Guarantee Engineers (Pvt) Ltd

Project :
BOQ Item#
Subject : Rate analysis of Proving, cutting, bending and fixing in position of 60 Grade steel rebars

Unit = 1.0 Ton

Description of Work Unit Qty Rate Amount

60-G Steel Rebars Ton 1.00 x 122,000 Rs. 122,000

Wastage+Chairs, Spacer Bars Etc @5% Ton 0.05 x 122,000 Rs. 6,100

Binding Wire Kg 10.00 x 180 Rs. 1,800

Labor for Fixing Ton 1.00 x 7,000 Rs. 7,000

Carrage+Loading, Unloading Ton 1.00 x 600 Rs. 600

T&P L/S 250

Electricity Charges L/S 150

Total Amount Rs. 137,900

Contractor Profit and Overhead @ 25% Rs. 34,475

Total amount i/c OH 172,375

Income Tax @ 7% (7.52% of Total Amount) 12,974

Total Cost: Rs. 185,349

Cost per KG: Rs. 185

Submitted By Approved By