-021 DW-CB Panels P06
statement
BSV 11-Nov-08 C 26-Mar-09
the work
Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
27 MNC-ACT-BBI-NCR-FON-022 DW-CB Panels P38
statement
BSV 18-Nov-08 C 25-Apr-09 25-Apr-09 Closed Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
28 MNC-ACT-BBI-NCR-FON-024 DW-CB Panels P42
statement
BSV 18-Nov-08 C 25-Apr-09 25-Apr-09 Closed undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method Waiting for completion of
29 MNC-ACT-BBI-NCR-FON-023 DW-CB Panels P35
statement
BSV 3-Dec-08 C 26-Mar-09
the work
Undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
30 MNC-ACT-BBI-NCR-FON-026 DW-CB Panels P37
statement
BSV 1-Dec-08 C 26-Mar-09 7-Apr-09 Closed undeterminated
Non conformance of Sonic Test results with the ratings Criteria on Method
32 MNC-ACT-BBI-NCR-FON-025 DW-CB Panels P13
statement
BSV 19-Jan-09 C 26-Mar-09 7-Apr-09 Closed undeterminated
Defective Hollow Sections 300x300x16mm not conforming on the quality Waiting for approval of the
34 MNC-ACT-BBI-NCR-FON-029 Bored Pile 300x300
base on the UT conducted
C&T 16-Jan-09 O 23-May-09
proposed disposition
Quality of Material
35 MNC-ACT-BBI-NCR-FON-030 Bored Pile BP 43 Pouring without Stanchions BVN 27-Feb-09 C 20-Mar-09 26-Mar-09 Closed Method Statement Implementation
Non-conformance of M27*100 (abp) bolts Tensile strength test results Waiting for completion of
38 MNC-ACT-BBI-NCR-FON-033 Bored Pile S54-S32-S72-S68
with the raiting criteria on the design drawing
EEI 13-Mar-09 O 20-Mar-09
the work
Quality of Material
Non conformance of Sonic Test results with the ratings Criteria on Method
39 MNC-ACT-BBI-NCR-FON-034 Bored Pile BP136
statement
BVN 20-Mar-09 C 14-Apr 17-Apr-09 Closed Method Statement Implementation
41 MC-BBI-Q+-NC-BA-FON-023 Bored Pile BP 141 139 144 142 Non conformance of steel cages top level BVN 7-May-09 S 16-Jun-09 16-Jun-09 Closed Method Statement Implementation
43 MC-BBI-Q+-NC-BA-FON-025 Bored Pile BP 146 Shaft grouting work not as per design, tube No 7, 1 and 6 BVN 28-May-09 C 10-Aug-09 14-Sep-09 Closed Method Statement Implementation
44 MC-BBI-Q+-NC-PO-GEN-026 DW-CB CB 12 & CB 11 16 starters bars located on the top of the d-wall are broken HBC 15-Jun-09 O 17-Jun-09 11-Aug-09 Closed Method Statement Implementation
One water stop was not poured inside CB 11. Incorect installation of Waiting for completion of
46 MC-BBI-Q+-NC-PO-GEN-038 DW-CB CB 11
formwork
HBC june F 21-Sep-09
the work
Method Statement Implementation
47 MC-BBI-Q+-NC-BA-FON-041 Bored Pile S40 Starter bars were cut HBC 21-Jul-09 O 22-Jul-09 11-Aug-09 Closed Workmanship
49 MC-BBI-Q+-NC-PO-GEN-043 DW-CB D'wall P01 P02 & P09 Broken bars during straightening up HBC 30-Jul-09 O 1-Aug-09 17-Aug-09 Closed Workmanship
date happened
Contractor
Starter bars
Form work
Concreting
Steel fixing
Date of
Setting out
Reference Number Scope Location Description Date issued Date cleared Status NCR canceled Causes
Proposition
Cracks
Other
Surface of P05 is not aligned with adjacent one and theoritical position of
50 MC-BBI-Q+-NC-BA-FON-044 DW-CB P05
CB, the deviation is about 50mm comparing to the outer concrete surface.
BSV 1-Aug-09 C 6-Aug-09 14-Sep-09 Closed Workmanship
The bars HA20 reference 36 were not installed in the first casting of
52 MC-BBI-Q+-NC-PO-GEN-059 DW-CB CB 3
Capping Beam CB3.
HBC 7-Sep-09 S 9-Sep-09 14-Sep Closed Document
Water leakage of the connection between capping beam and diaphragm Pending proposed
53 MNC-ACT-BBI-NCR-FON-071 DW-CB North and East area
wall .
HBC 22-Sep-09 C 30-Sep-09
disposition
Workmanship
Spacing of starter bar, in cases between 2 successive panels, 2 steel cages septembr Waiting for completion of
54 MC-BBI-Q+-NC-BA-B02-066 DW-CB Panel 35 to 46
or tremie pipes, is longer than 500mm.
BSV
e 2008
10-Nov-09 S 13-Nov-09
the work
Workmanship
Some rebars are not aligned with the rest and are coming out of the frame
57 MC-BBI-Q+-NC-PO-GEN-028 Transfer cap TC 20,21
of 5 to 8 cm because the reinforcement bars were too long.
HBC Jun 25-Jun-09 S 25-Jun-09 11-Aug-09 Closed Method Statement Implementation
Two missing column hooks at first layer and hooks reference 32 not closed
58 MC-BBI-Q+-NC-PO-GEN-030 Transfer Cap TC 10
properly.
HBC Jul 7-Jul-09 S 22-Jul-09 7-Aug-09 Closed Workmanship
Hooks HA 16 reference 25 are not installed properly: one side of the hooks
59 MC-BBI-Q+-NC-PO-GEN-031 Transfer cap TC 9
is not bent into the column.
HBC Jul 7-Jul-09 S 10-Jul-09 11-Aug-09 Closed Workmanship
60 MC-BBI-Q+-NC-PO-GEN-032 Transfer cap TC 10 Formwork was not closed properly. Tie rods missing HBC Jul 7-Jul-09 F 22-Jul-09 7-Aug-09 Closed NCR ACT 049 Workmanship
61 MC-BBI-Q+-NC-PO-GEN033 Transfer cap G106/ TC10 Installation of starter bars for G106 without ACT Approval BBI Jul 11-Jul-09 O 14-Jul-09 7-Aug-09 Closed NCR ACT 048 Method Statement Implementation
65 MC-BBI-Q+-NC-PO-GEN-037 Transfer cap TC 15 The installed starter bar of ground beam G84 from TC 15 is too high HBC Jul 18-Jul-09 S Sr 31-Jul-09 Closed NCR ACT 053 Shop Drawings Conformity
66 MC-BBI-Q+-NC-PO-GEN-039 Transfer cap TC 18 Column hooks not closed properly at layers 11 to 17 at reference 24. HBC Jul 20-Jul-09 S 5-Aug-09 11-Aug-09 Closed Shop drawings conformity
67 MC-BBI-Q+-NC-PO-GEN-040 Transfer cap Tc 10 Bar reference 15 not installed in first casting HBC Jul 20-Jul-09 S 3-Aug-09 7-Aug-09 Closed NCR ACT 057 Shop drawings conformity
69 MNC-ACT-BBI-NCR-FON-055 Slab & Beam P 09 Piezometer P. 09 does not confirm with Method statement HBC Jul 23-Jul-09 O 15-Sep-09 17-Nov Closed Method Statement Implementation
Thread rebar diameter 25 is to close to the stanchion: can't install the Pending proposed
70 MC-BBI-Q+-NC-BA-B02-083 Transfer cap C73
coupler
HBC Jul 19-Dec-09 S disposition
Workmanship
Installation of sheet piles at west area not according to the method Pending proposed Waiting for SIDF
71 MNC-ACT-BBI-NCR-FON-056 Slab & Beam
statement
HBC Jul 25-Jul-09 O disposition DRR
Method Statement Implementation
The installed starter bar of the beam G95 from transfer cap TC05 are
72 MC-BBI-Q+-NC-PO-GEN-045 Transfer cap TC 05
wrong position (235mm from the side of the beam)
HBC Aug 1-Aug-09 S Sr 3-Aug-09 17-Aug-09 Closed Workmanship
74 MNC-ACT-BBI-NCR-FON-059 Slab & Beam Slab 2.1 Structural cracks are found at the soffit of slab 2.1 HBC Aug 6-Aug-09 Cr 4-Sep-09 14-Sep Closed Undeterminated
75 MC-BBI-Q+-NC-PO-GEN-046 Transfer Cap G 33 Starter bars touching soffit of beam formwork HBC Aug 11-Aug-09 S Sr 13-Aug-09 14-Sep Closed Workmanship
76 MC-BBI-Q+-NC-PO-GEN-047 Transfer Cap TC2 G76 Starter bars touching soffit of beam formwork HBC Aug 13-Aug-09 S Sr 20-Aug-09 14-Sep Closed Shop drawings conformity
77 MC-BBI-Q+-NC-PO-GEN-048 Transfer Cap G 30 Starter bars touching soffit of beam formwork HBC Aug 14-Aug-09 S Sr 17-Aug-09 14-Sep Closed Shop drawings conformity
Starter bars of beam G46 have not been installed during the 1st casting of
78 MC-BBI-Q+-NC-PO-GEN-049 Transfer Cap G 46
Tower Crane pad 2.
HBC Aug 14-Aug-09 S Sr 19-Aug-09 14-Sep Closed Shop drawings conformity
79 MC-BBI-Q+-NC-PO-GEN-050 Transfer Cap G 55 Starter bars touching soffit of beam formwork HBC Aug 19-Aug-09 S Sr 20-Aug-09 14-Sep Closed Shop drawings conformity
The downstand beam incorporated in the temporary slab over the ramp void
80 MC-BBI-Q+-NC-PO-GEN-051 Slab & Beam Slab 2.5
is offset by 300mm
HBC Aug 27-Aug-09 SO 27-Aug-09 7-Sep Closed Shop drawings conformity
81 MC-BBI-Q+-NC-PO-GEN-052B Transfer cap Wall 19 transfer core Embedded plate forgotten HBC Aug 20-Aug-09 S 31-Aug-09 7-Sep Closed Shop drawings conformity
82 MC-BBI-Q+-NC-PO-GEN-053 Transfer cap TC 3 Starters bars missing during the first casting of TC 3 HBC Aug 22-Aug-09 S Sr 31-Aug-09 7-Sep Closed Shop drawings conformity
83 MC-BBI-Q+-NC-PO-GEN-055 Transfer cap wall 19 20 transfer core Cross head bars were not installed in the 1st castiong step HBC Aug 24-Aug-09 S 26-Aug-09 14-Sep Closed Shop drawings conformity
Pending proposed
86 MNC-ACT-BBI-NCR-FON-062 Slab & Beam Slab 1.4 Long Crack on surface of Slab 1.4 HBC Aug 28-Aug-09 Cr disposition
Undeterminated
87 MNC-ACT-BBI-NCR-FON-063 Verticals TC 15 Lightning Reinforcement rod is out of column position HBC Aug 28-Aug-09 S 10-Sep-09 14-Sep Closed Workmanship
Pending proposed
88 MNC-ACT-BBI-NCR-FON-064 Slab & Beam Slab 1.3 Long crack on surface of slab 1.3 HBC Aug 31-Aug-09 Cr disposition
Undeterminated
Construction Joint between slab 1.3 and slab 2.5 does not conform with Pending proposed
89 MNC-ACT-BBI-NCR-FON-065 Slab & Beam Slabs 1.3 / 2.5
requirement
HBC Aug 31-Aug-09 C disposition
Undeterminated
Pending proposed
90 MNC-ACT-BBI-NCR-FON-066 Slab & Beam Slab 1.1 Long crack on soffit of slab 1.1 HBC Aug 31-Aug-09 Cr disposition
Undeterminated
91 MC-BBI-Q+-NC-PO-GEN-056 Transfer cap C 18 C19 Starter bars misplaced HBC Aug 5-Sep-09 S Sr 8-Sep-09 14-Sep Closed Shop drawings conformity
92 MC-BBI-Q+-NC-PO-GEN-057 Transfer cap C24,25,26,27 Starter bars too short HBC Aug 5-Sep-09 S Sr 8-Sep-09 14-Sep Closed Shop drawings conformity
93 MC-BBI-Q+-NC-PO-GEN-060 Transfer cap C10 and 32 Starter bars of the column are too short HBC Aug 9-Sep-09 S Sr 12-Sep-09 16-Oct Closed Shop drawings conformity
C 1, 2, 3, 4, 5, 8, 9, 12,
94 MC-BBI-Q+-NC-PO-GEN-062 Transfer cap
13, 14
Starter bars of the coulumn are too short HBC Aug 11-Sep-09 S Sr 12-Sep-09 16-Oct Closed Shop drawings conformity
Some specing between consecutive vertical rebars of the columns are too Waiting for completion of to be close during
95 MC-BBI-Q+-NC-BA-B02-076 Transfer cap C30 C23
large (due to installation of bars in the TC)
HBC Aug 28-Nov-09 S Sr 9-Dec-09
the work columns casting
Method Statement Implementation
Lack of one starter rebar coupler (diameter 16) of ground floor corewall at Waiting for approval of the
96 MC-BBI-Q+-NC-BA-B02-081 Transfer cap Wall 19/21 transfer core
connection W19 and W21
HBC Aug 17-Dec-09 S 19-Dec-09
proposed disposition
Workmanship
98 MC-BBI-Q+-NC-PO-GEN-058A Transfer cap W19 transfer core Starter bar installation not as per the design HBC Sept 6-Sep-09 S Sr 8-Sep-09 16-Oct Closed Shop drawings conformity
99 MNC-ACT-BBI-NCR-FON-067 Verticals C28 Segregation of concrete HBC Sept 5-Sep-09 C 1-Oct-09 24-Oct Closed Undeterminated
100 MC-BBI-Q+-NC-PO-GEN-061 Transfer cap W45 transfer core Expansion wall of W45 - Missing Starter Bars HBC Sept 11-Sep-09 S 12-Sep-09 16-Oct Closed Shop drawings conformity
101 MNC-ACT-BBI-NCR-FON-068 Transfer cap W11 transfer core Cavity in core Wall 11 under Beam G86 HBC Sept 11-Sep-09 F 15-Sep-09 23-Oct Closed Method Statement Implementation
Pending proposed
104 MNC-ACT-BBI-NCR-FON-069 Transfer cap TC08 TC 15 Structure Crack at Transfer Cap TC.8 HBC Sept 22-Sep-09 Cr disposition
Undeterminated
Pending proposed
105 MNC-ACT-BBI-NCR-FON-070 Transfer cap TC18 Structure Crack at Transfer Cap TC.18 HBC Sept 22-Sep-09 Cr disposition
Undeterminated
Pending proposed
106 MNC-ACT-BBI-NCR-FON-072 Transfer cap TC4 Structure Crack at Transfer Cap TC4 HBC Sept 24-Sep-09 Cr disposition
Undeterminated
U bars diameter 14 for 1st floor slab installed in the corewall not installed
109 MC-BBI-Q+-NC-PO-001-067B Core wall W 45, 20, 10, 13, 1 at the correct level and some of them have not been installed during the HBC Oct 2-Dec-09 S Sr 2-Dec-09 17-Dec Closed Document
corewall casting
U bars diameter 14 for 1st floor slab installed in the corewall not installed
110 MC-BBI-Q+-NC-PO-001-068B Core wall W11 W1a at the correct level and some of them have not been installed during the HBC Oct 10-Nov-09 S Sr 12-Nov-09 17-Dec Closed Document
corewall casting
Pending proposed
111 MC-BBI-Q+-NC-BA-B02-082 Transfer cap Wall 17/20 transfer core Couppler rebar dIameter 20 was broken during chipping of lean concrete HBC Oct 18-Dec-09 O disposition
Workmanship
7 bars of the columns C3 and C5 have been bended by oxygen, in order to Pending proposed Waiting for
114 MC-BBI-Q+-NC-BA-B02-070 Verticals C3 & C5
rectify the coupler implemantation.
HBC Nov 18-Nov-09 S disposition stamped report
Method Statement Implementation
Starter bars
Form work
Concreting
Steel fixing
Date of
Setting out
Reference Number Scope Location Description Date issued Date cleared Status NCR canceled Causes
Proposition
Cracks
Other
Pending proposed
117 MNC-ACT-BBI-NCR-FON-074 Core wall OFF: 2F - 3F Concrete of core wall had been separated during slipping Fuvi Nov 20-Nov-09 C disposition
Method Statement Implementation
The casted concrete of Bay 1 - 1st floor slab had wooden parts in the Pending proposed
118 MC-BBI-Q+-NC-PO-001-073 Slab & Beam Bay 1 and 2
concrete surface.
Holcim Nov C disposition
Method Statement Implementation
POUR BREAK @BAY Additional bars reference 58 at top l ayer for pouring break (T10-250) for
119 MC-BBI-Q+-NC-PO-001-074 Slab & Beam
1 - 1st floor first floor slab was not installed during slab bay 1 pouring
HBC Nov 24-Nov-09 S 1-Dec-09 17-Dec Closed Document
2 starter bars diameter 14 for first floor slab installed in PT beamF1. PT 40 Waiting for approval of the
120 MC-VSL-Q+-NC-PO-001-001 Slab & Beam Bay 4 gridline C/2
are damaged partly when VSL labours doing strand cutting work.
VSL Nov 28-Nov-09 S proposed disposition
Workmanship
U staerter bars ref 1a and ref 1 for 2nd floor slabs installed in corewall not
W1a W11 W24 W25 installed at the correct level and some of them have not been installed Waiting for approval of the
121 MC-BBI-Q+-NC-PO-002-085 Core wall
(residential) during during core wall realisation; and some starter bars were broken
HBC Nov 23-Dec-09 S Sr 7-Jan-10
proposed disposition
Workmanship
during rebending to straight.
U staerter bars ref S13 for 2nd floor slabs installed in corewall not installed
Inside the core: W6 W23 at the correct level and some of them have not been installed during during Waiting for approval of the
122 MC-BBI-Q+-NC-PO-002-086 Core wall
W16a W21a W5 W15 core wall realisation; and some starter bars were broken during rebending
HBC Nov 23-Dec-09 S Sr 7-Jan-10
proposed disposition
Workmanship
to straight.
Pending proposed
123 MC-BBI-Q+-NC-PO-001-077 Core wall A lot of oil leak on surface concrete and rebars Fuvi Nov 2-Dec-09 O disposition
Workmanship
Pending proposed
124 MC-BBI-Q+-NC-BA-002-079 Slab & Beam B02 - Bay 5 Long crack on the surface of Basement 2 bay 5 HBC Dec 11-Dec-09 Cr disposition
NCR ACT 075 Undeterminated
Starter bars with coupler 3x3 HA32 for the beam F1.12 installed in Pending proposed
125 MC-BBI-Q+-NC-PO-001-080 Core wall beam F1.12 connection
corewall are wrong size (the couplers installed in core wall are 3x3 HA36)
CANCELED S disposition
Workmanship
Pending proposed
126 MC-BBI-Q+-NC-BA-B02-084 Slab & Beam B 02 Bay 8 along PT 23 Some cracks are found on slab of basement 2 - bay 8, along PT beam HBC dec 21-Dec-09 Cr disposition
NCR ACT 078 Undeterminated
Dimension of column at conjunction between C33 and beam F1.48 is Pending proposed
128 MNC-ACT-BBI-NCR-FON-077 Slab & Beam 1st floor Bay 4
insufficient
HBC Dec 22-Dec-09 C disposition
Workmanship
Pending proposed
129 MNC-ACT-BBI-NCR-BA-B02-079 Slab & Beam 2nd Basement Bay 1 Crack on the surface of Storm water tank slab HBC Dec 26-Dec-09 Cr disposition
Undeterminated
Pending proposed
130 MNC-ACT-BBI-NCR-BA-B02-080 Slab & Beam 2nd Basement Bay 3,4 Crack on the surface of slab at Basement 2 HBC Dec 28-Dec-09 Cr disposition
Undeterminated
Starter bars with coupler ref 113 of the W8 installed in Column c34 not Pending proposed
132 MC-BBI-Q+-NC-PO-GFL-089 Verticals C34
installed at the correct position after installation of column formwork
HBC Dec 30-Dec-09 S Sr disposition
Method Statement Implementation
Pending proposed
133 MC-BBI-Q+-NC-PO-GFL-090 Transfer cap TC21 coring rebar Dec Cr disposition
Workmanship