Академический Документы
Профессиональный Документы
Культура Документы
1
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
3.3.1.4 Cumulative Impacts............................................................................................. 31
3.3.2 Issue 2: What are the Potential Impacts of Oil and Gas Leasing to Climate
Change/Greenhouse Gases? .................................................................................................. 34
3.3.2.1 Affected Environment ......................................................................................... 34
3.3.2.2 Environmental Consequences ............................................................................. 36
Impacts of the Proposed Action ........................................................................................ 36
Impacts of the No Alternative Action ............................................................................... 38
3.3.2.3 Required Design Features/Mitigation Measures ................................................. 38
3.3.2.4 Cumulative Impacts............................................................................................. 38
Chapter 4 Consultation and Coordination ............................................................................... 42
4.1 Introduction .................................................................................................................... 42
4.2 Persons, Groups, and Agencies Contacted/Consulted ................................................... 42
4.2.1 Endangered Species Act of 1973 ............................................................................ 42
4.2.2 National Historic Preservation Act (NHPA) of 1966 ............................................. 42
4.3 Public Participation ........................................................................................................ 47
4.3.1 Modifications Based on Public Comment and Internal Review [Reserved] .......... 47
4.4 Preparers ......................................................................................................................... 47
Chapter 5 Appendices .............................................................................................................. 49
Appendix A – Parcel List with Stipulations and Notices ..................................................... 50
Appendix B – Stipulations and Notices ................................................................................ 68
Stipulation Summary Table .............................................................................................. 68
Notice Summary Table ..................................................................................................... 86
Threatened and Endangered Species Notices ................................................................. 104
Appendix C – Figures/Maps ............................................................................................... 112
Appendix D – Interdisciplinary Parcel Review Team Checklist ........................................ 115
Appendix E – References.................................................................................................... 128
Appendix F – Acronyms/Abbreviations ............................................................................. 136
Appendix G – Reasonable Foreseeable Development of Leases Scenario......................... 138
5.1.1 Well Drilling and Completion Operations ............................................................ 138
5.1.2 Production Operations .......................................................................................... 140
5.1.3 Produced Water Handling ..................................................................................... 140
5.1.4 Maintenance Operations ....................................................................................... 141
5.1.5 Plugging and Abandonment .................................................................................. 141
2
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Appendix H – Comments and Responses [reserved].......................................................... 142
List of Tables
Table 1. Issues Identified for Detailed Analysis ........................................................................... 10
Table 2. Issues not included in Further Detail in the Environmental Assessment ....................... 12
Table 3. Leasing Category Acreages for Monticello Field Office................................................ 24
Table 4. Leasing Category Acreages by Parcel. ........................................................................... 24
Table 5. AQI Index Summary Statistics by County ..................................................................... 26
Table 6. 2015-2017 Criteria Pollutant Design Values .................................................................. 26
Table 7. 2014 Criteria Air Pollutant Emissions (tpy) by Source for San Juan County ................ 27
Table 8. Triennial Inventory of HAPs (2014). .............................................................................. 27
Table 9. Emissions Inventory Estimate. ....................................................................................... 29
Table 10. Climate Trends .............................................................................................................. 35
Table 11. GHG Emission in Million Metric Tons (CO2e) ............................................................ 36
Table 12. Single Well GHG Emissions Based on the Moab MLP FEIS Inventory ..................... 36
Table 13. Production of Oil and Gas for a Single Well and Associated GHG Combustion
Emissions ...................................................................................................................................... 37
Table 14. Annual Cumulative GHG Emissions from Oil and Gas Wells. .................................... 39
Table 15. Comparison of Cumulative Annual Emissions with State and National Emissions..... 39
Table 16. Lease Sale Emissions Compared to the Cumulative, State, and U.S. Emissions ......... 39
Table 17. List of Contacts and Findings. ...................................................................................... 44
Table 18. Preparers of This EA..................................................................................................... 47
List of Figures
Figure 1. ARMS predicted ozone design values with on the books controls for oil and gas
emissions in the year 2021. ........................................................................................................... 32
Figure 2. ARMS predicted PM2.5 design values with on the books controls for oil and gas
emissions in the year 2021. ........................................................................................................... 33
Figure 3. Potential for climate change impacts for the Colorado Plateau .................................... 40
Figure 4. Lease Sale Parcel Overview. ....................................................................................... 113
Figure 5. Hovenweep Viewshed Analysis .................................................................................. 114
3
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Environmental Assessment
DOI-BLM-UT-000-2019-0003-OTHER_NEPA_MtFO-EA
1.3 Background
This EA analyzes 19 nominated parcels comprising of 32,067.42 acres for the lease sale that are under the
administration of the MtFO. The 19 parcels were determined to be open to leasing for oil and gas
development under the applicable plans. The mineral rights for these parcels are owned by the federal
government and administered by the MtFO. The legal descriptions of the nominated parcels are in
Appendix A.
During the land use planning process the BLM decides which public lands and minerals are open for
leasing and under what terms and conditions. In accord with Resource Management Plans (RMPs), lands
can be deemed open to leasing under standard terms and conditions, closed to leasing, or open under
special operating constraints identified as lease stipulations at the lease stage. Lease stipulations are used
to mitigate potential impacts to resources. Any surface management of non- BLM administered land
overlaying federal minerals is determined by the BLM in consultation with the appropriate surface
management agency or the private surface owner.
The Mineral Leasing Act of 1920 (MLA), as amended [30 U.S.C. 181 et seq.], and the Federal Onshore
Oil and Gas Leasing Reform Act of 1987 (FOOGLRA), require the BLM UTSO to conduct quarterly,
competitive lease sales to offer available oil and gas lease parcels in Utah. Expressions of Interest (EOI)
1
The DNA and all documents pertaining to the March 2019 analysis can be found on BLM’s ePlanning site at
http://go.usa.gov/xPfJg
2 Significance is defined by NEPA, and is found in 40 Code of Federal Regulations (CFR) 1508.27
4
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
to nominate parcels for leasing by the BLM are submitted by the public. From these EOIs, the BLM
prepares the parcels and determines whether or not the existing analyses in the LUPs, as amended,
provide basis for leasing oil and gas resources within these parcels or if additional NEPA analysis is
needed before making a leasing decision.
In the process of preparing a lease sale, the UTSO compiles a list of lands nominated by the public,
legally available for leasing, and sends a preliminary parcel list to the appropriate District Office where
the parcels are located. Field Office staff reviews the legal descriptions of the parcels to determine if they
are in areas open to leasing under the relevant RMP, ensures appropriate stipulations have been applied
and identify any special resource conditions of which potential bidders should be made aware. Standard
lease terms also provide for reasonable measures to minimize adverse impacts to specific resource values,
land uses, or users (Standard Lease Terms are contained in Form 3100-11, Offer to Lease and Lease for
Oil and Gas, U.S. Department of the Interior, BLM, October 2008 or later edition). Compliance with
valid, nondiscretionary statutes (laws) is included in the standard lease terms.
Once the Field Offices completed the interdisciplinary parcel review (IDPR), the BLM determined that
preparation of an EA was necessary for considering the parcels within MtFO. This EA and an unsigned
FONSI are made available to the public, along with the list of available parcels and stipulations and
notices, for a 30-day public comment period on the BLM’s NEPA Register 3 (also known as ePlanning).
The UTSO Oil and Gas Leasing webpage 4 is also updated and maintained for the lease sale. Additional
information regarding the BLM’s leasing process is also made available for public review and reference.
At the end of the public comment period, the BLM analyzes and incorporates the comments, where
appropriate, into the EA and/or parcel list. The final parcel list with stipulations and notices is made
available to the public through a Notice of Competitive Lease Sale (NCLS), which starts a 30-day protest
period, and includes the revised EA and unsigned FONSI. If any changes to the parcels or
stipulations/notices result from the protests, an erratum to the NCLS would be posted to the BLM website
and on NEPA Register to notify the public of the change, prior to the lease sale. The parcels would be
available for sale at an online auction held by the BLM, tentatively scheduled for September 11, 2019.
If the parcel is not purchased at the lease sale by through the competitive bidding process, it may still be
leased non-competitively within two years after the initial offering at the minimum bid cost. Parcels
obtained non-competitively may be re-parceled by combining or deleting other previously offered lands.
Mineral estate that is not leased within a two-year period after an initial offering will no longer be
available and must go through another separate competitive lease sale process prior to being leased.
An issued lease may be held for ten years, after which the lease expires unless oil or gas is produced in
paying quantities (43 CFR 3107.2). A producing lease can be held indefinitely by economic production.
The act of leasing does not authorize any development or use of the surface of lease lands without further
application by the operator and approval by the BLM. In the future, operators must submit an Application
for Permit to Drill (APD) (Form 3160-3) to the BLM for approval and must possess an approved APD
prior to any surface disturbance in preparation for drilling. 5 An APD may only be approved when an
operator complies with any stipulations and/or notices attached to the standard lease form. If an APD is
received, the BLM would conduct additional site-specific NEPA analysis before deciding whether to
approve the APD, and what conditions of approval (COA) should apply.
Following BLM’s approval of an APD, a lessee may produce oil and gas from the well in a manner
approved by the BLM in the APD or in subsequent sundry notices. The operator must notify the
3
The NEPA Register is a BLM environmental information internet site and can be accessed online at: https://bit.ly/2Z5PlYd
4 UTSO Oil and Gas Leasing program webpage can be accessed at: http://go.usa.gov/xXk8c
5
Additional Information regarding the BLM’s oil and gas management program can be accessed online at:
https://www.blm.gov/programs/energy-and-minerals/oil-and-gas/
5
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
appropriate BLM authorized officer 48 hours before starting any surface disturbing activity approved in
the APD.
Standard lease terms provide for reasonable measures to minimize adverse impacts to specific resource
values, land uses, or users. Compliance with valid, nondiscretionary statutes (laws) is included in the
standard lease terms. Nondiscretionary actions include the BLM’s requirements under federal
environmental protection laws, such as Clean Water Act, Clean Air Act, Endangered Species Act,
National Historic Preservation Act, and Federal Land Policy and Management Act, which are applicable
to all actions on federal lands, including split estate. Also included in all leases are two mandatory
stipulations for the statutory protection of cultural resources and threatened or endangered species
(Handbook H-3120-1).
Once the lease has been issued, the lessee has the right to use as much of the leased land as necessary to
explore for, drill for, extract, remove, and dispose of oil and gas deposits located under the leased lands,
subject to the standard lease terms and additional restrictions attached to the lease in the form of lease
stipulations (S) (43 CFR 3101.1-2) and lease notices (LN) (43 CFR 3101.1-3). Even if no restrictions are
attached to the lease, the operations must be conducted in a manner that avoids unnecessary or undue
degradation of the environment and minimizes adverse impacts to the land, air, water, cultural, biological,
and visual elements of the environment, as well as other land uses or users.
1.4 Purpose and Need
The purpose of this action is for the UTSO to respond to the nominations or expressions of interest for oil
and gas leasing on specific federal mineral estate through a competitive leasing process and either lease or
defer from leasing, pending additional information. The need for the Proposed Action is established by
the BLM’s responsibility under the MLA of 1920, as amended, the Mining and Minerals Policy Act of
1970 as amended, the Federal Onshore Oil and Gas Leasing Reform Act of 1987 (Reform Act) as
amended, and Federal Land Policy and Management Act of 1976 as amended, and to promote the
development of oil and gas on the public domain. Parcels may be nominated by the public, the BLM or
other agencies. The MLA establishes that deposits of oil and gas owned by the United States are subject
to disposition in the form and manner provided by the MLA under the rules and regulations prescribed by
the Secretary of the Interior, where consistent with FLPMA and other applicable laws, regulations, and
policies.
1.5 Decision to be Made
Following the completion of the NEPA process the BLM would determine whether or not to lease the
nominated parcels and, if so, under what lease terms and conditions (stipulations and/or notices). In order
to make an informed decision, the BLM is using this EA to identify the environmental impacts of the
Proposed Action and its alternatives. This EA analyzes two alternatives. The first alternative analyzed is
the Proposed Action, the second is Alternative B, the No Action Alternative.
6
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
• Bald and Golden Eagle Protection Act of 1962 (BGEPA)
• Endangered Species Act of 1973 (ESA)
• Migratory Bird Treaty Act of 1918 (MBTA)
• Clean Water Act of 1972 (CWA)
Regulations
• 40 CFR Part 93 Subpart E
• 43 CFR 1600
• 43 CFR 3100
• 40 CFR 1500 – 1508
• 40 CFR 104
• 36 CFR 800
• 36CFR 60.4
Manuals6
• BLM Manual 6840 – Special Status Species
• BLM Manual 3120 – Competitive Leasing
• BLM Manual 6310 - Conducting Wilderness Characteristics Inventory of BLM Lands
• BLM Manual 6320 - Considering Lands with Wilderness Characteristics in the BLM Land Use
Planning Process
Handbooks 7
• Competitive Leasing Handbook (H-3120-1)
Policies/Instruction Memoranda (IM) 8
• Updating Oil and Gas Leasing Reform – Land Use Planning and Lease Parcel Reviews (WO IM
2018-034)
• Directional Drilling into Federal Mineral Estate from Well Pads on Non-Federal Locations (WO
IM 2018-014)
• Oil and Gas Leasing Program NEPA Procedures Pursuant to Leasing Reform (UT IM 2014-006)
• Utah Riparian Management Policy (2006)
• Utah’s Standards for Rangeland Health (1997)
• Utah BLM Drinking Water Source Protection Zone (2010)
• Secretarial Order 3355 Streamlining NEPA (2017)
• Secretarial Memorandum August 6, 2018, Streamlining Environmental Assessments
• Protection of Ground Water Associated with Oil and Gas Leasing, Exploration and Development
(BLM UT IM 2010–055)
• BLM Utah Guidance for Lands with Wilderness Characteristics Resource (UT IM 2016-027)
• Updated BLM Sensitive Species Lists for Utah (UT IM 2019-005)
6
BLM manuals can be accessed online at: https://www.blm.gov/media/blm-policy/manuals.
7
BLM handbooks can be accessed online at: https://www.blm.gov/media/blm-policy/handbooks.
8
BLM instruction memoranda and information bulletins can be accessed online at:
https://www.blm.gov/media/blm-policy/instruction-memorandum and https://www.blm.gov/media/blm-
policy/information-bulletin.
7
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Agreements
• MOU Among the United States Department of Agriculture, the United States Department of
Interior and the United States Environmental Protection Agency Regarding Air Quality Analysis
and Mitigation for Federal Oil and Gas Decisions through the NEPA Process (2011)
• State Protocol Agreement Between the Utah State Director of the Bureau of Land Management
and the Utah State Historic Preservation Officer Regarding the Manner in which the BLM Will
Meet its Responsibilities Under the National Historic Preservation Act and the National
Programmatic Agreement Among the BLM, the Advisory Council on Historic Preservation and
the National Conference of State Historic Preservation Officers (2001)
• MOU between the USDI BLM and USFWS to Promote the Conservation and Management of
Migratory Birds (April 2010)
8
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
actions align with the following BLM Land Use Plans within the designated Field Office boundaries (43
CFR 1610.5, BLM 1617.3).
9
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
• 2008 Biological Opinion for the MtFO RMP 9 (BLM 2008)
• March 2019 Lease Sale Cultural Resources Report (Utah SHPO Case No. 19-0235) (BLM 2019)
In order to reduce redundant paperwork and analysis in the NEPA process (See 40 CFR 1502.20 and
1502.21) the previous documents and their associated information or analysis are hereby incorporated by
reference. The attached IDPR Checklist, Appendix D, was also developed after consideration of these
documents and their contents.
1.8 Issues Identified
Identification of issues, concerns, and potential impacts that require detailed analysis was accomplished
through internal review/discussion. The UTSO sent letters/ memorandum to the following stakeholders:
the National Park Service (NPS), the United States Fish and Wildlife Service (USFWS), the United States
Forest Service (USFS), the State of Utah’s Public Lands Policy Coordination Office (PLPCO), Division
of Wildlife Resources (UDWR), and the School Institutional Trust Lands Administration (SITLA) to
notify them of the pending lease sale, and solicit comments and concerns on the preliminary parcel list.
The BLM also provided GIS shapefiles depicting the proposed sale parcels to contacts within the NPS
and UDWR. Consultation and coordination efforts are summarized in Chapter 4, Table 17.
The UTSO received the September 2019 lease sale parcel nomination list on April 1, 2019.
Internal scoping was initiated on April 5, 2019 when the nominated lease parcels for the September 2019
competitive oil and gas lease sale were presented to the MtFO Interdisciplinary (ID) Team. Resource
specialists on the ID teams helped identify the following issues through coordination, and meetings.
The key issues identified through the scoping process were developed using the guidelines set forth in
section 8.3.3 of the BLM NEPA Handbook and EA are summarized in Table 1 and Table 2, below.
Table 1. Issues Identified for Detailed Analysis
Air Quality What quantity of air pollutants would be Tons per year of PM-10,
produced based on the reasonably PM-2.5, NO X, SO2, CO,
foreseeable development (RFD) scenario? VOCs, HAPs.
How would air pollutant emissions from
subsequent development of leased parcels
affect air quality?
Greenhouse What quantity of greenhouse gas emissions Metric tons (MT) or million
Gas/Climate Change (GHG) would be generated from subsequent metric tons (MMT) per year of
oil and gas development of leased parcels carbon dioxide equivalents
based upon the RFD scenario? How do (CO2eq)
these amounts compare to other sources of
GHGs?
9
MtFO ROD, RMP/FEIS is located on ePlanning at https://eplanning.blm.gov/epl-front-
office/eplanning/planAndProjectSite.do?methodName=dispatchToPatternPage¤tPageId=98873
10
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
1.9 Issue Statement Rationale for Not Further Discussing in Detail in the EA 10
Where resources are present but not determined to be impacted or resources are determined not to be
present, a rationale for not considering them further is provided in the Interdisciplinary Parcel Review
Team (IDPRT) checklist (Appendix D ), and in the external coordination as described in Table 17. Table
2 highlights key issues evaluated and not discussed in further detail in this EA for the resources the BLM
commonly receives public comments and/or interests. These resources are described below in Table 2.
10
Refer to the IDPRT checklist (Appendix D ) for the complete rational for resources identified for analysis and
resources not considered for further detailed analyses.
11
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Table 2. Issues not included in Further Detail in the Environmental Assessment
Issue Issue Statement Rationale for Not Further Discussing in Detail in the EA
T&E Species What are the potential The parcels involved in the September 2019 lease sale were analyzed individually within each field office
impacts to federally-listed for occurrence of federally-listed species, in coordination with the USFWS. The Threatened and
threatened and Endangered Species Act Stipulation is applied across all lease parcels which states that if any parcel is
endangered species or found to contain plants, animals or their habitats determined to be threatened, endangered or special
habitats in areas related to status species, the BLM may recommend modifications to exploration and development proposals to
oil and gas development? further its conservation and management objective. Under this stipulation, the BLM may also require
modifications to or disapprove proposed activity that is likely to result in jeopardy to the continued
existence of a proposed or listed threatened or endangered species, or result in destruction or adverse
modification of a designated or proposed critical habitat.
As appropriate, BLM attaches stipulations or notices to the lease which give notice to the lessor/operator
of potential for occurrence of federally-listed species, and measures that may be required to mitigate
impacts.
The BLM will not approve any ground-disturbing activity that may affect any such species or critical
habitat until it completes its obligations under applicable requirements of the Endangered Species Act as
amended, 16 U.S.C. § 1531 et seq., including completion of any required procedure for conference or
consultation.
BLM Sensitive What are the potential BLM Manual 6840 requires conservation of special status species and the ecosystems upon which they
Species impacts to BLM sensitive depend on BLM-administered lands. BLM special status species are those listed or proposed for listing
(Wildlife and species (wildlife and under the ESA, and species requiring special management consideration to promote their conservation
Plants) plants) or their habitats and reduce the likelihood and need for future listing under the ESA. Instructional Memorandum No. UT
from oil and gas IM-2019-005 provides the plant and wildlife Species lists for BLM-administered public lands in Utah and
development? these species have been evaluated for potential impacts from the proposed lease sale, as documented by
the checklist found in Appendix D of this EA.
The Utah BLM has several lease notices that protect sensitive species statewide (see UT-LN-49 Utah
Sensitive Species in Appendix A of this document) or on a species specific basis (see UT-LN-107: Bald
Eagle). For the Monticello Field Office, September 2019 lease sale, the BLM analysis of potential for
impacts to sensitive wildlife and plants or their habitat, and determined that application of the following
lease notices was appropriate for every parcel in the sale: UT-LN-49 (Utah Sensitive Species).
12
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Issue Issue Statement Rationale for Not Further Discussing in Detail in the EA
The application of sensitive species protections contained in UT-LN-49: Utah Sensitive Species tells the
lessee/operator that no surface use or otherwise disruptive activity would be allowed that would result in
direct disturbance to populations or individual special status plant and animal species, and that
modifications to the Surface Use Plan of Operations may be required to protect these resources from
surface disturbing activities.
In addition, multiple parcels contained sensitive habitat for game species such as elk, mule deer or
pronghorn antelope. The application of these stipulations and notices is discussed in detail in Appendix D
of this EA, under “Game Species.”
Leasing of the proposed leases would not, by itself, authorize any ground disturbance; however, the
proposed lease sale has the potential to impact habitat through future oil and gas development. Although
site-specific effects cannot be analyzed until an exploration or development application is received,
attachments of stipulations and notices to leases will assure the opportunity to make adjustments, such as
design modifications, at the site specific level when an Application for Permit to Drill is received, to
address specific wildlife and plant resources.
Migratory Birds What are the potential The Migratory Bird Treaty Act (MBTA) protects migratory birds; Instructional Memorandum No. 2008-
impacts to migratory 050 requires the BLM to Address the potential effects of the project son migratory bird populations and
birds from oil and gas their habitat, and implement best management practices to avoid or minimize the possibility of impacts,
development? through such measures as timing limitations during nesting seasons, surveys for bird nests, and
monitoring (https://www.blm.gov/policy/im-2008-050).
The Utah BLM has several lease notices that implement this policy during lease sales, ranging from those
applied statewide (UT-LN-45: Migratory Birds, found in Appendix B of this document) to species
specific (see UT-LN-107L Bald Eagle and UT-LN-44 Raptors). In addition, several migratory birds have
been designated as BLM Sensitive Species, and these may have additional protections through notices to
potential buyers of potential for occurrence on a given parcel (see UT-LN-49).
For the Monticello Field Office, September 2019 lease sale, the BLM analysis of potential for occurrence
indicated that application of the following lease notices was appropriate for every parcel in the sale, UT-
LN-43 Raptors, and UT-LN-45: Migratory Birds.
UT-LN-43 provides that raptor habitat exists in a given parcel, and that surveys will be required to
identify any nesting birds. UT-LN-45 gives prospective buyers notice that surveys for nesting migratory
birds may be required during migratory bird breeding season whenever surface disturbances and/or
occupancy is proposed in association with fluid mineral exploration and development within priority
13
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Issue Issue Statement Rationale for Not Further Discussing in Detail in the EA
habitats. Based on these surveys, buffers and timing limitations may be applied. In combination these
lease notices provide mitigation measures which will mitigate impacts to migratory birds, by allowing the
opportunity to make adjustments, such as design modifications, at the site specific level when an
Application for Permit to Drill is received.
Paleontology What are the potential Fossils uncovered during ground disturbing activities would be protected owing to the standard discovery
impacts on the integrity requirements. Additionally, should a parcel be located in an area that has high potential for
of paleontological paleontological resources, COAs would be applied at the APD stage. The proponent is required to notify
resources associated with the BLM of any discoveries they come across during construction following the APD stage.
oil and gas disturbance?
The Monticello RMP, 2008 decision WC-1 (page 85) identified which lands identified at the time as
Lands With What are the potential
having wilderness characteristics would be managed to “Protect, maintain and preserve wilderness
Wilderness impacts to Lands With
characteristics.” The inventories current at the time identified three non-contiguous areas adjacent to the
Characteristics Wilderness
Squaw and Papoose Canyons WSA as possessing wilderness characteristics, These areas are not “stand
Characteristics?
alone” units due to being less than 5000 contiguous acres but could increase the size of the WSA,
however the RMP decision was to not manage the units to protect the wilderness characteristics.
Parcel 420, 421, 422 and 423 intersect 1852 Acres of the Squaw and Papoose Canyons Wilderness
Characteristic Units. No existing leases intersect the units.
According to the 2008 MtFO RMP FEIS: “Based on the percentage of non-WSA lands with wilderness
characteristics and the existing and pending leases within those areas, the highest potential for leasing and
development would be in Comb Ridge, Cross Canyon, and Squaw and Papoose Canyon. Given that the
projection for drilling for oil and gas is three wells per year for all of the public lands within the Blanding
Subbasin area, and that just over 9% of the development area includes non-WSA lands with wilderness
characteristics open to leasing under standard stipulations, CSU, or TL stipulations, it is still anticipated
that up to one well per year would be drilled in the non-WSA lands with wilderness characteristics
because the Blanding Sub-basin area contains oil and gas fields and the majority of existing wells within
the Monticello PA. This would disturb up to 9.6 acres per year, or approximately 144 acres over the next
15 years…Leasing and development within these non-WSA lands with wilderness characteristics would
cause the affected portion to lose its natural characteristics. Loss of opportunities for solitude and
primitive recreation due to exploration for and development of oil and gas resources would be broader
than just for the 144 acres of direct surface-disturbing activities, and could impact these values for up to
one-half mile from the ongoing activity. However, it is not anticipated that any of the areas would lose
14
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Issue Issue Statement Rationale for Not Further Discussing in Detail in the EA
their wilderness characteristics in totality because of the small amount of acreage projected to be
disturbed and the few projected wells in this development area over the next 15 years.”
On October 21, 2014, the Southern Utah Wilderness Alliance (SUWA) submitted information
suggesting the presence of wilderness characteristics in the Tin Cup Mesa Central and Monument
Canyon units. BLM conducted an analysis and lands within these units were found to possess
wilderness character (WC) as determined by the Documentation of BLM Wilderness Characteristics
Inventory Findings: The Tin Cup Mesa Unit was found to have 9,743 acres of Wilderness
Characteristics, and the Monument Canyon Unit was found to have 17,200 acres, adding a total of
26,953 acres of identified acres of WC within the Blanding Subbasin area. At the time the RMP FEIS
was prepared, there were 38,540 acres of identified acres of wilderness characteristics, however since
that time the Fish and Owl Creeks, Lime Creek, Road Canyon, San Juan River and Comb Ridge, Unit,
consisting of 33,260 acres, have been incorporated into the Bears Ears National Monument and is no
longer available for lease, leaving 32,233 acres of wilderness characteristics available for lease, or a
20% decrease in lands with wilderness characteristics within the Blanding Subbasin available for lease.
Thus, the RMP FEIS projection of a total loss of 144 acres of wilderness characteristics with no totality
of loss in any one unit is still valid.
Since the Monument Canyon and Tin Cup Mesa Units were found to possess wilderness characteristics
subsequent to the RMP, they are not subject to RMP decision WC-1 to “Protect, maintain and preserve
wilderness characteristics …” However the March 2018 Oil and Gas Lease EA disclosed the possible
impairment of the Units, and the decision was made to lease several parcels within the units. This lease
sale will increase the acreage leased in both Units, to a total of about 80% leased for the Monument
Canyon Unit and 100% leased for the Tin Cup Mesa Unit. These numbers cannot be extended out to the
projected acres of wilderness characteristics that may be impacted beyond saying that the Units may
experience a decrease of no, some or all of their wilderness characteristics.
National What are the potential On December 13, 2018, staff from the Hovenweep and Natural Bridges National Monuments submitted
Historic impacts to Hovenweep comments on the DNA initially prepared for the parcels considered in this EA. They brought forth the
Trails/Units of National Monument? following concerns for Hovenweep National Monument:
the National
1. Air Quality in the Monument from Ozone production and Dust emissions
Park Service
2. Vibrations from Heavy Equipment on roads in the immediate vicinity of the Monument
3. Viewshed
4. Night Skies
15
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Issue Issue Statement Rationale for Not Further Discussing in Detail in the EA
5. Soundscapes
6. Drinking Water Quality
7. Earthquakes Induced from Oil and Gas Activity
Reason the concerns are not considered in detailed analysis
Concerns 1 and 6:
Air Quality and Drinking Water are statutorily protected, regardless of the concern is inside or outside the
Monument. Air Quality is being analyzed in detail for this proposal, and drinking water sources are
protected through the measures operators must take to prevent contamination of potable aquifers and
surface waters.
Concern 2
The concern that vibrations from heavy equipment could damage historic structures within the
Monument. Again, Sites eligible for inclusion in the National Historic Registry, whether inside or
outside the Monument, are statutorily protected. At the time of development, operators disclose the
routes they propose to use to access their drill sites. At that time, the proximity of the route to any fragile
historic structure can be assessed, and the operator required to find an alternate access route.
Concern 3
The BLM overlayed a GIS viewshed analysis from several points within the Monument. The parcels did
not fall within the viewshed of any of those points (Figure 5). The NPS confirmed the BLM’s findings
in an email dated May 17, 2019.
Concerns 4 and 5
A lease notice UT-LN-125 informing the potential lessee of the possible need to use sound and light
reducing measures have been added to all the parcels.
Concern 7
The concern is that earthquakes could be induced from oil and gas activity as has happened in other
regions in the United States, and that the earthquakes would damage sensitive historic structures. As
explained in the Mineral Resources/Energy Production section of Appendix D, induced earthquakes are
16
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Issue Issue Statement Rationale for Not Further Discussing in Detail in the EA
unlikely to occur in Utah. More site specifically, there are currently well over a hundred enhanced oil
recovery water injection wells within 25 miles of the Monument on BIA lands. The injection of water
under for oil recovery is much less likely to induce earthquakes as are water disposal wells, as has been
demonstrated by the lack of induced earthquakes from the highly developed are south west of the
Monument.
Cultural What are the potential The BLM has conducted a literature search using survey and site information from the CURES
Resources impacts from ground geodatabase, Preservation Pro, DAM, GLO maps, and Field Office records to identify currently known
disturbing oil and gas sites within the lease parcels, and to determine whether these sites could be avoided or mitigated
activities on cultural through standard archaeological practices at the APD stage.
resources?
The Cultural Resources and Tribal Consultation Stipulation (H 3120-1) is applied across all lease parcels.
This stipulation states that the lease area may be found to contain historic properties and/or resources
protected under the National Historic Preservation Act (NHPA), American Indian Religious Freedom
Act, Native American Graves Protection and Repatriation Act, Executive Order 13007, or other statutes
and executive orders. The BLM will not approve any ground-disturbing activities that may affect any
such properties or resources until it completes its obligations (e.g., State Historic Preservation Officer
(SHPO) and tribal consultation) under applicable requirements of the NHPA and other authorities.
The BLM may require modification to exploration or development proposals to protect such properties,
or disapprove any activity that is likely to result in adverse effects that cannot be successfully avoided,
minimized, or mitigated. Moreover, prior to granting APDs on Federal surface or split-estate lands,
cultural resource inventories are required.
Additional cultural resource analysis was completed in March 2018 EA (BLM 2018).
17
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
18
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Chapter 2 Description of Alternatives
2.1 Introduction
This EA addresses two alternatives (Alternative A – Proposed Action and Alternative B – No Action, No
Leasing).
Other alternatives were not considered in detail because the issues identified during scoping or the
alternatives identified during the comment period did not indicate a need for additional alternatives or
protective measures beyond those contained in the Proposed Action. The No Action alternative is
considered and analyzed to provide a baseline for comparison of the impacts of the Proposed Action.
Leasing is an administrative action that does not directly cause environmental consequences. However,
leasing is considered to be an irretrievable commitment of resources because the BLM generally cannot
deny all surface use of a lease unless the lease is issued with a no surface occupancy (NSO) stipulation.
Potential oil and gas exploration and production activities, committed to in a lease sale, could impact
other resources and uses in the planning area. Direct, indirect, or cumulative effects to resources and uses
could result from future levels of lease exploration or development, however these future levels are
uncertain and undetermined.
2.2 Analysis Assumptions
2.2.1 Reasonably Foreseeable Development Scenario
The Reasonably Foreseeable Development Scenario (RFDS) is a planning tool to provide a reasonable
estimate of what oil and gas exploration and development activities might be proposed, should a decision
be made to lease the area. The RFDS is a 20-year forward-looking estimation of oil and gas exploration
and development that is exclusive of other concerns that might compete for use of land in a multiple-use
scenario. The MtFO has classified lands within the district boundary. The parcels are located in San Juan
County, and are classified as high potential for occurrence of oil and gas but with a lower level of
certainty of production. It is estimated that 59 percent of the wells drilled in MtFO will be capable of
production and 41 percent is estimated to be a dry hole. If relevant resource conditions have changed
(e.g., establishment of wells capable of producing oil or gas in paying quantities per 43 CFR 3107.2-3),
the MtFO would re-evaluate the RFDS to address the new geologic information.
Although at this time the BLM does not know when, where, or if future well sites or roads might be
proposed on any leased parcel. Should a lease be issued, site specific analysis of individual wells or roads
would occur when a lease holder submits an APD.
When and if an APD is submitted for any of the leases, BLM would adhere to numerous IMs (as revised
through the life of an active lease) including specific instructions for directional drilling, split estate,
bonding, and other laws (such as NHPA, ESA). Some of these IMs include:
• Approval of Notice of Intent to Conduct Geophysical Exploration to Federal Oil and Gas Lessee
on Split Estate (WO IM 2009-121)
• Cultural Resources Requirements for Split Estate Oil & Gas Development (WO IM-2009-027)
• Split Estate Report to Congress--Implementation of Fluid Mineral Leasing and Land Use
Planning Recommendations (WO IM 2007-165)
• Permitting Oil & Gas on Split Estate Lands (WO IM 2003-131)
• Legal Responsibilities on Split Estate Lands (WO IM 1989-201)
• Directional Drilling into Federal Mineral Estate from Well Pads on Non‑Federal Locations (WO
IM 2018-014).
Management provisions would adhere to the Gold Book best management practices (United States
Department of the Interior and United States Department of Agriculture 2007). In general, activities are
19
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
anticipated to take place as described in Appendix H. This appendix provide a general discussion of
possible post-leasing RFDS activities. All of these activities would require additional NEPA review when
a lease holder submits an APD.
RFDS for the MtFO
The 2005 RFD (BLM 2005) to the MtFO RMP predicted that over 15 years, on average, 3 wells will be
drilled each year. It is recognized there would be some years with less than 3 wells, and some years with
more than 21 wells (Table 4.1 in RMP).
Seismic Activity:
• 1,230 miles of seismic lines for a total disturbance of 2,236 acres
Exploration Activity:
• Anticipate 195 well pads in 15 years
• Average disturbance is projected to be 9.6 acres per well.
• Anticipate 115 producing wells
RFDS Assumption for Analysis in this EA
For the analysis of the 19 nominated parcels encompassing 32,067.42 acres, the MtFO estimated a
maximum of 4 wells 11 would be drilled, and the maximum new disturbance will be 4 wells totaling 38.40
acres (one well pad and access road disturbance at 9.6 acres). This scenario would occur rarely, if at all.
Over the last three years (2015-2018) 12, six wells have been drilled in San Juan County. Out of those six
wells, only 1 well was capable of production. Statistically, it is more probable that three wells would be
drilled for the nominated MtFO parcels.
11
The RMP (page 4-112) states 42 wells on federally managed subsurface encompassing 405, 664 acres would be
drilled over the next 15 years. Approximately, only 31 percent could be capable of production in this area. The
nominated parcels cover 32,067.42 acres. The RFD calculation was (405,664/32,067.42)*.31 equaling 4 wells for all
the 19 nominated parcels.
12
Statistical information can be found on Utah Division of Oil, Gas and Mining website.
https://oilgas.ogm.utah.gov/oilgasweb/statistics/spuds-by-cnty.xhtml
20
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Areas offered for oil and gas leasing would be subject to measures necessary to mitigate adverse impacts,
according to the categories, terms, conditions, and stipulations identified in the land use plans, as
amended.
BLM regulations at 43 CFR 3101.1-2 allow for the relocation of proposed oil and gas leasing operations
up to 200 meters and/or timing limitations up to 60 days to provide additional protection to ensure that
proposed operations minimize adverse impacts to resources, uses, and users.
Additional measures would be applied to some leases to further protect specific resources (Appendices A
and Appendix B). In addition to the stipulations provided for by the governing LUPs (as amended) and
BLM policies, Lease Notices have been developed for conservation measures and would be applied on
specific parcels as warranted by subsequent IDPRT review. The addition of prescribed notices would be
applied to all leasing categories detailed in Appendix B.
At the leasing stage it is uncertain whether development on all leased parcels will move forward;
however, for the purposes of this analysis, and in order to assess potential impacts, Reasonably
Foreseeable Development (RFD) is assumed wherein all 19 nominated parcels will be developed. The
Reasonably Foreseeable Development used for analysis assumptions under this alternative is described in
Section 2.2.1.
2.4 Alternative B – No Action
The No Action Alternative would not offer any of the nominated parcels in the lease sale. The parcels
could be considered for inclusion in future lease sales. Surface management would remain the same and
ongoing oil and gas development would continue on surrounding private, state, and existing federal
leases.
2.5 Other Alternatives Considered but Not Analyzed in Detail
Other alternatives to the Proposed Action were not identified that would meet the purpose and need of
agency action.
The Interior Board of Land Appeals has held that subsumed in a no action alternative is consideration of
not leasing any or all parcels (Biodiversity Conservation Alliance et al., 183 IBLA 97, 124 (2013)). The
No Action alternative allows the authorized officer to resolve resource conflicts by deferring or removing
parcels from the lease sale, before offering those parcels for sale. The alternatives carried forward
represent those necessary for a reasoned choice (40 CFR 1502.14) and are based on the issues that were
identified by the IDPRT.
2.5.1 No Leasing Alternative (Designating the Parcels as Closed to Leasing)
A no leasing alternative was considered but eliminated because it is inconsistent with the management
plans for the area, and therefore is outside the purpose and need of this EA. This alternative would require
a RMP Plan Amendment because the areas in question were found suitable for leasing by the governing
RMPs and preceding management plans. The RMPs as amended also identified the lands as available for
leasing subject to a range of constraints, and reject a no leasing alternative. This alternative was dismissed
from detailed consideration.
2.5.2 Deferring Specific Parcels from the Sale
Since each parcel is an independent, though similar, action the BLM at the end of the EA process could
choose to either lease or defer any parcel in the EA’s decision record. Therefore this alternative to defer
for specific resource concerns was not considered in detail because it is substantially a combination of the
proposed action and no action and does not improve the range of alternatives. Offering or deferring any
particular parcel in this EA is within the range of alternatives already considered in detail in this EA, and
21
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
can be implemented at the discretion of the Authorized Officer, as the need is identified in the NEPA
analysis.
2.5.3 Adding Stipulations Beyond those Required by the Management Plan
This alternative to add additional stipulations beyond those identified by the applicable Management Plan
to the nominated parcels was not considered in detail because it would require a plan amendment, which
is outside the scope of this EA. A plan maintenance was done to the Monticello RMP (BLM 2017)
Maintenance Change 102 to adopt the Moab MLP notices. Therefore, those notices in the MLP can be
applied to the parcels in Appendix A. However, deferral of any particular parcel due to unresolved
resource conflicts is within the range of alternatives considered in detail in this EA, and can be
implemented at the discretion of the Authorized Officer, or as the need is identified in the NEPA analysis.
22
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Chapter 3 Affected Environment
3.1 Introduction
This chapter presents the potentially affected existing environment (i.e., the physical, biological, social,
and economic values and resources) of the impact area as identified in the IDPRT Checklist as found in
Appendix D and introduced in Chapter 1 of this EA. Only those aspects of the affected environment that
are potentially impacted are described in detail. Only those aspects of the affected environment related to
the issues presented in Table 1 and discloses any potential direct, indirect and cumulative impacts on the
resources identified as issues. Once issues are identified, impact indicators are selected to assess the
impacts of alternatives and are used as a basis for future monitoring (Table 1).
The CEQ Regulations state that NEPA documents “must concentrate on the issues that are truly
significant to the action in question, rather than amassing needless detail” (40 CFR 1500.1(b)). While
many issues may arise during scoping, not all of the issues raised warrant analysis in an EA. Issues will
be analyzed if: 1) an analysis of the issue is necessary to make a reasoned choice between alternatives; or
2) if the issue is associated with a significant direct, indirect, or cumulative impact, or where analysis is
necessary to determine the significance of the impacts. To see which resources were determined to not be
present or not expected to be impacted by the Proposed Action please refer to Appendix D.
Assumptions for analysis
The act of leasing nominated parcels in and of itself would have no immediate impacts on resources in the
Monticello Field Office. However, for the purposes of this analysis, a framework of RFD is assumed
wherein all parcels under each alternative are leased and developed.
While an appropriate level of NEPA for wells or roads would occur when a leaseholder submits an APD,
reasonable development assumptions for lease development will be used in the analysis of impacts in this
EA to inform the decision since leasing results in a commitment resources unless the lease is allowed to
expire without development.
Cumulative impacts include the combined effect of past projects, ongoing projects, and other reasonably
foreseeable future actions.
13
ArcGIS data displaying land status by surface management agency and existing oil and gas leases on federal lands
can be found at: https://bit.ly/2Uy8TpF.
23
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
sold in the lease sale then total leased acres for the MtFO would cumulatively increase to 275,803 acres or
25% leased acres. This would be a cumulative increase of 3% compared to current leased acres (Table 3).
NA 37,754 NA 2,1664 NA
No Leasing Decision Category
682,286 235 NA 0 0
Closed2
1
Leased acres are calculated as of March 2019 and include the previous NCLS lease sale acres sold on March 25 -
26, 2019. Acres calculated using GIS data and are therefore a close approximation of actual leased acres. All
calculations were rounded to the nearest whole number.
2
Authorized leases, held by production.
3
Designated acres total only includes the leasable designated acres and excludes the 682,286 closed acres.
4
Surface is private ownership.
The proposed action would result in additional leasing of 32,067.42 acres in San Juan County. 14
Table 4. Leasing Category Acreages by Parcel.
Number Standard Moderate Major Acreage Private Federal
Stipulations Constraints Constraints Total Surface Surface
(CSU/TL) 15 (NSO)
406 2,232.30 - - 2,232.30 120.23 2,112.07
407 2,227.00 - - 2,227.00 160.56 2,066.44
408 1,741.30 - - 1,741.30 - 1,741.30
409 480.00 1,440.00 - 1,920.00 - 1,920.00
410 1,533.25 - 383.31 1,916.56 - 1,916.56
14
Calculations of acreages leased were calculated from GIS Utah Oil and Gas Lease layer. The acreages are subject
to change.
15
The BLM approved a land use plan amendment that added leasing stipulations for important resources, such as
wildlife species. The planning area encompasses the parcels included in this lease sale. The amendment categorized
these parcels as "open, with special stipulations," which is equivalent to "moderate constraints (CSU/TL)." These
stipulations would only apply to those portions of the parcels that have the resource present.
24
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Number Standard Moderate Major Acreage Private Federal
Stipulations Constraints Constraints Total Surface Surface
(CSU/TL) 15 (NSO)
412 1,920.00 - - 1,920.00 - 1,920.00
413 241.64 - - 241.64 241.64 -
414 1,373.21 444.40 - 1,817.61 40.00 1,777.61
415 1,600.00 - - 1,600.00 321.43 1,278.57
416 1,600.00 - - 1,600.00 - 1,600.00
417 1,320.00 - - 1,320.00 - 1,320.00
418 1,440.00 - - 1,440.00 79.20 1,360.80
419 1,600.00 - - 1,600.00 199.14 1,400.86
420 1,129.95 - - 1,129.95 - 1,129.95
421 2,480.56 - - 2,480.56 319.37 2,161.19
422 1,840.00 - - 1,840.00 558.26 1,281.74
423 1,840.48 - - 1,840.50 - 1,840.48
424 1,920.00 - - 1,920.00 - 1,920.00
Total 29,799.690 1,884.40 383.31 32,067.42 2,039.83 30.027.57
CSU = Controlled Surface Use, TL = Timing Limitations, NSO = No Surface Occupancy
25
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Air quality in a given region can be measured by its Air Quality Index value (AQI). The AQI is reported
according to a 500-point scale for each of the major criteria air pollutants, with the worst denominator
determining the ranking. For example, if an area has a CO value of 132 on a given day and all other
pollutants are below 50, the AQI for that day would be 132. The AQI scale breaks down into six
categories: good (AQI<50), moderate (50-100), unhealthy for sensitive groups (100-150), unhealthy
(>150), very unhealthy and hazardous. The AQI is a national index, therefore the air quality rating and the
associated level of health concern is the same throughout the country. The AQI is an important indicator
for populations sensitive to air quality changes (USEPA, 2018c).
When the AQI value is in the good range, pollutant concentrations are well below the NAAQS and air
pollution poses little or no risk. Moderate AQI values occur when pollution is below but near the NAAQS
and voluntary emission reduction measures are encouraged. The AQI is considered unhealthy when the
NAAQS is exceeded and major pollution sources are often required to implement mandatory emission
reduction measures. Counties without AQI data usually have fewer air pollutant sources and are assumed
to have good air quality.
AQI data for San Juan County is presented in Table 5. At least 81% of days were rated as good, with only
one day rated as unhealthy during the 2015-2017 timeframe. The pollutants primarily determining the
AQI over the three year period were ozone and PM2.5. Additional AQI data for the rest of the state is
provided in the AMR (BLM 2019).
Table 5. AQI Index Summary Statistics by County
Ozone and PM2.5 are identified in the AQI data as the primary pollutants determining air quality in the
area. Air pollutant concentrations can be reported using design values. A design value is a statistic that
describes the air quality status of a given location relative to the level of the National Ambient Air Quality
Standards (NAAQS). Design values are typically used to designate and classify nonattainment areas, as
well as to assess progress towards meeting the NAAQS. Design values are provided in Table 5. No design
value for PM2.5 is reported for San Juan County, so values from the nearest representative county (Mesa
County, CO) is presented. Reported ozone and PM2.5 concentrations are below the NAAQS.
Table 6. 2015-2017 Criteria Pollutant Design Values
Pollutant Location Averaging Time Concentration NAAQS
The Utah Division of Air Quality (DAQ) compiles statewide emission inventories to assess the level of
pollutants released into the air from various sources. The latest inventory is summarized in the AMR
(BLM 2019), and in Table 6. Only emissions from San Juan County are listed since this is where lease
26
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
parcels are located. On-road mobile sources are the highest human emission source for CO and NOx, with
area source the highest for PM, and oil and gas sources the highest emitters of SOx, and VOCs.
Table 7. 2014 Criteria Air Pollutant Emissions (tpy) by Source for San Juan County
Source CO NOx PM10 PM2.5 SOx VOCs
Hazardous air pollutants (HAPs) are known or suspected to cause cancer or other serious health effects, or
adverse environmental effects, so they are also regulated by the EPA. Examples of listed HAPs emitted
by the oil and gas industry include benzene, toluene, ethyl benzene, mixed xylenes, formaldehyde,
normal-hexane, acetaldehyde, and methanol. A list of HAP point source emissions by County is published
by the Utah Division of Air Quality (UDAQ 2018), and is incorporated by reference. A summary of
existing HAP emissions in San Juan County is presented in Table 7.
Table 8. Triennial Inventory of HAPs (2014).
HAPS (tpy) San Juan
County
Benzene 3.525
Toluene 0.745
Ethylbenzene 0.044
Xylenes 0.121
n-Hexane 0.954
Formaldehyde 0.242
Acetaldehyde 0.001
Naphthalene 0.001
27
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
The parcels in this lease sale occur within Prevention of Significant Deterioration Class II areas and do
not occur adjacent to National Parks or other sensitive areas. The closest Class I areas are Canyonlands
and Mesa Verde National Parks to the northwest and southeast respectively. Lease parcels are farther than
50 kilometers (approximately 30 miles) from the Class I area, which is the transition point from near-field
to far-field analysis. Additional Air Quality Related Values (AQRVs) include visual air quality (haze),
and acid (nitrogen and sulfur) deposition. AQRVs do not have threshold standards, but Federal land
managers have identified levels of concern. Current visibility and deposition information for nearby Class
I areas is summarized in the AMR (BLM 2019).
3.3.1.2 Environmental Consequences
Impacts of the Proposed Action
Leasing the subject tracts would have no direct impacts to air quality. Any potential effects to air quality
from the sale of lease parcels would occur at such time that any issued leases are developed. Please note,
this proposed action does not authorize or guarantee specific development scenarios. If leased, drilling of
wells on a lease would not be permitted until the BLM approves an Application for Permit to Drill (APD).
Any APDs received would be subject to additional site specific NEPA review. However development
assumptions have been made in this EA to inform the decision since an issued lease must be developed to
keep it from expiring. This discussion remains qualitative as variations in emission control technologies
as well as construction, drilling, and production technologies used by various operators make it difficult
to accurately estimate potential air quality impacts from modeling at this time. Well development would
likely be exploratory and impacts from construction and drilling would be temporary or short-term and
would cease after the associated activities.
During well development, there could be emissions from earth-moving equipment, vehicle traffic,
drilling, and completion activities. NO2, SO2, and CO would be emitted from vehicle tailpipes. Fugitive
dust concentrations would increase with additional vehicle traffic on unpaved roads and from wind
erosion in areas of soil disturbance. Drill rig and fracturing engine operations would result mainly in NO2
and CO emissions, with lesser amounts of SO2. These temporary emissions would be short-term during
the drilling and completion times.
During well production there could be continuous emissions from separators, condensate storage tanks,
and daily tailpipe and fugitive dust emissions from operations traffic. During the operational phase of the
Proposed Action, NO2, CO, VOC, and HAP emissions would result from the long-term operation of
condensate storage tank vents, and well pad separators. Additionally, road dust (PM10 and PM2.5) would
be produced by vehicles servicing the wells.
An emissions inventory (EI) estimate for an oil and gas well for this lease sale is shown in Table 9. Due
to the very small level of anticipated development and lack of information regarding potential emissions
control technologies an operator may use, the EI is based on the following assumptions:
• Each oil and gas well would cause 6.8 acres of surface disturbance. This acreage includes access.
• Construction activity for each well is assumed to be 10 days. It is further assumed that, based on
the acreage disturbed, 4.5 days would be spent in well pad construction and 5.5 days would be
spent in road and pipeline construction.
• Control efficiency of 25% for dust suppression would be achieved as a result of compliance with
Utah Air Quality regulation R307-205.
• Post construction particulate matter (dust) emissions are likely to occur on a short term basis due
to loss of vegetation within the construction and staging areas. Assuming appropriate interim
reclamation, these emissions are likely to be minimal to negligible and will not be considered in
this EA.
• Drilling operations would require 14 days.
28
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
• Completions and testing operations would require 3 days.
• Off-road mobile exhaust emissions from heavy equipment during construction activities and on-
road mobile emissions would not be considered as they are dispersed, sporadic, temporary, and
not likely to cause or contribute to exceedances of the NAAQS.
Table 9. Emissions Inventory Estimate.
1 2 3 4
PM10 NOX CO VOC VOC NOX CO PM10 NOX CO VOC PM10
O&G Well 0.34 13.31 1.83 0.23 0.85 0.07 0.07 0.00 0.11 0.09 6.44 0.07
Emissions from a well would include particulate matter of less than 10 micrometers in diameter (PM10),
nitrogen oxides (NOX), carbon monoxide (CO), and volatile organic compounds (VOCs). Emissions of
sulfur dioxide (SO2) and lead (Pb) from oil and gas development activities are minor and are not included.
PM2.5 is not specifically included as it is a component of PM10.
Emission factors for activities of the proposed action were based on information contained in the EPA’s
Emission Factors & AP 42, Volume I, Fifth Edition (EPA 1995). Production emissions from oil storage
tanks were estimated based on the emission factor contained in the Colorado Department of Public Health
and Environment PS Memo 05-01, Oil & Gas Atmospheric Condensate Storage Tank Batteries
Regulatory Definitions and Permitting Guidance (APCD 2017)
For total foreseeable emissions, multiply the amounts in the table by the total number of foreseeable wells
(4). However, it is not reasonable to assume that all wells will be drilled in a single year because the
lessee has 10 years to establish production on a lease, and historically most leases never have production
attempted or established 16. If production is not attempted within the 10 year timeframe, the lease will be
terminated with no development or production emissions occurring. If production is not established
within the 10 year timeframe, the lease will be terminated with no production emissions occurring.
Based on the emissions estimates contained in Table 9, the area being in compliance with all NAAQS,
and considering the location of the parcels relative to population centers and Class I areas, substantial air
resource impacts are not anticipated as a result of this leasing action, and no further analysis or modeling
is warranted for the leasing decision. Emissions resulting from the sale of these parcels are not likely to
16
See GAO’s October 2008 finding that for leases issued from 1987 through 1996, development occurred on 6% of
onshore leases and production was achieved on 5%. https://www.gao.gov/new.items/d0974.pdf
29
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
result in major impacts to air quality nor are they likely to cause a violation of the NAAQS. As identified
in notice UT-LN-102 additional analysis may be required when parcels are developed.
Potential impacts to visibility to Arches and Canyonlands National Parks was analyzed for the Cane
Creek Project (Golder 2010). The VISCREEN model was used to assess the change in color difference
index (ΔE) and plume contrast (C) against the background sky and terrain. In every case the VISCREEN
results were less than the default criteria, indicating no adverse effect on visibility from the proposed
projects to the two National Parks. Visibility impacts to Class I areas from potential development from
this lease sales are likely to be less than those identified for the Cane Creek Project since parcels are much
farther from the National Parks.
If exploration occurs, short-term impacts would be stabilized or managed rapidly (within two to five
years) and long-term impacts are those that would substantially remain for more than five years.
Impacts of the No Alternative Action
Under the No Action Alternative, BLM would continue to manage these lands based on the objectives
outlined in their class categories. No new attendant infrastructure associated with oil and gas development
would be built under the No Action Alternative. No new emissions of pollutants would occur.
3.3.1.3 Required Design Features
Application Stipulations UT-S-01 and Notices UT-LN-96, UT-LN-99, UT-LN-101 and UT-LN-102
would be adequate for the leasing stage to disclose potential future restrictions and to facilitate the
reduction of potential impacts.
The BLM does look to mitigate pollutants via lease stipulations and notices and further NEPA actions
throughout the lease process. Stipulations and notices would be applied to leases when issued to notify the
operator of what would be required (stipulation) and what could potentially be required (notice) at the
APD stage. This allows the potential lessee, at the time of bidding on the parcel, to be informed of the
range of requirements that could be expect when lease rights are exercised. Additional air quality control
measures may be warranted and imposed at the APD stage (such as mitigation measures, best
management practices, and an air emissions inventory). The BLM would do this in coordination with the
EPA, UDAQ and other agencies that have jurisdiction on air quality. By applying stipulations and
notices, leasing would have little impact on air quality. At the APD stage, further conditions of approval
(COAs) could be applied based on the environmental analysis for the APD. These control measures are
dependent on future regional modeling studies or other analysis or changes in regulatory standards.
Application of these notices would be sufficient to notify the lease holder of additional air quality control
measures that are necessary to ensure protection and maintenance of the NAAQS.
The BLM requires industry to incorporate and implement BMPs, which are designed to reduce impacts to
air quality by reducing emissions, surface disturbances, and dust from field production and operations.
Typical measures include: adherence to BLM’s waste prevention regulations, flare hydrocarbon gases at
high temperatures to reduce emissions of incomplete combustion; water dirt roads during periods of high
use to reduce fugitive dust emissions; collocate wells and production facilities to reduce new surface
disturbance; implementation of directional drilling and horizontal completion technologies whereby one
well provides access to petroleum resources that would normally require the drilling of several vertical
wellbores; suggest that vapor recovery systems be maintained and functional in areas where petroleum
liquids are stored; and perform interim reclamation to revegetate areas of the pad not required for
production facilities and to reduce the amount of dust from the pads.
In addition, the BLM encourages industry to participate in the Gas STAR program that is administered by
EPA. The Natural Gas STAR program is a flexible, voluntary partnership that encourages oil and natural
gas companies to adopt proven, cost-effective technologies and practices that improve operational
efficiency and reduce natural gas emissions. The EPA has promulgated air quality regulations for
30
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
completion of hydraulically fractured gas wells. These rules require air pollution mitigation measures that
reduce the emissions of volatile organic compounds during gas well completions.
Southeastern Utah has been identified as an area susceptible to wind erosion (Duniway et. al 2019). BMPs
to reduce fugitive dust include use of speed mitigation techniques, use of over-sized or low pressure tires,
directional drilling to reduce the number of well pads, and application of soil stabilization techniques
(Duniway et. al 2019).
3.3.1.4 Cumulative Impacts
The cumulative impact analysis area (CIAA) for air quality is Southeast Utah, specifically San Juan
County. The CIAA also includes regional Class I areas and other environmentally sensitive areas (e.g.,
national parks and monuments, wilderness areas, etc.) nearest to the parcels. No recent cumulative
modeling analysis has been performed for the CIAA area. However, modeling domains from the Moab
MLP (BLM 2016) and BLM’s Air Resource Management Strategy (ARMS) Modeling Project (BLM
2014) overlap with the CIAA. While emissions from lease parcels were not included in these analysis, the
RFD for the lease sale is a tiny fraction of the total wells analyzed in the modeling. As a result these
modeling analysis provide a reference for potential cumulative impacts due to regional oil and gas
development. It is important to note that the ARMS model performance evaluation of ozone indicated a
negative model bias (under predicts) during the winter and a positive model bias (over predict) during the
summer in the 4 km domain. The model performance evaluation for PM2.5, indicated a negative model
bias (under predict) throughout the year in the 4 km domain (BLM 2014).
Emissions
Past and present actions that have affected and would likely continue to affect air quality in the CIAA
include surface disturbance resulting from oil and gas development and associated infrastructure,
geophysical exploration, ranching and livestock grazing, range improvements, recreation (including OHV
use), authorization of ROWs for utilities and other uses, and road development. Past and present actions
in CIAA that have affected and would likely continue to affect air quality are too numerous to list here
but would include the development of power plants; the development of energy sources such as oil, gas,
and coal; the development of highways and roads; and the development of various industries that emit
pollutants. These types of actions and activities can reduce air quality through emissions of criteria
pollutants (including fugitive dust), VOCs, and HAPs, as well as contribute to deposition impacts and to a
reduction in visibility.
Past, present, and reasonably foreseeable oil and gas development is listed in the Utah Division of Oil Gas
and Mining’s Well Counts statistical report (UDOGM 2018). At the end of 2018 there were 719 active
producing wells (mostly tribal wells) in San Juan County. This number is down from 767 producing wells
when the Monticello RMP was approved, and down from 754 producing wells during the 2014 emission
inventory year. Emissions from the 5 wells estimated for this lease sale would add to the emissions from
the existing 719 wells. However, total oil and gas emissions are anticipated to be lower than those listed
Table 6.
The Moab MLP analysis included far-field modeling to evaluate impacts on NAAQS and AQRVs from
multiple sources over the entire MLP area. Technical details for this modeling are incorporated from
Appendix F of the MLP FEIS. The modeling analysis evaluated three scenarios based on the range of
alternatives in the MLP FEIS. Modeling results show no exceedances of the NAAQS for any pollutant for
any of the modeled scenarios (BLM 2016). Emissions from this lease sale would slightly increase
modeled concentrations, but pollutant concentrations are likely to remain below the NAAQS due to the
low RFD.
In Class I and Class II areas outside the Uinta Basin ARMS study area, O3 concentrations are highest
during the summer period (BLM 2014). The ARMS model determined that in the 2021 future year, all
31
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
assessment areas are within the applicable PSD increments for annual NO2, 3-hour SO2, annual SO2, and
annual PM10, while most assessment areas exceed the 24-hour PM2.5 and PM10 PSD increment (BLM
2014). Figure 1 shows that the ARMS predicted ozone design values for the CIAA are below the
NAAQS, with concentrations generally between 0.055 to 0.065 ppm. However, areas near Arches and
Canyonlands National Parks are approaching the NAAQS standard of 0.070 ppm. The modeling results
are likely conservative due to the over prediction of summertime O3 in the ARMS model and due to
background levels listed in Table 5 being 0.064 ppm. If background O3 levels rise additional analysis may
be needed when plans of development are submitted for the lease parcels. Exceedances of the O3 NAAQS
occur outside the CIAA in the Uinta Basin and Salt Lake City metropolitan area. Predicted PM2.5 design
values are shown in Figure 2, with annual concentrations in the CIAA generally in the 4-8 µg/m3 range.
Although a hotspot is identified near the town of Blanding, with concentrations nearing the NAAQS. This
area is identified as being susceptible to wind erosion (Duniway et. al 2019), so implementation of dust
mitigation BMP’s is important for keeping PM concentrations down.
Figure 1. ARMS predicted ozone design values with on the books controls for oil and gas emissions
in the year 2021.
32
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Figure 2. ARMS predicted PM2.5 design values with on the books controls for oil and gas emissions
in the year 2021.
In 2013, the WRAP WestJump Air Quality Modeling Study was completed (WRAP 2013)This study was
intended to initiate the next generation of regional technical analysis and support for ozone transport and
attainment demonstrations for the intermountain West. The project incorporated all of the recent western
modeling analyses into a single modeling database, and went through a comprehensive model
performance evaluation in an open technical forum independent of any specific project or regulatory
activity. One of the functions of the modeling platform is the ability to perform a comprehensive source
apportionment analysis to evaluate local source, western regional, natural and international impacts of
elevated ozone impacts (both rural and urban) across the west and at specific locations within the
modeling domain.
For purposes of the analysis for the MLP EIS, Canyonlands National Park was chosen as a source
receptor to evaluate both local and regional emission sources impacts on ozone, PM2.5, and visibility.
The WestJump source apportionment tool was used to specify source contributions by type; for instance
mobile, point, oil and gas and fires. Mobile sources (cars and trucks) make up the largest single source
category, followed by natural sources (primarily vegetative volatile organic compound [VOC] emissions),
and point sources (e.g., power plants). Oil and gas emissions account for less than 1 percent of the
regional source category emissions (WRAP 2013).
Based on the relatively minor levels of emissions associated with this proposed development, and the
application of BMPs, it is unlikely emissions from any subsequent development of the proposed leases
would contribute to regional ozone formation in the project area, nor is it likely to contribute or cause
exceedances of any NAAQS. Other emission contributors would continue at present rates such as
construction, urban development, and personal vehicle use.
Exceptional events such as a dust storm or major large wildfires could result in very high PM10 values
across the area. Data of such events would likely be reviewed by the EPA under the exceptional event
rules.
33
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Air Quality Related Values
The MLP analyzed changes to visibility conditions by modeling the number of days there was a change in
deciviews, which is a unit of measurement to quantify human perception of visibility. It is derived from
the natural logarithm of atmospheric light extinction coefficient. One (1) deciview is roughly the smallest
change in visibility (haze) that is barely perceptible. Modeled visibility impacts ranged from greater than
0.5 dv impacts on almost half the year (159 days) at Canyonlands National Park during the 2008
meteorological year for the high emissions scenario, to no visibility impacts greater than 1.0 dv at any
park for any meteorological year under the low emissions scenario. Coarse particulate (PM10), primarily
road dust from truck traffic on unpaved roads, was the dominate pollutant of concern under both high and
medium emissions scenarios. Under the low emissions scenarios nitrogen oxides play a greater role in
visibility impacts. The specific meteorological year used in the analysis also had a significant influence on
modeled impacts. Meteorology in 2008 had substantially greater levels of impacts across the board
compared to the previous two years of meteorological data. This indicates sensitivity to meteorological
variability, and given the large role particulates play, adverse visibility impacts can most likely be tied to
drier, hotter, and/or windier conditions (BLM 2016). Development of lease sale parcels would slightly
increase the impacts to visibility, but are not likely to be perceptible.
All MLP modeled values of sulfur and nitrogen deposition were near or below the Deposition Analysis
Thresholds of 0.005 kg/ha/yr for total nitrogen and total sulfur for all the modeled alternatives, with the
exception of the high and medium emissions scenarios for nitrogen deposition in Arches and
Canyonlands National Park for the 2008 meteorological year (BLM 2016). Development of lease parcels
has the potential to slightly add to the deposition rate.
The proposed action, in concert with other past, present, and reasonably foreseeable actions may
contribute to an increase of emissions through direct and indirect impacts, but it would not be expected to
increase cumulative effects to levels that would compromise the viability of air quality within or near the
CIAA. Visibility and deposition conditions in Class I and Class II areas would follow current trends as
described in the AMR (BLM 2019).
Hazardous Air Pollutants
The Past and present projects which contribute HAPs to the CIAA are detailed in the Utah Division of Air
Quality’s 2014 Point Source Emissions Inventory (UDAQ 2018). The BLM is unaware of any
foreseeable point source projects. The 2014 Triennial Inventory of HAPs (cumulative inventory of point
source HAPs) for the project area is summarized in Table 7. The EPA has determined that for the
cumulative impact area the total cancer risk is 13 to 19 in 1 million (EPA 2019). This cancer risk is within
the acceptable range of risk published by the EPA of 1 to 100 in a million as discussed in the National
Contingency Plan, 40 CFR 300.430.
The proposed action of leasing would not directly contribute to cumulative HAPs emissions or cancer
risk. Future potential development of the leases would contribute to HAPs emissions and cancer risk.
However, the HAPs emission contribution is not meaningful in the context of point source emissions
ongoing in the CIAA.
The No Action alternative would not contribute to criteria pollutant emissions, HAP emissions, or AQRV
impacts because the leases would not be issued and no development could occur.
3.3.2 Issue 2: What are the Potential Impacts of Oil and Gas Leasing to Climate
Change/Greenhouse Gases?
3.3.2.1 Affected Environment
Climate is the composite of generally prevailing weather conditions of a particular region throughout the
year, averaged over a series of years such as temperature and precipitation. The 2018 BLM Utah Air
34
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Monitoring Report (BLM 2019) discusses the current climate conditions in Utah, and is incorporated by
reference. The report presents the three-decade average and trends of temperature and precipitation for
each of the seven climate divisions in Utah.
Parcels included in this lease sale are within the Southeast Utah climate divisions. The Southeast climate
division on generally has warmer and drier conditions than the other climate divisions in Utah. Average
annual temperature and precipitation information for the climate division is presented in Table 6.
Additional details on climate in the leasing area and the rest of Utah are provided in the 2018 BLM Utah
Air Monitoring Report (BLM 2019).
Table 10. Climate Trends
1895-2017 Mean 1981-2010 Trend
Climate Division Temp (ºF) Precip (in.) Temp (ºF) Precip (in.)
7, Southeast 51.5 9.8 + 0.5 -0.51
In November 2018 the Fourth National Climate Assessment (NCA4) Volume II was published.
Compared to previous reports, NCA4 provides greater detail on regional scales as impacts and adaptation
tend to be realized at a more local level. The Southwest region (Arizona, California, Colorado, New
Mexico, Nevada, and Utah) encompasses diverse ecosystems, cultures, and economies, reflecting a broad
range of climate conditions, including the hottest and driest climate in the United States. The average
annual temperature of the Southwest increased 1.6°F (0.9ºC) between 1901 and 2016. Moreover, the
region recorded more warm nights and fewer cold nights between 1990 and 2016, including an increase
of 4.1°F (2.3°C) for the coldest day of the year. Each NCA has consistently identified drought, water
shortages, and loss of ecosystem integrity as major challenges that the Southwest confronts under climate
change. Since the last assessment, published field research has provided even stronger detection of
hydrological drought, tree death, wildfire increases, sea level rise and warming, oxygen loss, and
acidification of the ocean that have been statistically different from natural variation, with much of the
attribution pointing to human-caused climate change (USGCRP 2018).
Climate change includes both historic and predicted climate shifts that are beyond normal weather
variations. Climate change may be due to natural internal processes or external forces. Earth’s atmosphere
has a natural greenhouse effect wherein naturally occurring gases such as water vapor, carbon dioxide
(CO2), methane (CH4), nitrous oxide (N2O) and fluorinated gases absorb and retain heat (EPA 2018). A
number of activities contribute to the phenomenon of climate change, including emissions of GHGs
(especially CO2 and methane) from fossil fuel development, large wildfires, activities using combustion
engines, changes to the natural carbon cycle, and changes to radiative forces and reflectivity (albedo).
Current atmospheric concentrations of GHG’s are presented in the Specialist Report on GHG Analysis for
BLM Utah Oil and Gas Leasing (BLM 2019). Atmospheric concentration of CO2 is 406 ppm and is
increasing at a rate of 2.2 ppm/yr.
It is important to note that GHGs will have a sustained climatic impact over different temporal scales due
to their differences in global warming potential (described above) and lifespans in the atmosphere. For
example, CO2 may last 50 to 200 years in the atmosphere while methane has an average atmospheric life
time of 12 years. Each GHG has a global warming potential (GWP) that accounts for the intensity of each
GHG’s heat trapping effect and its longevity in the atmosphere. GWP allows for different gases to be
represented as an equivalent amount of CO2. As discussed in the Specialist Report on GHG Analysis for
BLM Utah Oil and Gas Leasing (BLM 2019), the BLM uses GWP that represent the current state of
science with the 100 year time horizon to allow for a direct comparison with national and global
emissions.
35
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
State, national, and global GHG emissions are reported in Table 7. Additional details about these GHG
emissions are discussed in the GHG Analysis for BLM Utah Oil and Gas Leasing (BLM 2019) report and
is incorporated by reference.
Table 11. GHG Emission in Million Metric Tons (CO2e)
Total emissions from well construction and operations for a single well is 3,900.8 MT CO2e/yr. Multiplying
the total direct emissions by the RFD of 4 wells provides an annual GHG emission estimate of 15,603 MT
CO2e/yr.
36
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
the BLM has no authority to direct or regulate the end-use of the produced products and an actual end-use
may differ from the assumption used for calculating downstream GHG emissions.
Calculations of indirect emissions from downstream combustion can be made by multiplying the
produced number of barrels (bbl) of oil and thousand cubic feet (mcf) of gas with GHG emission factors
from the EPA Greenhouse Gases Equivalencies Calculator – Calculations and References website (EPA,
2019). These emission factors are used because they provide an easy calculation of the amount of
equivalent amount of CO2 produced from a bbl of oil or mcf of gas. The emission factors also follow
IPCC guidance by accounting for 100% oxidation of carbon in the fossil fuel to CO2, regardless if the
carbon atom is part of a CO2, CH4, or other hydrocarbon molecule.
Existing oil and gas annual production data is obtained from the Utah Division of Oil, Gas and Mining
(UDOGM, 2018). It is assumed that future wells will produce oil and gas in similar amounts as other
existing nearby wells. Annual data from 2008 to 2018 is used to determine the average production per
well. However, some wells may produce more or less than the average. To better inform decision makers
and the public a low and high production estimates are also used to calculate a range of downstream
combustion emissions. Details on estimating production and downstream emissions are found in the GHG
Analysis for BLM Utah Oil and Gas Leasing (BLM 2019) report. Table 9 lists the estimated annual GHG
emissions per well. The lease total is calculated by multiplying the RFD (4 wells) with the single well
emissions. While a range of combustion emissions is presented, for simplicity, the average is used when
discussing total lease sale emissions.
Table 13. Production of Oil and Gas for a Single Well and Associated GHG Combustion
Emissions
2008-2018 Range of Oil 2008-2018 Range of Gas Range of Emissions per
Production (bbl/well) Production (mcf/well well (metric tons CO2e/yr)
Field Office Low Ave High Low Ave High Low Ave High
Monticello 4,753 5,555 6,356 10,264 13,635 17,006 2,609 3,140 3,670
EPA Emission factors: 0.43 metric tons CO2e/bbl, and 0.0551 metric tons CO2e/mcf. (EPA 2019).
Production data obtained from the Utah Division of Oil, Gas and Mining (UDOGM 2018).
Projected average annual combustion GHG emissions from this lease sale is 12,559 MT CO2e/yr. Actual
GHG emissions may range from zero (assuming no parcels sold or developed) to an indeterminate upper
range based on realized production rates, control technology, and physical characteristics of any oil
produced.
At present there are no scientifically proven methods for assigning a “significance” value of a single
sources contribution to global or regional climate change. GHG emissions are presented here as a proxy
for the indirect climate change impact from this lease sale. To express GHG emissions on a scale relatable
to everyday life the EPA GHG equivalency calculator can be used
(https://www.epa.gov/energy/greenhouse-gas-equivalencies-calculator). The construction, operation, and
average combustion GHG emissions projected per year from this lease sale is 28,162 MT CO2e/yr. and is
equivalent to 5,979 passenger vehicles driven for one year, or energy use for 3,372 homes for one year.
While the BLM provides an estimate of direct and indirect GHG emissions from the potential
development of lease parcels, there is significant uncertainty due to unknown factors including actual
production, life expectancy of a well, how produced minerals are used, the form of regulation of GHG
parameters by delegated agencies, and whether any Best Available Control Technologies are utilized at
the upstream or downstream emission location(s). Statewide, the range of combustion emissions alone has
an uncertainty of nearly 340% based on if a well is low or high producing. This uncertainty is
compounded when accounting for other factors listed above.
37
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Impacts of the No Alternative Action
Under the No Action Alternative, the parcels would not be leased so no future development could occur.
As a result, no GHG emissions from the development of these lease parcels would occur and there would
be no addition to the existing national and global emissions that influence climate change.
Additionally, the BLM encourages natural gas companies to adopt proven cost-effective technologies and
practices that improve operation efficiency and reduce natural gas emissions, to reduce the ultimate
impact from the emissions.
In October 2012, the EPA promulgated air quality regulations for completion of hydraulically fractured
gas wells. These rules require air pollution mitigation measures that reduce the emissions of VOCs during
gas well completions. Mitigation includes a process known as “green completion” in which the recovered
products are sent through a series of aboveground, closed, separators which negates the need for flowing
back into surface pits as the product is immediately sent to gas lines and the fluids are transferred to
onsite tanks.
3.3.2.4 Cumulative Impacts
Even though the Proposed Action of leasing would not contribute to cumulative effects on air resources,
future foreseeable development could contribute to cumulative GHG emissions and therefore climate
change. Cumulative GHG emissions from existing and foreseeable oil and gas wells within the
Monticello Field Office boundaries from well operation and downstream combustion are calculated in the
GHG Analysis for BLM Utah Oil and Gas Leasing Specialist Report (BLM, 2019) and is incorporated by
reference. Emissions from well construction, operations, and downstream combustion of existing wells
and foreseeable wells from current APDs and other recent leasing actions are included in the cumulative.
38
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Annual cumulative GHG emissions from existing and foreseeable oil and gas sources are presented in
Table 10. Emissions from well development are listed separately as they would only occur one time
during construction, drilling, and completion of new wells and not be an ongoing emission.
Table 14. Annual Cumulative GHG Emissions from Oil and Gas Wells.
Metric Tons CO2e/yr
Foreseeabl
Total
Existing Existing Foreseeabl Foreseeabl e One-
Field Office Annual
Direct Indirect e Direct e Indirect Time
Emissions
Emissions
Monticello 1,101,881 2,214,643 50,785 103,612 3,470,921 77,979
32,143,71 48,071,50
Statewide Total
7,348,088 4 1,216,853 7,362,851 6 1,842,235
For context, these cumulative emissions are compared to state and U.S. emissions from 2017 in Table 15.
Statewide cumulative emissions are larger than the state emissions due to the state total only including
major industrial sources and much of the indirect combustion emissions occur outside of Utah.
Table 15. Comparison of Cumulative Annual Emissions with State and National Emissions
Table 16 shows the lease sales contribution to the cumulative and a comparison to state and national
emissions.
Table 16. Lease Sale Emissions Compared to the Cumulative, State, and U.S. Emissions
Percent of
Lease Sale Percent of Percent of Percent of
Field Office Utah
Emissions Cumulative U.S. Energy U.S. Total
Emissions
The U.S. Geological Survey (USGS) has produced estimates of the greenhouse gas emissions resulting
from the extraction and end-use combustion of fossil fuels produced on Federal lands in the United States,
as well as estimates of ecosystem carbon emissions and sequestration on those lands (USGS, Federal
lands greenhouse emissions and sequestration in the United States—Estimates for 2005–14: Merrill,
M.D., Sleeter, B.M., Freeman, P.A., Liu, J., Warwick, P.D., and Reed, B.C. 2018). In 2014, nationwide
GHG emissions from fossil fuels extracted from Federal lands was 1,332.1 MMT CO2e. Corresponding
Utah Federal fossil fuel related emissions in 2014, were 43.1 MMT CO2e. Projected lease sale emissions
would add to the USGS calculated emissions. However, Federal lands also uptake carbon in vegetation,
soil, and water. On average Federal lands will sequester approximately 15% of potential GHG emissions
39
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
resulting from the lease sale (USGS, Federal lands greenhouse emissions and sequestration in the United
States—Estimates for 2005–14: Merrill, M.D., Sleeter, B.M., Freeman, P.A., Liu, J., Warwick, P.D., and
Reed, B.C. 2018).
As mentioned earlier, climate change is driven in part by GHG emissions from human activities.
Emissions from the lease sale would contribute incrementally to the cumulative national and global
emissions that influence climate change. BLM prepared several Rapid Ecoregional Assessments (REA) to
predict future conditions, including climate change, in various regions. The leasing area is within the
Colorado Plateau REA (Bryce 2012) analysis area. Past, present, and reasonably foreseeable activities in
the analysis include energy development, agricultural development, urban and road development, and
recreation development. The assumption details and modeling methodology are incorporated by
reference. The Colorado Plateau REA depicts the data sources for potential oil and gas leasing,
development and production, and oil shale and tar sand extraction. Modeled average annual future
temperatures in the Colorado Plateau REA are generally predicted to increase. Average annual
precipitation predicted by the model in general are predicted to decrease (drier) through 2030 and increase
(wetter) through 2060. Figure 3 shows the potential for climate related change and is a composite of
predicted changes to temperature, precipitation, runoff, and vegetation. Potential for climate related
change in the Colorado Plateau area generally predicted to be mostly moderate or lower (about 70%),
areas with high or very high (approximately 30%) potential for change are generally seen in higher
elevations. Due to inherent uncertainties described in the Colorado Plateau REA, caution should be used
for interpreting climate change potential at site specific scales (Bryce 2012).
Figure 3. Potential for climate change impacts for the Colorado Plateau
“Social cost of carbon” estimates are one approach that an agency can take to examine climate
consequences from greenhouse gas emissions resulting from a proposed action. However, leasing action
Environmental Assessments provide no quantitative monetary estimates of any benefits or costs. The
National Environmental Policy Act (NEPA) does not require an economic cost-benefit analysis (40
C.F.R. § 1502.23), although NEPA does require consideration of “effects” that include “economic” and
40
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
“social” effects (40 C.F.R. 1508.8(b)). Quantifying only the costs of oil and gas development by using the
social cost of carbon metrics but not the benefits (as measured by the economic value of the proposed oil
and gas development and production generally equaling the price of oil and gas minus the cost of
producing, processing, and transporting the minerals) would yield information that is both inaccurate and
not useful for the decision-maker, especially given that there are no current criteria or thresholds that
determine a level of significance for social cost of carbon monetary values.
Instead, BLM’s approach to GHG and climate change impacts analysis is to include calculations to show
estimated direct, indirect, and cumulative GHG emissions from potential future development. BLM’s
approach recognizes that there are adverse environmental impacts related to climate change associated
with the development and use of fossil fuels, provides potential GHG emission estimates, and discusses
potential climate change impacts qualitatively. This effectively informs the decision-maker and the public
of the potential for GHG emissions and the potential implications of climate change. This approach
presents the data and information in a manner that follows many of the guidelines for effective climate
change communication developed by the National Academy of Sciences (Council 2010) by making the
information more readily understood and relatable to the decision-maker and the general public.
The proposed action, in concert with other past, present, and reasonably foreseeable actions may
contribute to incremental increases to GHG emissions through direct and indirect impacts. There are
currently no established significance thresholds for GHG emissions that BLM can reference in NEPA
analyses, but all GHGs contribute incrementally to the climate change phenomenon. When determining
NEPA significance for an action, BLM is constrained to the extent that cumulative effects (such as
climate change) are only considered in the determination of significance when such effects can be
prevented or modified by decision-making (refer to BLM NEPA Handbook, pg.72). While GHG
emissions resulting from individual decisions can certainly be modified or potentially prevented by
analyzing and selecting reasonable alternatives that appropriately respond to the action’s purpose and
need, BLM has limited decision authority to meaningfully or measurably prevent the cumulative climate
change impacts that would result from global emissions.
The No Action alternative would not contribute to the cumulative emissions or climate change because
the leases would not be issued and no development would occur. The cumulative oil and gas related GHG
emissions, from Table 15, in the leasing area (3.5 MMT CO2e/yr.) and statewide (48.1 MMT CO2e/yr.)
would be reduced by 0.03 MMT CO2e/yr or approximately 0.8% and 0.06% respectively.
41
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Chapter 4 Consultation and Coordination
4.1 Introduction
The issues included in Section 1.8 identifies those that are analyzed in detail in Chapter 3. The IDPRT
Checklist (Appendix D) provides the rationale for issues that were considered but not analyzed further.
The issues were identified through the public and agency involvement process described in Sections 4.3
below.
4.2 Persons, Groups, and Agencies Contacted/Consulted
Persons, agencies, and organizations that were contacted or consulted during the preparation this EA are
identified in Table 17.
4.2.1 Endangered Species Act of 1973
The effects of Oil and Gas leasing development on T&E species were analyzed through Section 7
consultation on existing Utah BLM resource Management Plans was completed in 2008 (Cons. # 6-UT-
08-F-0024). This action is in compliance with T&E species management outlined in accordance with the
requirements under the FLMPA and the NEPA.
While Federal regulations and policies require the BLM to make its public land and resources available
on the basis of the principle of multiple-use, it is BLM policy to conserve special status species and their
habitats, and to ensure that actions authorized by the BLM do not contribute to the need for the species to
become listed as T&E by the USFWS.
Consultation on Oil and Gas leasing occurred in 2007, for existing RMP’s such as that for the Cedar City
jurisdictional area. For lease sales conducted on listed species covered by this consultation action, the
BLM regularly coordinates with the USFWS to assure agreement that the Proposed Action (leasing): 1)
does not exceed the impacts analyzed in the PRMP and BA/BO; and 2) would not exceed the effects
contained in the associated USFWS biological opinion(s) concurring with BLM’s Not Likely to
Adversely Affect (NLAA) determinations. Many of the parcels in the September 2019 lease sale were
deferred from the December 2018, March 2019 and June 2019 lease sales. The following is a summary of
dates associated with coordination with the USFWS on these sales:
• March 2019
o Lease notice provided to USFWS: December 13, 2018
o NLAA Agreement: February 25, 2019
• September 2019
o Lease notice provided to USFWS: April 17, 2019
o NLAA Agreement Confirmation Old Parcels: Consultation is ongoing
o NLAA Agreement New Parcels: Consultation is ongoing
The BLM is working with USFWS to confirm their agreement with BLM determinations. The BLM will
complete coordination on the September 2019 lease sale with the USFWS prior to issuance of the leases
for all parcels contained in the September 2019 lease sale, if offered. When or if disturbance is proposed
for parcels (APD stage) that contain or affect ESA species, further evaluation and Section 7 consultation
of these ESA species with the USFWS will occur as necessary.
4.2.2 National Historic Preservation Act (NHPA) of 1966
The BLM prepared a cultural resources report to document its reasonable and good faith effort to identify
effects this undertaking may have on historic properties, as required by Section 106 of the National
Historic Preservation Act of 1966 (54 U.S.C 306108).
The Advisory Council for Historic Preservation’s (ACHP) document titled Meeting the “Reasonable and
42
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Good Faith” Identification Standards in Section 106 Review, from
https://www.achp.gov/sites/default/files/guidance/2018-05/reasonable_good_faith_identification.pdf
outlines the steps to determine when a reasonable and good faith identification effort has been met. The
ACHP states:
• Prior to beginning the identification stage in the Section 106 process, the regulations (at 36 CFR §
800.4) require the federal agency to do the following:
• Determine and document the APE [Area of Potential Effect] in order to define where the agency
will look for historic properties that may be directly or indirectly affected by the undertaking;
• Review existing information on known and potential historic properties within the APE, so the
agency will have current data on what can be expected, or may be encountered, within the APE;
• Seek information from others who may have knowledge of historic properties in the area. This
includes the State Historic Preservation Officer (SHPO)/Tribal Historic Preservation Officer
(THPO) and, as appropriate, Indian tribes or Native Hawaiian organizations who may have
concerns about historic properties of religious and cultural significance to them within the APE.
Following these initial steps, the regulations (36 CFR § 800.4(b) (1)) set out several factors the agency
must consider in determining what is a “reasonable and good faith effort” to identify historic properties:
Take into account past planning, research and studies; the magnitude and nature of the
undertaking and the degree of federal involvement; the nature and extent of potential effects on
historic properties; and the likely nature and location of historic properties within the APE. The
Secretary of the Interior’s standards and guidelines for identification provide guidance on this
subject. The agency official should also consider other applicable professional, state, tribal, and
local laws, standards, and guidelines. The regulations note that a reasonable and good faith effort
may consist of or include ‘background research, consultation, oral history interviews, sample
field investigation, and field survey.’
For lease sales, BLM’s identification efforts include: (1) completing a comprehensive "records review,"
which is an intensive review and analysis of available pertinent cultural resource records and information
for each parcel and the surrounding areas that are included in the undertaking APE; and (2) proactively
seeking information from others who may have knowledge of historic properties in the area. The BLM's
identification efforts that are described in this report for the March 2019 lease sale undertaking are
consistent with the direction provided in multiple Interior Board of Land Appeals (IBLA)
decisions/orders, including Mandan, Hidatsa, and Arikara Nation, 164 IBLA 343 (2005), Southern Utah
Wilderness Alliance, IBLA 2008-264 (2009), and Southern Utah Wilderness Alliance, IBLA 2002-334.
On November 5, 2018 the BLM sent invitations to participate in government to government consultations
to: The Confederated Tribes of the Goshute, The Northwest Band of the Shoshone Nation, The Hopi
Tribe, Kaibab Band of Paiute Indians, Navajo Nation, Navajo Nation – Oljato Chapter, Navajo Nation –
Red Mesa Chapter, Navajo Utah Commission, Ohkay Owingeh, Paiute Indian Tribe of Utah, All Pueblo
Council of Governors, Pueblo of Acoma, Pueblo of Cochiti, Pueblo of Isleta, Pueblo of Jemez, Pueblo of
Kewa, Pueblo of Laguna, Pueblo of Nambe, Pueblo of Picuris, Pueblo of Pojoaque, Pueblo of San Felipe,
Pueblo of San Ildefonso, Pueblo of Sandia, Pueblo of Santa Ana, Pueblo of Santa Clara, Pueblo of Taos,
Pueblo of Tesuque, Pueblo of Zia, Pueblo of Zuni, Skull Valley Band of Goshutes, Southern Ute Tribe,
Uintah and Ouray Ute Tribe, Ute Mountain Ute Tribe, White Mesa Ute.
On November 15th, 2018 UTSO BLM posted data and instructions on ePlanning for consulting parties to
request consulting party status on the March 2019 Lease Sale Cultural Resource Report. BLM UTSO
consulted with Friends of Cedar Mesa, Southern Utah Wilderness Alliance, Box Elder County, Uintah
County, San Juan County, and Golden Spike National Park. BLM UTSO received comments and
concerns from SUWA and FOCM, supplemental data incorporated into the report from FOCM, and a
letter of support from San Juan County.
43
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Table 17. List of Contacts and Findings.
Name Purpose & Authorities Findings & Conclusions
for Consultation or
Coordination
National Park Service Coordinated with as Letter transmitting the preliminary list was sent on October 24, 2018 and April
leasing program partner. 17, 2019. A map and GIS shapefiles were sent to the NPS on October 26, 2018
through May 5, 2019 via email. Coordination is ongoing. UTSO sent an
additional letter via email to Golden Spike National Park on December 20th,
2018, with the draft March 2019 Lease Sale Cultural Resources Report.
United States Fish and Wildlife Service Coordinated with as Letter transmitting the preliminary list was sent April 17, 2019. Emails were
leasing program partner. sent on April 3 and April 25, 2019 transmitting the corresponding shapefiles.
United States Forest Service Coordinated with as Letter transmitting the preliminary list was sent on October 24, 2018 and April
leasing program partner. 17, 2019. Comments or concerns were not expressed.
Public Lands Policy Coordination Office Coordinated with as Letter transmitting the preliminary list was sent on October 24, 2018 and April
leasing program partner. 17, 2019. An e-mail with GIS shape-files was sent to UDWR to satisfy the
requirements of IM-2012-43 on October 26, 2018, March 27, 2019 and April
3, 2019.
Utah Division of Wildlife Resources Coordinated with as Letter transmitting the preliminary list was sent on October 24, 2018 and April
leasing program partner. 17, 2019. An early email was sent on October 26, 2018, March 27, 2019, and
April 3, 2019 transmitting the corresponding shapefiles.
State Institutional Trust Lands Coordinated with as Letter transmitting the preliminary list was sent on October 24, 2018 and April
Administration leasing program partner. 17, 2019.
State Historic Preservation Office Consultation as required On October 24, 2018 and March 13, 2019, a no adverse effect on historic
by NHPA (16 USC 470) properties determination was mailed to the SHPO. On October 25, 2018 and
March 25, 2019 SHPO concurrence was received.
The Hopi Tribe, Kaibab Band of Paiute Consultation as required On November 5, the MtFO archaeologist sent an invitation to consult letter to
Indians, Navajo Nation, Navajo Nation – by the American Indian each tribe. On November 8th the MtFO discussed the anticipated consultation
Oljato Chapter, Navajo Nation – Red Religious Freedom Act timetable with the Pueblo of Santa Clara. On November 23rd the Hope Tribe
Mesa Chapter, Navajo Utah Commission, of 1978 (42 USC 1996) requested consultation on the March 2019 Lease. On November 26 the MtFO
Ohkay Owingeh, Paiute Indian Tribe of and NHPA (16 USC received a letter from the Hopi, an email from the Pueblo of Isleta to arrange
Utah, All Pueblo Council of Governors, 470) consultation, had the consultation meeting with the Pueblo of Isleta, and
44
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Name Purpose & Authorities Findings & Conclusions
for Consultation or
Coordination
Pueblo of Acoma, Pueblo of Cochiti, exchanged emails with the White Mesa Ute about parcels. On December 3rd
Pueblo of Isleta, Pueblo of Jemez, Pueblo the MtFO responded to the White Mesa Ute, and received a letter to consult
of Kewa, Pueblo of Laguna, Pueblo of from the Pueblo of Santa Clara; both of which were responded to on the same
Nambe, Pueblo of Picuris, Pueblo of day. On December 12th the MtFO received a letter from the Pueblo of Acoma.
Pojoaque, Pueblo of San Felipe, Pueblo On December 14th the MtFO received a letter from the Southern Ute
of San Ildefonso, Pueblo of Sandia, requesting additional information and to participate in consultation. On
Pueblo of Santa Ana, Pueblo of Santa January 15th the MtFO received a letter from the Pueblo of Acoma demanding
Clara, Pueblo of Taos, Pueblo of a halt to APD processing during government shutdown, and noted that BLM
Tesuque, Pueblo of Zia, Pueblo of Zuni, has not announced timeline extensions for the March and June Lease sales. On
Southern Ute Tribe, Uintah and Ouray January 22nd the MtFO received an email from the Southern Ute Tribe stating
Ute Tribe, Ute Mountain Ute Tribe, that BLM cannot make determinations without tribal consultation, and
White Mesa Ute recommending the BLM send the Southern Ute Tribe the Cultural Report. On
January 28th the MTFO received a letter attached to an email from the Navajo
Nation with a statement that the lease sale will have no adverse effect to
Navajo TCP’s, as well as a request to consult on the lease. On February 5th, the
MtFO received an email from the Hopi Tribe reiterating the request from
December 10 that the BLM cancel the March lease sale, further asserting that
energy development results in adverse effects, RFD acreage. On February 11th
the MtFO received a letter from the Pueblo of Santa Clara noting the draft
report was received, and requested BLM postpone all lease activities until the
end of the shutdown, with a requested for more information and further
consultation; as well as an email from the Southern Ute reiterating response
letter that the Southern Ute Tribe wishes to engage in consultation for the lease
sale, and that they request a list of sites in the parcels. On February 15th, the
MtFO emailed the Hopi Tribe, Kaibab Band of Paiute Indians, Navajo Nation,
Navajo Nation – Oljato Chapter, Navajo Nation – Red Mesa Chapter, Navajo
Utah Commission, Ohkay Owingeh, Paiute Indian Tribe of Utah, All Pueblo
Council of Governors, Pueblo of Acoma, Pueblo of Cochiti, Pueblo of Isleta,
Pueblo of Jemez, Pueblo of Kewa, Pueblo of Laguna, Pueblo of Nambe,
Pueblo of Picuris, Pueblo of Pojoaque, Pueblo of San Felipe, Pueblo of San
Ildefonso, Pueblo of Sandia, Pueblo of Santa Ana, Pueblo of Santa Clara,
Pueblo of Taos, Pueblo of Tesuque, Pueblo of Zia, Pueblo of Zuni, Southern
Ute Tribe, Uintah and Ouray Ute Tribe, Ute Mountain Ute Tribe, and the
45
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Name Purpose & Authorities Findings & Conclusions
for Consultation or
Coordination
White Mesa Ute informing the tribes of the coming certified mail invitation to
consulting meetings on February 25th and 26th at the Monticello Field Office.
On February 19th the MtFO received an email from the Uintah and Ouray
Tribes informing the BLM that a representative would not attend the meeting.
On February 20th the MtFO send a letter to the the Hopi Tribe, Kaibab Band
of Paiute Indians, Navajo Nation, Navajo Nation – Oljato Chapter, Navajo
Nation – Red Mesa Chapter, Navajo Utah Commission, Ohkay Owingeh,
Paiute Indian Tribe of Utah, All Pueblo Council of Governors, Pueblo of
Acoma, Pueblo of Cochiti, Pueblo of Isleta, Pueblo of Jemez, Pueblo
of Kewa, Pueblo of Laguna, Pueblo of Nambe, Pueblo of Picuris, Pueblo of
Pojoaque, Pueblo of San Felipe, Pueblo of San Ildefonso, Pueblo of Sandia,
Pueblo of Santa Ana, Pueblo of Santa Clara, Pueblo of Taos, Pueblo of
Tesuque, Pueblo of Zia, Pueblo of Zuni, Southern Ute Tribe, Uintah and Ouray
Ute Tribe, Ute Mountain Ute Tribe, and the White Mesa Ute inviting the tribes
to a consulting parties meeting February 25th and 26th at the Monticello Field
Office. On February 25th the MtFO hosted a teleconference consultation
meeting. The Pueblo of Pojoaque was in attendance. Discussed the lease sale
and the section 106 process, and the Pueblo of Pojoaque requested a copy of
the draft section 106 report, which was delivered that day. On February 25th,
2019 the Mtfo had a phone discussion with the Pueblo of San Felipe and the
Monticello Field Office. Discussed Lease sale, authority of phased approach,
determination of effect, the trust relationship, tribal difficulty with traveling to
consultation, and the best way to keep communication open. Coordination and
consultation will continue up until the lease auction, at the request of any tribe.
Box Elder County Commission, Uintah Representatives of local On December 20th, 2018, the UTSO emailed a copy of the March 2019 Lease
County Commission, San Juan County governments, per 36 Sale Cultural Resources Report to Box Elder County Commission, Uintah
Commission, C.F.R. 800 (2)(C)(3) County Commission, San Juan County Commission requested their comments
and input. On January 28th, 2019, the UTSO received a letter of support for the
March 2019 lease from San Juan County.
46
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
4.3 Public Participation
Scoping Period
The UTSO sent letters/memorandum to the following stakeholders: the National Park Service (NPS), the
United States Fish and Wildlife Service (USFWS), the United States Forest Service (USFS) and the State
of Utah’s Public Lands Policy Coordination Office (PLPCO), Division of Wildlife Resources (UDWR)
and the School Institutional Trust Lands Administration (SITLA) to notify them of the pending lease sale,
solicit comments and concerns on the preliminary parcel list. The BLM also provided GIS shapefiles
depicting the proposed sale parcels to contact points within the NPS and UDWR. Consultation and
coordination efforts are summarized in Table 17.
Comment Period
As introduced in Section 1.2, the preliminary EA and the unsigned Finding of No Significant Impact
(FONSI) were posted and made available for a 30-day public review and comment period on May 30,
2019. This announced the 30-day comment period (05/30/2019-07/01/2019) for this lease sale. The
documents were made available online at the Utah State Office’s Oil and Gas Leasing Webpage and the
BLM’s NEPA Register.
Section 4.3.1 will identify changes to this EA that were made as a result of public comments and internal
review. Comments and BLM’s responses to each of the comment letters will be shown in Appendix H
[Reserved].
NHPA Coordination
The BLM utilized and coordinated the NEPA public participation requirements to assist the agency in
satisfying the public involvement requirements under Section 106 of the National Historic Preservation
Act (NHPA) [16 U.S.C. 470(f) pursuant to 36 CFR 800.2(d)(3)]. The information about historic and
cultural resources within the area potentially affected by the proposed project/action/approval will assist
the BLM in identifying and evaluating impacts to such resources in the context of both NEPA and Section
106 of the NHPA. The BLM will consult with Indian tribes on a government-to-government basis in
accordance with Executive Order 13175 and other policies, if requested by any Tribe. If Tribal concerns
are identified, including impacts on Indian trust assets and potential impacts to cultural resources, they
will be given due consideration.
On May 28, 2019, BLM also provided a copy of the draft cultural report to individuals and/or
organizations who participated as a Consulting Party.
4.3.1 Modifications Based on Public Comment and Internal Review [Reserved]
The public comment period and corresponding internal review identified necessary corrections or
clarifications to this EA. [ongoing]
4.4 Preparers
An IDPRT prepared the document and analyzed the impact of the proposed action upon the various
resources (Table 18). They considered the affected environment and documented their determination in
the IDPRT Checklist (Appendix D). Only those resources that would likely be impacted were carried
forward into the body of the EA for further analysis.
Table 18. Preparers of This EA.
Name Title Responsible for the Following Section(s) of this
Document
Leah Waldner Natural Resource Project Lead, Oil and Gas Leasing Program Coordinator
Specialist
47
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Name Title Responsible for the Following Section(s) of this
Document
Glenn Stelter Archaeologist Oil and Gas Leasing Program, NHPA Compliance
Karen Cathey Wildlife Biologist Oil and Gas Leasing Program, USFWS Consultation
Angela Wadman Natural Resource Oil and Gas Leasing Program, NEPA Compliance
Specialist
Ken Bradshaw Hydrologist Oil and Gas Leasing Program
Aaron Roe Botanist Oil and Gas Leasing Program, USFWS Consultation
Erik Vernon Air Quality Specialist Oil and Gas Leasing Program, Air Quality; Greenhouse
Gases.
Leslie Wilken Land Law Examiner Oil and Gas Leasing Program
Travis Kern Acting Fluid Minerals Oil and Gas Leasing Program Review and Oversight
Branch Chief
Robin Naeve Acting Senior Leasing Oil and Gas Leasing Program Review and Oversight
Specialist
All specialists that reviewed the parcels are identified in Appendix D.
48
May 2019
Monticello Field Office
DOI-BLM-UT-000-2019-0003-EA
Chapter 5 Appendices
A. Parcel List with Stipulations and Notices
B. Stipulations and Notices
C. Figures (Maps)
D. Interdisciplinary Parcel Review Team Checklist
E. References
F. Acronyms/Abbreviations
G. Reasonable Foreseeable Development Scenario
H. Comments and Responses
49
May 2019
UT0319 – 406
T. 38 S., R. 23 E., SLM
Sec. 17: All;
Sec. 19: Lots 1, 2, NE, E2NW;
Secs. 20 and 21: All.
2,232.30 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air QualityUT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-294 California Condor
UT-S-297: CSU/TL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-69: High Potential for Cultural Resources
UT-LN-70: High Potential for Cultural Resource Occurrence
UT-LN-72: High Potential Paleontological Resources
50
May 2019
UT0319 – 407
T. 38 S., R. 23 E., SLM
Secs. 28, 29 and 30: All;
Sec. 31: E2.
2,227.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSU/TL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-69: High Potential for Cultural Resources
UT-LN-70: High Potential for Cultural Resource Occurrence
UT-LN-72: High Potential Paleontological Resources
UT-LN-96: Air Quality Mitigation Measures
UT-LN-99: Regional Ozone Formation Controls
UT-LN-102: Air Quality Analysis
UT-LN-113: Yellow Billed Cuckoo
51
May 2019
UT0319 – 408
T. 39 S., R. 23 E., SLM
Sec. 5: Lots 3, 4, S2NW, SW;
Secs. 6 and 7: All;
Sec. 8: NW.
1,741.30 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSU/TL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-69: High Potential for Cultural Resources
UT-LN-70: High Potential for Cultural Resource Occurrence
UT-LN-72: High Potential Paleontological Resources
UT-LN-96: Air Quality Mitigation Measures
UT-LN-99: Regional Ozone Formation Controls
UT-LN-102: Air Quality Analysis
UT-LN-113: Yellow Billed Cuckoo
UT-LN-125: Light and Sound – Sensitive Resources
UT-LN-128: Floodplain Management
52
May 2019
UT0319 – 409
T. 36 S., R. 25 E., SLM
Sec. 25: S2;
Sec. 26: S2;
Secs. 34 and 35: All.
1,920.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSU/TL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-04: Crucial Mule Deer and Elk Winter Habitat
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-69: High Potential for Cultural Resources
UT-LN-70: High Potential for Cultural Resource Occurrence
53
May 2019
UT0319 – 410
T. 37 S., R. 25 E., SLM
Secs. 1, 11 and 12: All.
1,916.56 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL - Mexican Spotted Owl
NOTICES
T&E-06 Mexican Spotted Owl
T&E-11: California Condor
T&E-28 California Condor
UT-LN-04: Crucial Mule Deer and Elk Winter Habitat
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-69: High Potential for Cultural Resources
UT-LN-70: High Potential for Cultural Resource Occurrence
UT0319 – 411
T. 37 S., R. 25 E., SLM
Secs. 13 and 14: All.
1,280.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
54
May 2019
UT0319 – 412
T. 37 S., R. 25 E., SLM
Secs. 24, 25 and 26: All.
1,920.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
NOTICES
T&E-06 Mexican Spotted Owl
T&E-11: California Condor
55
May 2019
UT0319 – 413
T. 38 S., R. 25 E., SLM
Sec. 4: Lots 2, 3, SWNE, SENW, NESW, NWSE.
241.64 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-170: CSU – Cultural
UT-S-234: TL – Crucial Deer Winter Range
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-288: CSU/TL – Mexican Spotted Owl
NOTICES
T&E-06 Mexican Spotted Owl
T&E-11: California Condor
T&E-28: California Condor
UT-LN-04: Crucial Mule Deer and Elk Winter Habitat
UT-LN-25: White-Tailed and Gunnison prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-47: Bald Eagle Habitat
UT-LN-49: Utah Sensitive Species
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-69: High Potential for Cultural Resources
56
May 2019
UT0319 – 414
T. 38 S., R. 25 E., SLM
Sec. 5: SW, SWSE;
Sec. 6: Lots 3-7, SENW, E2SW, SE;
Sec. 7: Lots 1, 2, E2, E2NW;
Sec. 8: All.
1,777.61 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-17: CSU – Alkali Ridge ACEC
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-242: TL – Crucial Elk Winter Range
UT-S-275: CSU/TL – Bald Eagles
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSU/TL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-04: Crucial Mule Deer and Elk Winter Habitat
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
57
May 2019
UT0319 – 415
T. 38 S., R. 25 E., SLM
Sec. 10: S2;
Secs. 15 and 22: All.
1,600.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-LN-04: Crucial Mule Deer and Elk Winter Habitat
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSU/TL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-72: High Potential Paleontological Resources
UT-LN-96: Air Quality Mitigation Measures
UT-LN-99: Regional Ozone Formation Controls
UT-LN-102: Air Quality Analysis
UT-LN-113: Yellow Billed Cuckoo
58
May 2019
UT0319 – 416
T. 38 S., R. 25 E., SLM
Secs. 12 and 13: All;
Sec. 14: S2.
1,600.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-288: CSU/TL – Mexican Spotted Owl
NOTICES
T&E-06 Mexican Spotted Owl
T&E-11: California Condor
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-72: High Potential Paleontological Resources
UT-LN-96: Air Quality Mitigation Measures
UT-LN-99: Regional Ozone Formation Controls
UT-LN-102: Air Quality Analysis
UT-LN-125: Light and Sound – Sensitive Resources
UT-LN-128: Floodplain Management
UT0319 – 417
T. 38 S., R. 25 E., SLM
Sec. 23: NE, E2SE;
Sec. 24: All;
Sec. 25: E2, N2NW, SENW.
1,320.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
59
May 2019
UT0319 – 418
T. 38 S., R. 25 E., SLM
Sec. 26: SW;
Secs. 27 and 28: All.
1,440.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
60
May 2019
UT0319 – 419
T. 38 S., R. 25 E., SLM
Sec. 33: N2;
Secs. 34 and 35: All.
1,600.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSU/TL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
61
May 2019
UT0319 – 420
T. 37 S., R. 26 E., SLM
Sec. 4: All;
Sec. 5: Lot 1, SENE, E2SE;
Sec. 8: W2E2NW, W2NW, SW, NWSWSE, S2S2SE.
1,129.95 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
NOTICES
T&E-06 Mexican Spotted Owl
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-28 California Condor
UT-LN-04: Crucial Mule Deer and Elk Winter Habitat
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-72: High Potential Paleontological Resources
62
May 2019
63
May 2019
UT0319 – 421
T. 37 S., R. 26 E., SLM
Secs 6: Lots 1-4, SWNE, S2NW, SW, W2SE, SESE;
Secs. 7, 17 and 18: All.
2,480.56 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-234: TL – Crucial Deer Winter Range
UT-S-288: CSU/TL – Mexican Spotted Owl
NOTICES
T&E-06 Mexican Spotted Owl
T&E-11: California Condor
UT-LN-04: Crucial Mule Deer and Elk Winter Habitat
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-72: High Potential Paleontological Resources
UT-LN-96: Air Quality Mitigation Measures
UT-LN-99: Regional Ozone Formation Controls
UT-LN-102: Air Quality Analysis
UT-LN-125: Light and Sound – Sensitive Resources
UT-LN-128: Floodplain Management
UT0319 – 422
T. 37 S., R. 26 E., SLM
Sec. 19: All;
Sec. 20: W2NWNW, SWNW, W2SENW, W2E2SW, W2SW;
Sec. 30: W2NE, W2;
Sec. 31: W2NE, SENE, W2, SE.
1840.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
64
May 2019
UT0319 – 423
T. 37 S., R. 26 E., SLM
Sec. 33: SESE;
T. 38 S., R. 26 E., SLM
Sec. 4: Lot 1, S2NE, S2NW, S2;
Secs. 5 and 6: All.
1,840.48 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSU/TL – Yellow-billed Cuckoo
65
May 2019
NOTICES
T&E-06 Mexican Spotted Owl
T&E-07: Southwestern Willow Flycatcher
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-72: High Potential Paleontological Resources
UT-LN-96: Air Quality Mitigation Measures
UT-LN-99: Regional Ozone Formation Controls
UT-LN-102: Air Quality Analysis
UT-LN-113: Yellow Billed Cuckoo
UT-LN-125: Light and Sound – Sensitive Resources
UT-LN-128: Floodplain Management
UT0319 – 424
T. 38 S., R. 26 E., SLM
Secs. 7, 17 and 18: All.
1,920.00 Acres
San Juan County, Utah
Monticello Field Office
STIPULATIONS
UT-S-01: Air Quality
UT-S-98: NSO – Fragile Soils/Slopes Greater than 40 Percent
UT-S-106: CSU – Fragile Soils/Slopes 21-40 Percent
UT-S-128: NSO – Floodplains, Riparian Areas, Springs, and Public Water Reserves
UT-S-170: CSU – Cultural
UT-S-182: NSO – Critical Habitat of the Endangered Colorado River Fishes
UT-S-288: CSU/TL – Mexican Spotted Owl
UT-S-290: CSU/TL – Southwestern Willow Flycatcher
UT-S-297: CSUTL – Yellow-billed Cuckoo
NOTICES
T&E-06 Mexican Spotted Owl
T&E-11: California Condor
T&E-26: Southwestern Willow Flycatcher Habitat– Riparian Areas
T&E-27: Yellow-billed Cuckoo
T&E-28 California Condor
UT-LN-25: White-Tailed and Gunnison Prairie Dog
66
May 2019
UT-LN-43: Raptors
UT-LN-44: Raptors
UT-LN-45: Migratory Bird
UT-LN-49: Utah Sensitive Species
UT-LN-67: Historical and Cultural Resource Values
UT-LN-68: Notification & Consultation Regarding Cultural Resources
UT-LN-72: High Potential Paleontological Resources
UT-LN-96: Air Quality Mitigation Measures
UT-LN-99: Regional Ozone Formation Controls
UT-LN-102: Air Quality Analysis
UT-LN-113: Yellow Billed Cuckoo
UT-LN-125: Light and Sound – Sensitive Resources
UT-LN-128: Floodplain Management
67
May 2019
AIR QUALITY
All new and replacement internal combustion gas field engines of less than or equal to 300 design-rated horsepower shall not
emit more than 2 grams of NOx per horsepower-hour.
Exception: This requirement does not apply to gas field engines of less than or equal to 40 design-rated horsepower.
UT-S-01 Modification: None
2008 RMPs Only Waiver: None
(Outside of AND
Moab MLP) All new and replacement internal combustion gas field engines of greater than 300 design rated horsepower must not emit
more than 1.0 gram of NOx per horsepower-hour.
Exception: None
Modification: None
Waiver: None
NO SURFACE OCCUPANCY – HOVENWEEP ACEC
(VISUAL EMPHASIS ZONE)
No surface-disturbing activities allowed within Hovenweep ACEC (visual emphasis zone).
UT-S-13
Exceptions: An exception could be granted if after an analysis the authorized officer determines that the project would be in
Monticello
the public interest.
Modification: None
Waiver: None
NO SURFACE OCCUPANCY – SHAY CANYON ACEC
No surface occupancy allowed within the Shay Canyon ACEC.
UT-S-14 Purpose: To protect cultural and historic values.
Monticello Exception: The Authorized Officer may grant an exception if it is determined that the factors leading to its inclusion in the
lease have changed sufficiently such that: 1) the protection provided by the stipulation is no longer justified or necessary to
meet resource objectives established in the Moab MLP; or 2) proposed operations would not cause unacceptable impacts.
The Authorized Officer may require additional plans of development, surveys, mitigation proposals, or environmental
68
May 2019
69
May 2019
70
May 2019
71
May 2019
72
May 2019
73
May 2019
74
May 2019
75
May 2019
76
May 2019
77
May 2019
78
May 2019
79
May 2019
Additional measures to avoid or minimize effects to the species may be developed and implemented in consultation with the
U.S. Fish and Wildlife Service between the lease sale stage and lease development stage to ensure continued compliance with
the ESA.
Modifications to the Surface Use Plan of Operations may be required in order to protect the MSO and/or habitat in
accordance with Section 6 of the lease terms, the Endangered Species Act, and the regulations at 43 CFR 3101.1-2.
Exception: An exception may be granted by the authorized officer if authorization is obtained from USFWS (through
applicable provisions of the ESA). The authorized officer may also grant an exception if an analysis indicates that the nature
or the conduct of the actions would not impair the primary constituent element determined necessary for the survival and
recovery of the MSO and USFWS through consultation concurs with this determination.
Modification: The authorized officer may modify the boundaries of the stipulation area if an analysis indicates and USFWS
(through applicable provisions of the ESA) determines a portion of the area is not being used as Critical Habitat.
Waiver: A waiver may be granted if the MSO is de-listed and the Critical Habitat is determined by USFWS as not necessary
for the survival and recovery of the MSO.
CONTROLLED SURFACE USE/TIMING LIMITATION – SOUTHWESTERN WILLOW FLYCATCHER
In areas that contain riparian habitat within the range for the Southwestern Willow Flycatcher, actions would be avoided or
restricted that may cause stress and disturbance during nesting and rearing of their young. Appropriate measures will depend
on whether the action is temporary or permanent, and whether it occurs within or outside the nesting season. A temporary
action is completed prior to the following breeding season leaving no permanent structures and resulting in no permanent
habitat loss. A permanent action continues for more than one breeding season and/or causes a loss of habitat or displaces
flycatchers through disturbances, i.e., creation of a permanent structure. The following avoidance and minimization measures
UT-S-290 have been designed to ensure activities carried out on the lease are in compliance with the Endangered Species Act.
Monticello Integration of, and adherence to these measures, will facilitate review and analysis of any submitted permits under the
(Outside of authority of this lease. Following these measures could reduce the scope of Endangered Species Act, Section 7 consultation
MLP) at the permit stage.
Current avoidance and minimization measures include the following:
1. Surveys will be required prior to operations unless species occupancy and distribution information is complete and
available. All surveys must be conducted by qualified individual(s) and be conducted according to protocol.
2. Activities will require monitoring throughout the duration of the project. To ensure desired results are being achieved,
minimization measures would be evaluated and, if necessary, Section 7 consultation reinitiated.
3. Water production will be managed to ensure maintenance or enhancement of riparian habitat.
80
May 2019
81
May 2019
82
May 2019
83
May 2019
84
May 2019
85
May 2019
UT-LN-20 ROCKY MOUNTAIN BIGHORN SHEEP CRUCIAL LAMBING AND RUTTING HABITAT
86
May 2019
87
May 2019
88
May 2019
89
May 2019
90
May 2019
91
May 2019
92
May 2019
93
May 2019
94
May 2019
95
May 2019
96
May 2019
97
May 2019
98
May 2019
99
May 2019
100
May 2019
101
May 2019
RESURVEY REQUIRED
UT-LN-148
The lessee/operator is given notice that an updated survey is required for this parcel. The legal
description and acreage is subject to change after the survey is complete.
COLORADO RIVER WILDLIFE MANAGEMENT AREA CONSERVATION EASEMENT
The lessee/operator is given notice that, due to the existence of the Colorado River Wildlife
Management Area Conservation Easement between the private land owner and the U.S. Fish and
UT-LN-155 Wildlife Service, the lessee/operator may not be able to access this lease from the private landowner's
surface. Any development proposed on the private land may be subject to the terms of that
Conservation Easement. The Bureau of Land Management, and this lease, do not guarantee access to
the lands within the Conservation Easement.
POLLINATORS AND POLLINATOR HABITAT
In order to protect pollinators and pollinator habitat, in accordance with BLM policy outlined in
Instruction Memorandum No. 2016-013, Managing for Pollinators on Public Lands, and Pollinator-
Friendly Best Management Practices for Federal Lands (2015), the following avoidance,
UT-LN-156 minimization, and mitigation measures would apply to this parcel:
Statewide 1. Give a preference for placing well pads in previously disturbed areas, dry areas that do not
(Based on the September support forbs, or areas dominated by nonnative grasses.
2018 San Rafael EA 2. Utilize existing well pads where feasible.
3. Avoid disturbance to native milkweed patches within Monarch migration routes to protect
DOI-BLM-UT-0000-2018-
Monarch butterfly habitat.
0001-EA
4. Avoid disturbance of riparian and meadow sites, as well as small depressed areas that may
function as water catchments and host nectar-producing species, to protect Monarch butterfly
habitat and nectaring sites.
5. Minimize the use of pesticides that negatively impact pollinators.
6. During revegetation treatments:
102
May 2019
103
May 2019
104
May 2019
105
May 2019
106
May 2019
107
May 2019
108
May 2019
109
May 2019
110
May 2019
111
May 2019
Appendix C – Figures/Maps
• Lease Sale Parcel Overview
• Hovenweep Viewshed Analysis
112
May 2019
113
May 2019
114
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
Leasing itself would not have impacts to air quality. However, should development
occur on issued leases, activities related to exploration, construction, drilling,
completion, testing, and production of an oil or gas well may affect air quality All
parcels are in areas designated as attainment or unclassifiable for all criteria air
pollutants.
Erik Vernon
PI Air Quality
4/16/2019
Air Quality Stips and LNs to be applied to all parcels:
UT-S-1: Air Quality
LN-96: Air Quality Mitigation Measures
LN-99: Regional Ozone Formation Controls
LN-102: Air Quality Analysis
John Chmelir
Areas of
(Cultural)
Critical
NP None of the parcels are within ACECs. 4/15/2019
Environmental
Jason Byrd
Concern
4/15/2019
BLM Natural Misti Haines
NP None of the parcels are within BLM Natural Areas
Areas 4/15/2019
BLM archaeologists have compiled cultural resources data from the Monticello field
office cultural resource libraries, GIS data (CURES), and the Preservation Pro
database area. These data sources contain information of all of the recorded cultural
resource sites and cultural resource survey data for the area available to BLM and the
Utah Division of State History. In addition, the BLM is using the field office cultural
resources planning model to help provide cultural resources information for areas not
previously surveyed (Beck et al. 2017).
Archaeologist use this data to determine if oil and gas development could occur
within each parcel while avoiding know cultural sites. The parcels are reviewed for
the application of stipulations and lease notices as required by the Monticello RMP.
The preliminary analysis using the cultural resources planning model (Beck et. Al.,
2017) indicates that, in the vast majority of the Monticello FO parcels, there is a high
probability of the presence of cultural resources. John Chmelir
4/15/2019
Cultural The Monticello RMP requires stipulation UT-S-170: CSU – Cultural to be attached
NI Glenn Stelter
Resources to all parcels.
4/17/2019
BLM received concurrence with its finding of No Adverse Effect to Historic
Properties from the Utah State Historic Preservation Officer on March 25, 2019.
BLM’s consultation with Native American Tribes, is ongoing.
For future undertakings related to this lease sale, BLM will not approve any ground
disturbing activities until it completes its obligations to consider cultural resources
under NEPA, NHPA and other authorities specific to those future undertakings.
Consideration of impacts to cultural resources and adverse effects to historic properties
will be taken into account during the review stage of site specific development plans.
From the cultural resource report for the March 2019 Oil and Gas Lease Sale, a total of
598 sites were identified within the parcels. 1006 sites were identified outside of the
parcels within a 1/2 buffer. The report identified cultural resources eligible to the
National Register of Historic Places (NRHP) as well as cultural resources that are not
115
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
eligible to the NRHP. The amount of cultural resource survey within the parcel area
ranges from 4.38% to 60.68%.
Greenhouse Gases (GHG) are composed mostly of CO2, CH4, N2O, HFCs, PFCs, &
Greenhouse SF6. Primary sources of GHG emissions include fossil fuel combustion for well
Erik Vernon
PI Gas/Climate construction and operation, fugitive CH4, and combustion of produced oil and gas. A
4/16/2019
Change representative emissions inventory of GHGs for parcel development, contribution to
cumulative emissions, and impacts to climate change should be presented.
Minority and low income populations do exist in the Monticello FO area. The
PRMP/FEIS, 2008 adequately assessed impacts to environmental justice population
as defined in Executive Order 12898 and it was determined that no BLM action
proposed across all alternatives or the Proposed Plan would target or cause any
disproportionate impacts to any minority or low income segments of the population
(Monticello PRMP/FEIS, 2008 p. 4-421).
Environmental All citizens can file an expression of interest or participate in the bidding process (43 CGiffen
NI
Justice CFR §3120.3-2). The stipulations and notices applied to the subject parcels do not 4/10/2019
place an undue burden on these groups.
Potential impacts to Environmental Justice from oil and gas leasing are adequately
analyzed and documented in the environmental analysis prepared for the Monticello
RMP. Actions and impacts are not changed from those disclosed in the existing
NEPA documents.
The impacts of oil and gas development on general wildlife and big game and general
wildlife species and their habitats were fully analyzed in the Monticello RMP, 2008
and the March 2018 EA. Actions and impacts are not changed from those disclosed
in these NEPA documents. See Wildlife and Botany Resources Leasing Assessment
for detailed species and habitat information.
The following stipulation will be attached, as noted to all parcels:
Oil and Gas development that may occur as a result of this lease sale may affect
floodplains. The decision to lease is connected to these impacts; however it does not Jed Carling
affect floodplains to a degree that detailed analysis is required. If an APD is filed, 04/11/19
NI Floodplains SOPs required by regulation and design features would be sufficient to isolate and
protect all usable ground or surface water sources before drilling or exploration begin. Ken Bradshaw
The SOPs include the requirements for disposal of produced water contained in 04/18/2019
Onshore Oil and Gas Order (O.O.) No. 7 and the requirements for drilling operations
contained in O.O No. 2. Potential fresh water aquifers zones would be protected by the
116
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
requirement of casing and cementing the drill hole to total depth. The casing would be
pressure tested to ensure integrity prior to drilling out the surface casing shoe plug.
Executive Order 11990 directs federal agencies to avoid short and long term impacts
to wetlands to the extent possible; Executive Order 11988 directs federal agencies to
avoid similar impacts through modification of floodplains, and to restore and preserve
the natural and beneficial values served by floodplains. The BLM Manual 1737 –
Riparian-Wetland Area Management, Riparian-Wetland Initiative provides direction
for planning and management actions related to riparian areas, and Instructional
Memorandum No UT 2005-091 provides specific guidance to Utah BLM riparian
lands while supporting all BLM national guidance directives.
UT-S-128: NSO -- Floodplains, Riparian Areas, Springs, and Public Water Reserves
will be attached to the following parcels: 406, 407, 408, 409, 410, 411, 412, 414, 415,
419, 423, and 424.
Given the executive directives, Stipulations, Lease Notices and mitigation measures
(e.g., BMPs and SOPs) discussed above, impacts to floodplains would be mitigated
and detailed analysis is not required in this EA.
Impacts to Fire and Fuels Management from leasing are adequately analyzed in the
Monticello RMP. Actions and impacts are not changed from those disclosed in these
NEPA documents. The implementation of appropriate reclamation standards at the
Fuels/Fire P. Plemons
NI APD stage would prevent an increase of hazardous fuels. Fuels and fire management
Management 04/15/19
would not be impacted by the lease process. Fuels projects planned for the parcels
proposed for competitive leasing would still be able to be implemented. BMPs, SOPs
and site specific mitigation may be applied at the APD stage as COAs.
The proposed action would not exceed the level of activity predicted in the
Reasonably Foreseeable Development Scenario (RFDS) prepared for the 2008
Monticello Field Office Resource Management Plan (RMP). The RFDS is
documented at section 2.2.1. Potential impacts to mineral resources and energy
production from oil and gas leasing and development are adequately analyzed and
documented in the Proposed RMP and Final Environmental Impact Statement
(FEIS). Actions and impacts are not changed from those disclosed in the existing
NEPA document.
Oil and gas exploration could lead to an increased understanding of the geologic
setting, as subsurface data obtained through lease operations may become public
T. McDougall
Mineral record. This information promotes an understanding of mineral resources as well as
4/11/19
NI Resources/Ener geologic interpretation. While conflicts could arise between oil and gas operations
Angela Wadman
gy Production and other mineral operations, these could generally be mitigated under 43 CFR
4/25/2019
3101.1-2 and under standard lease terms (Sec. 6) where sitting and design of facilities
may be modified to protect other resources.
The majority of flow back water from hydraulic fracturing in Utah is recycled and
used in future hydraulic fracturing completions. Therefore, the underground injection
of hydraulic fracturing flow back in Utah is very limited and presents little potential
for inducing seismic activity. In fact, there has been no reported induced seismicity in
Utah that was from water injected into Class II wells. Oil and gas wells produce a
great amount of wastewater. The majority this water has high salt brine content and
must be disposed of in an environmentally safe manner. In Utah, a majority (95%) of
this produced water is pumped into Class II injection wells. In certain parts of the
117
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
country, water injection /waste water disposal has caused some induced seismicity in
the form of small earthquakes. Two major factors play a role in induced seismicity
from water injection. First, the amount of water being injected. Secondly, the local
geology of the water injection site. In Utah, the volumes are lower than those states
experiencing induced seismicity. Also, the geology is different than those states
experiencing induced seismicity. The injection zones are stratigraphically thousands
of feet above the basement rock that may contain large unknown faults. Therefore, at
this time it appears that induced seismicity from water injection is not a problem in
the oil fields of Utah. (Personal communication from John Rogers, Utah Division of
Oil, Gas and Mining (UDOGM) to Angela Wadman, March 27, 2018 (BLM 2018)).
In conclusion, there would be no negative affects to mineral resources. Lease
Stipulations and Notices are created to mitigate impacts of oil and gas development
on other resources.
118
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
development and the application of these lease notices applied for Migratory
Birds/Raptors and their habitats were fully analyzed in the 2008 Monticello RMP.
Actions and impacts are not changed from those disclosed in these NEPA documents.
See Wildlife and Botany Resources Leasing Assessment for detailed species and
habitat information and Appendix A for the applicable lease notices and stipulations
developed in the 2008 Monticello RMP.
Migratory birds and raptors may be present within all of the proposed parcels. The
following lease notices will be applied, as noted to all parcels:
• UT-LN-43: (Raptors)
• UT-LN-45: (Migratory Bird)
Leasing would not, by itself, authorize any ground disturbances which could affect
these resources. This proposed action, the sale and issuance of an oil and gas leases, is
an administrative action that does not result in any surface disturbance. Site-specific
effects cannot be analyzed until an exploration or development application is received,
after leasing has occurred. Development proposals on the leases would be subject to
the standard lease terms, and all applicable laws, regulations and onshore orders in
existence at the time of lease issuance. The applied lease notices will ensure impacts to
raptors are minimized, and adequately mitigate potential lease development impacts to
those species. Implementing applicable lease notices at the development stage will
ensure leasing of identified parcels will not impact listed or proposed plant species to
the degree that will require additional detailed analysis in this EA.
BLM Manual Section 6840, requires consideration of sensitive species lists in
planning and environmental documents. Instructional Memorandum No. UT IM-
2019-005 provides the plant and wildlife Species lists for BLM-administered public
lands in Utah. The impacts of oil and gas development and the application of these
lease notices and stipulations applied on Utah BLM Sensitive Species and their
habitats were fully analyzed in the 2008 Monticello RMP. See Wildlife and Botany
Resources Leasing Assessment for detailed species and habitat information and
Appendix A for the applicable lease notices and stipulations developed in the 2008
Monticello RMP.
Potential for occurrence of Utah BLM Sensitive Species exists in all parcels, and the
following lease notice will apply to all parcels:
Utah BLM
Melissa Wardle
NI Sensitive
• LN-49: (Utah Sensitive Species) 4/15/2019
Species
Leasing would not, by itself, authorize any ground disturbances which could affect
these resources. This proposed action, the sale and issuance of an oil and gas leases,
is an administrative action that does not result in any surface disturbance. Site-
specific effects cannot be analyzed until an exploration or development application is
received, after leasing has occurred. Development proposals on the leases would be
subject to the standard lease terms, and all applicable laws, regulations and onshore
orders in existence at the time of lease issuance. The applied lease notices will ensure
impacts to BLM Sensitive Species are minimized, and adequately mitigate potential
lease development impacts to those species. Implementing applicable lease notices at
the development stage will ensure leasing of identified parcels will not sensitive
species to the degree that will require additional detailed analysis in this EA.
The sale and issuance of an oil and gas lease is an administrative action that does not
Native directly result in any surface disturbance. However, the issuance of a lease is
considered to be an irretrievable commitment of resources because the BLM John Chmelir
American
NI generally cannot deny all surface use of a lease unless the lease is issued with a no 4/15/2019
Religious
Concerns surface occupancy stipulation.
The lessee/operator would submit an APD when oil and gas exploration and
119
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
development activities are proposed. The APD would be subject to site specific
NEPA analysis and relevant cultural resource avoidance or mitigation measures if
warranted.
Government to Government consultations with Native American Tribes were initiated,
by certified letter, on November 6, 2018.
Responses have been received from several tribes, by letter and by phone.
Consultation with Native American tribes is ongoing.
Native American Religious Concerns Stipulations and Lease Notices to all parcels;
UT-S-170:CSU; Cultural
LN-67; Historical And Cultural Resource Values
LN-68: Notification & Consultation Regarding Cultural Resources
Impacts to the paleontological resources from leasing are contained in the analysis
for the Monticello RMP.
The lessee/operator would submit an APD when oil and gas exploration and
development activities are proposed. The APD would be subject to site specific
NEPA analysis.
All lease parcels contain areas of high potential for paleontological resources. The
Monticello RMP contains management decisions to protect paleontological Angela Bulla
NI Paleontology
resources. Lease notice UT-LN-72: High Potential Paleontological Resources will be 4/11/2019
attached to all parcels as specified by the Monticello RMP
Potential impacts to rangeland health standards from oil and gas leasing are
adequately analyzed and documented in the environmental analysis prepared for the
Monticello 2008 RMP. Actions and impacts are not changed from those disclosed in
these NEPA documents.
Impacts to recreation from leasing are contained in the analysis for the Monticello
RMP. Actions and impacts are not changed from those disclosed in these NEPA
Jason Byrd
NI Recreation documents. No leases are adjacent to developed recreation sites or other recreation
4/15/2019
areas that would require additional stipulations or notices. These sites are not highly
used recreation areas.
Potential impacts to socio economics from oil and gas leasing are adequately
Socio- analyzed and documented in the environmental analysis prepared for the Monticello CGiffen
NI
Economics RMP. Actions and impacts are not changed from those disclosed in these NEPA 4/10/2019
documents.
The lessee/operator would submit an APD when oil and gas exploration and CGiffen
NI Soils development activities are proposed. The APD would be subject to site specific 4/10/2019
NEPA analysis. An approved APD is subject to standard operating procedures (SOP) Ken Bradshaw
120
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
required by regulation, stipulations attached to the lease, best management practices 4/18/2019
(BMP) included in the APD submission, and conditions of approval (COA)
developed during the NEPA analysis and documentation process. These SOPs,
BMPs, and COAs, mitigate impacts to other resources and users from oil and gas
exploration and development activities.
These lease stipulations, SOPs BMPs and COAs, including erosion control and
reclamation standards, would adequately mitigate impacts to the soil resource.
Potential impacts to soils from oil and gas leasing are adequately analyzed and
documented in the environmental analysis prepared for the Monticello RMP.
Actions and impacts are not changed from those disclosed in these NEPA documents.
The Endangered Species Act (ESA) requires federal agencies, in consultation with the
USFWS, to ensure that actions they authorize, fund or carry out are not likely to
jeopardize the continued existence of federally listed endangered or threatened
species, or result in destruction or adverse modification of their designated critical
habitat (16 U.S.C. §1531 et seq. (1973)). Through formal consultation with the FWS
during the development of the 2008 Monticello RMP, lease stipulations and notices
where developed to ensure listed species and habitats would receive needed protective
measures to ensure impacts from development activities are minimized. See Wildlife
and Botany Resources Leasing Assessment for detailed species and habitat
information and Appendix A for the applicable lease notices and stipulations
developed in the 2008 Monticello RMP. No habitat for the Navajo sedge or Jones’
Threatened, cycladenia occurs on the proposed parcels. The following lease notices will be Melissa Wardle
Endangered or applied: 4/15/2019
NI
Candidate Plant Karen Cathey
• Handbook H-3120-1: (Endangered Species Act) – All parcels
Species 05/06/2019
This proposed action, the sale and issuance of an oil and gas leases, is an
administrative action that does not result in any surface disturbance. Site-specific
effects cannot be analyzed until an exploration or development application is received,
after leasing has occurred. The BLM will consult with the USFWS as appropriate on
possible effects to federally listed species from this lease sale and during review of
future development plans. The applied lease notices and future consultation as
appropriate will ensure compliance with the ESA and adequately mitigate potential
lease development impacts to federally listed or proposed species/habitat.
Implementing applicable lease notices at the development stage will ensure leasing of
identified parcels will not impact listed or proposed species to the degree that will
require additional detailed analysis in this EA.
The Endangered Species Act (ESA) requires federal agencies, in consultation with
the USFWS, to ensure that actions they authorize, fund or carry out are not likely to
Threatened, jeopardize the continued existence of federally listed endangered or threatened Melissa Wardle
Endangered or species, or result in destruction or adverse modification of their designated critical 4/15/2019
NI
Candidate habitat (16 U.S.C. §1531 et seq. (1973)). Through formal consultation with the FWS Karen Cathey
Animal Species during the development of the 2008 Monticello RMP, lease stipulations and notices 05/06/2019
where developed to ensure listed species and habitats would receive needed
protective measures to ensure impacts from development activities are minimized.
121
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
See Wildlife and Botany Resources Leasing Assessment for detailed species and
habitat information and Appendix A for the applicable lease notices and stipulations
developed in the 2008 Monticello RMP. Potential habitat for the California condor,
Mexican spotted owl, southwestern willow flycatcher, yellow-billed cuckoo may
occur. In addition, due to potential water depletion through development, the
Bonytail chub, Colorado pikeminnow, humpback chub, and razorback sucker may be
indirectly affected, as indicated by application of the following lease stipulations:
There is consensus among BLM hydrologists and related resource specialties that
these required design criteria would minimize the potential for impacts to water
resources if/when development occurs. If leasing was proposed in an unusually
sensitive area, if foreseeable development was expected to be of high intensity, or if
water resource concerns unknown to BLM were brought forward then there may be a
122
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
need for detailed analysis in an EA. None of these conditions apply for this lease sale
and therefore detailed analysis is not required for this lease level EA. It may be
necessary to undertake detailed analysis of impacts to water resources when specific
plans for development are proposed, but the decision whether to complete NEPA
analysis will be made at that time based on scoping, issue sensitivity, and other
considerations.
Parcels 407 and 419 contain Public Water Reserves and Stipulation UT-S-128
NSO—Floodplains, Riparian Areas, Springs, and Public Water Reserves will be
attached to those parcels. There are also water rights within and/or adjacent to all
parcels.
Leasing the proposed parcels would not, by itself, authorize any disturbances or
impact water rights. Site-specific effects cannot be analyzed until an exploration or
development application is received, after leasing has occurred. However, any
development proposal on the lease parcels would be subject to the standard lease
terms, the protective lease notices and stipulations identified in Appendix A, and all
applicable laws, regulations and onshore orders in existence at the time of lease
issuance. Site- specific analysis would be required prior to the approval of any
ground disturbance proposal on the lease parcels. In addition water rights are
protected under State Law, and a junior water right holder is liable for damages
caused when senior water right holders are impacted by their water use.
123
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
"The above conclusions are based on cases of identified impacts and other data,
information, and analyses presented in the report. Cases of impacts were identified for
all stages of the hydraulic fracturing water cycle. Identified impacts generally occurred
near hydraulically fractured oil and gas production wells and ranged in severity, from
temporary changes in water quality to contamination that made private drinking water
wells unusable” (EPA 2016 p. ES-3-4).
If fracking should occur in an area where there is no vertical separation between the
hydraulically fractured rock formation and the bottom of the potential underground
drinking water source, fracking fluid may be introduced into the source. However, the
occurrence of fracking within a potential drinking water source is low, concentrated in
a few fields in Wyoming and Montana (EPA 2016 p. ES-8).
Produced water can contain many constituents depending on the composition of the
injected hydraulic fracturing fluid and the type of rock being fractured. Produced
water has been found to contain salts, metals, benzene, toluene, ethylbenzene, and
xylenes (BTEX), oil and grease, radioactive materials, and hydraulic fracturing
chemicals and their chemical transformation products. (EPA 2016 p. ES-33). Overall,
the severity of impacts on water quality from produced water spills depends on the
identity and amount of water spilled, the toxicity of constituents in the water, and the
characteristic of the receiving groundwater or surface water; and spill prevention and
response can prevent and/or minimize contamination of water resources (EPA 2016 p.
ES-37).
The measures required (spill containment systems, casing integrity testing, pit lining),
etc. for all wells drilled in Utah, fracked or not, are adequate to prevent fracking fluids
as well as hydrocarbons and produced water from the wells to prevent ground/surface
water contamination. The UDOGM has promulgated rules to prevent environmental
impacts from fracking (Utah Administrative Code R649-3-39). Further
analysis/mitigation of impacts is not warranted.
Oil and Gas development that may occur as a result of this lease sale may affect water
resources. The decision to lease is connected to these impacts; however it does not
affect water resources to a degree that detailed analysis is required. If an APD is filed,
SOPs required by regulation and design features would be sufficient to isolate and
protect all usable ground or surface water sources before drilling or exploration begin.
The SOPs include the requirements for disposal of produced water contained in
Onshore Oil and Gas Order (O.O.) No. 7 and the requirements for drilling operations
contained in O.O No. 2. Potential fresh water aquifers zones would be protected by the
requirement of casing and cementing the drill hole to total depth. The casing would be
pressure tested to ensure integrity prior to drilling out the surface casing shoe plug.
Melissa Wardle
Surface Water Requirements under O.O. 2 and O.O. 7, along with stipulation UT-S-128 NSO— 4/15/2019
NI Resources/Qual Floodplains, Riparian Areas, Springs, and Public Water Reserves will be attached to
ity parcels 406, 407, 408, 409, 410, 411, 412, 414, 415, 419, 422, 423, and 424. Ken Bradshaw
4/19/2019
In addition to requirements under O.O. 2 and O.O. 7 to protect surface water, BMPs
and mitigation measures that limit surface disturbances in or adjacent to intermittent
and perennial streams, wetlands, floodplains, and/or riparian areas maintain the health
and function of those areas. In addition, BMPs and mitigation measures that reduce
surface disturbances on soils help to reduce the potential for soil compaction, rutting,
and erosion, and lessen impacts to surface water quality.
Given the Stipulations, Lease Notices and mitigation measures (e.g., BMPs and SOPs)
discussed above, impacts to surface water quality would be mitigated and detailed
analysis is not required in this EA.
124
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
Oil and Gas development that may occur as a result of this lease sale may affect
wetland/riparian resources. The decision to lease is connected to these impacts;
however it does not affect water resources to a degree that detailed analysis is
required. If an APD is filed, SOPs required by regulation and design features would be
sufficient to isolate and protect all usable ground or surface water sources before
drilling or exploration begin. The SOPs include the requirements for disposal of
produced water contained in Onshore Oil and Gas Order (O.O.) No. 7 and the
requirements for drilling operations contained in O.O No. 2. Potential fresh water
aquifers zones would be protected by the requirement of casing and cementing the drill
hole to total depth. The casing would be pressure tested to ensure integrity prior to
drilling out the surface casing shoe plug.
Executive Order 11990 directs federal agencies to avoid short and long term impacts
to wetlands to the extent possible; Executive Order 11988 directs federal agencies to Jed Carling
avoid similar impacts through modification of floodplains, and to restore and 4/11/19
preserve the natural and beneficial values served by floodplains. The BLM Manual
Wetlands/Ripar 1737 – Riparian-Wetland Area Management, Riparian-Wetland Initiative provides
NI Ken Bradshaw
ian Zones direction for planning and management actions related to riparian areas, and 4/19/2019
Instructional Memorandum No UT 2005-091 provides specific guidance to Utah Karen Cathey
BLM riparian lands while supporting all BLM national guidance directives.
05/06/2019
Local knowledge, review of corporate GIS data, and review of the National Wetlands
Inventory identified the presence of springs, and other in the following parcels: 406,
407, 408, 409, 410, 411, 412, 414, 415, 416, 417, 418, 419, 421, 422, 423, and 424.
The following stipulations to be applied, as noted:
Given the executive directives, Stipulations, and mitigation measures (e.g., BMPs and
SOPs) discussed above, impacts to riparian resources, wetlands, and floodplains would
be mitigated and detailed analysis is not required in this EA.
.
There are no parcels within river segment corridors identified as suitable for
Wild and Silas Sparks
NP designation into the National Wild and Scenic River System (NW&SR). There are no
Scenic Rivers 4/12/19
designated NW&SR system river segments in the Monticello Field Office.
Wilderness/WS Misti Haines
NP There are no parcels within Wilderness or Wilderness Study Areas
A 4/15/2019
Potential impacts to woodlands and forestry from oil and gas leasing are adequately
analyzed and documented in the environmental analysis prepared for the Monticello Melissa Wardle
Woodland /
NI RMP. Actions and impacts are not changed from those disclosed in these NEPA 4/15/2019
Forestry
documents. Additional site specific review will occur at the development stage.
Vegetation Potential impacts to Vegetation Excluding USFWS Designated Species from oil and N. Noyes
Excluding gas leasing are adequately analyzed and documented in the environmental analysis 4/11/19
NI USFWS prepared for the Monticello 2008 RMP. Actions and impacts are not changed from Karen Cathey
Designated those disclosed in these NEPA documents, and further detailed analysis here is not 05/06/2019
Species necessary.
Potential impacts to visual resources from oil and gas leasing are adequately analyzed
Visual and documented in the environmental analysis prepared for the Monticello RMP, S. Sparks
NI
Resources which assigned visual resource management classes to these areas. Actions and 4/15/19
impacts are not changed from those disclosed in these NEPA documents
125
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
Parcel 408 and a portion of Parcel 407 are in VRM Class III. The goals of this
management class are partially retain the existing character of the landscape. Change
allowed may be moderate and activities may attract attention but should not dominate
the view. The remaining parcels are in VRM Class IV. This management class allows
for a high degree of change and activities that require major modification of the
existing character of the landscape.
Potential future development of these parcels could be visible from key observation
points and could potentially impact Visual Resources through modifications to the
landscape that would attract the attention of the casual observer. However, such
impacts would be mitigated and/or prevented at the development stage through the
use of best management practices such as strategic siting, color camouflaging, and
vegetative screening of facilities. The leasing and potential future development of all
parcels included in the proposed action would conform to all applicable Visual
Resource Management objectives established in the Monticello RMP.
• The Monticello RMP, 2008 decision WC-1 (page 85) identified which of
these lands would be managed to “Protect, maintain and preserve wilderness
characteristics.” These inventories identified the following lands adjacent to
the Squaw and Papoose Canyons WSA as possessing wilderness
characteristics:
Squaw and Papoose Canyons Unit
• 041 956
• 042 592
• 043 272
• 045 26
Total 1,846
On October 21, 2014, the Southern Utah Wilderness Alliance (SUWA) submitted
information suggesting the presence of wilderness characteristics in the Tin Cup
Mesa and Monument Canyon units. BLM conducted an analysis and lands within
these units were found to possess wilderness character (WC) as determined by
Documentation of BLM Wilderness Characteristics Inventory Findings.
The parcels and acreage of LWC are:
126
May 2019
Determi-
Resource Rationale for Determination* Parcel Reviewer
nation
Leasing of these parcels may result in the loss of WC in these areas. While these
areas were found to possess wilderness characteristics as determined subsequent to
the RMP, only those areas designated in RMP decision WC-1 will be managed to
“Protect, maintain and preserve wilderness characteristics …”
127
May 2019
Appendix E – References
AECOM. 2014. "Utah Air Resource Management Strategy Modeling Project Impact Assessment
Report." Bureau of Land Management. October. Accessed August 17, 2018.
https://www.blm.gov/sites/blm.gov/files/program_natural%20resources_soil%20air%20
water_airut_quick%20links_ImpactsRpt.pdf.
APCD. 2017. "Colorado Air Pollution Control Division, Department of Public Health and
Environment. PS Memo 05-01." State of Colorado. Accessed August 16, 2018.
https://www.colorado.gov/pacific/sites/default/files/AP_Memo-05-01-Oil-and-Gas-
Condensate-Tank-Batteries-Guidance.pdf.
BLM. 2008. Bureau of Land Management, Oil and Gas, Other Helpful Links. Accessed August
29, 2018.
https://www.blm.gov/sites/blm.gov/files/EPCA_III_Inventory_Onshore_Federal_Oil_Ga
s.pdf.
—. 2015. "Air Resource Management Program Strategy 2015-2020 ." Bureau of Land
Management. February. Accessed August 17, 2018.
https://www.blm.gov/sites/blm.gov/files/AirResourceProgramStrategy.pdf.
—BLM. 2008. "Biological Opinion for BLM Monticello Field Office RMP." West Valley City,
UT. https://eplanning.blm.gov/epl-front-
office/projects/lup/68097/85495/102695/Monticello_Biological_Opinion.pdf.
—. 2008. BLM Monticello Field Office Record of Decision and Approved RMP (UT-090-2007-
40). Monticello, Utah. https://eplanning.blm.gov/epl-front-
office/projects/lup/68097/85493/102694/Monticello_Final_Plan.pdf.
—. 2013. "BLM. 2013. H-3120 Competitive Oil and Gas Leasing."
https://www.blm.gov/sites/blm.gov/files/uploads/Media_Library_BLM_Policy_h3120.pd
f.
—. 2010. "Climate Change Supplementary Information Report For Montana, North Dakota, and
South Dakota, Bureau of Land Management." Report on Greenhouse Gas Emissions and
Climate Change for Montana, North Dakota, and South Dakota. Technical report
prepared for the Montana/Dakotas Bureau of Land Management by URS Corporation.
URS Project 22241790.
BLM. 2007. Final Vegetation Treatments Using Herbicides Programmatic Environmental
Impact Statement and Record of Decision. Washingtion, D.C., September.
https://eplanning.blm.gov/epl-front-
office/eplanning/planAndProjectSite.do?methodName=dispatchToPatternPage¤tP
ageId=103592.
BLM. 2018. "Instruction Memorandum 2018-014 Directional Drilling into Federal Mineral
Estate from Well Pads on Non-Federal Locations." Washington, D.C., D.C.
https://www.blm.gov/policy/pim-2018-014.
—. 1986. "Manual H-8410-1 - Visual Resource Inventory." Washington, D.C.: Washington
Office, January 17.
128
May 2019
BLM. 2018. March 2018 Canyon Country District Competitive Oil and Gas Lease Sale. Moab.
doi:https://eplanning.blm.gov/epl-front-
office/eplanning/planAndProjectSite.do?methodName=dispatchToPatternPage¤tP
ageId=122746.
BLM. 2019. "March 2019 Lease Sale Cultural Resources Report (Utah SHPO Case No. 19-
0235)." Salt Lake City, UT.
—. 2008. Migratory Bird Treaty Act Interim Guidance (IM 2008-050).
https://www.blm.gov/policy/im-2008-050.
—. 2016. Moab Master Leasing Plan and Proposed RMP Amendments/FEIS for Moab and
Monticello Field Offices (DOI-BLM-UT-Y010-2012-0107-EIS). Moab, Utah.
https://eplanning.blm.gov/epl-front-
office/eplanning/planAndProjectSite.do?methodName=dispatchToPatternPage¤tP
ageId=99718.
—. 2008. Monticello Field Office Proposed RMP and FEIS. Monticello: Monticello Field Office.
https://eplanning.blm.gov/epl-front-office/projects/lup/68097/85623/102818/RMP.pdf.
—. 2005. Monticello Reasonable Foreseeable Development Scenario (RFD) For Oil and Gas.
Monticello, Utah. https://eplanning.blm.gov/epl-front-
office/projects/lup/68097/85828/103015/RFD.pdf.
BLM. 2017. Monticello RMP Land Use Amendment/Maintence Change No. 102. Monticello,
July 24. https://eplanning.blm.gov/epl-front-
office/projects/lup/68097/144192/177756/Monticello_RMP_Maintenance_102.pdf.
—. 2012. Reasonably Foreseeable Development Scenario for Oil and Gas in the Moab MLP
Area, Canyon Country District. Moab, Utah: Bureau of Land Management.
https://eplanning.blm.gov/epl-front-
office/projects/lup/68430/88315/105655/MLP_OG_RFD_final_091012_508_web.pdf.
BLM. 2018. "Threatend and Endangered Species Report for western yellow-billed cuckoo."
West Valley.
—. 2018. "Utah Air Resource Management Strategy (ARMS)." Bureau of Land Management.
Accessed April 23, 2019. https://go.usa.gov/xmDkx.
BLM. 2014. Utah Air Resource Management Strategy Modeling Project Impact Assessment
Report. Modeling Project, Fort Collins: AECOM. Accessed August 2018.
https://www.blm.gov/sites/blm.gov/files/program_natural%20resources_soil%20air%20
water_airut_quick%20links_ImpactsRpt.pdf.
—. 2011. "Utah BLM Sensitive Fish and Widlife Species List."
BLM. 2017. "Utah Greater Sage-grouse Adaptive Trigger Review - Rich."
BLM, USGS, USFS, DOE, and EIA. 2008. Inventory of Onshore Federal Oil and Natural Gas
Resources and Restrictions to Their Development. Phase III Inventory. BLM/WO/GI-
03/0002+3100/REV08. Prepared by the U.S. Departments of the Interior, Agriculture,
and Energy.
https://www.blm.gov/sites/blm.gov/files/EPCA_III_Inventory_Onshore_Federal_Oil_Ga
s.pdf.
129
May 2019
Boden, T A, G Marland, and R J Andres. 2013. Global, regional, and national fossil-fuel CO2
emissions. Oak Ridge, TN: Carbon Dioxide Information Analysis Center, Oak Ridge
National Laboratory. doi:10.3334/CDIAC/00001_V2013.
Cochran, J. F. and Anderson, S. H. 1987. "Comparison of habitat attributes at sites of stable."
Great Basin Naturalist 47 (3): 460-466. Accessed 11 5, 2018. :
https://scholarsarchive.byu.edu/gbn/vol47/iss3/8.
eBird. 2017. "eBird: An online database of bird distribution and abundance [web application].
eBird, Cornell Lab of Ornithology, Ithaca, New York." Accessed December 2017.
http://www.ebird.org.
—. 2018. eBird: An online database of bird distribution and abundance [web application].
eBird, Cornell Lab of Ornithology, Ithaca, NY. Accessed August 2018.
http://www.ebird.org.
EIA. 2018. "Petroleum & Other Liquids." US Energy Information Administration. Accessed
August 16, 2018. https://www.eia.gov/petroleum/data.php.
EPA. 2018. "Air Emissions Factors and Quantification. AP-42, Fifth Edition Compilation of Air
Pollutant Emissions Factors, Volume 1: Stationary Point and Area Sources." Accessed
March 23, 2018. https://www.epa.gov/air-emissions-factors-and-quantification/ap-42-
compilation-air-emissions-factors and
https://www3.epa.gov/tnn/chief/ap42/ch05/index.html.
—. 1995. "AP-42: Compilation of Air Emissions Factors." United States Environmental
Protection Agency. Accessed August 16, 2018. https://www.epa.gov/air-emissions-
factors-and-quantification/ap-42-compilation-air-emissions-factors#5thed.
—. 2018. "Compliance. National Emission Standards for Hazardous Air Pollutants Compliance
Monitoring. ." Accessed March 23, 2018. https://www.epa.gov/compliance/national-
emission-standards-hazardous-air-pollutants-compliance-monitoring.
—. 2018. Criteria Air Pollutants. Accessed August 16, 2018. https://www.epa.gov/criteria-air-
pollutants.
—. Undated. "Final Area Designations for the 2015 Ozone NAAQS, Technical Support
Document." United States Environmental Protection Agency. Accessed August 16, 2018.
https://www.epa.gov/sites/production/files/2018-05/documents/ut_tsd_final.pdf.
—. 2016. "Hydraulic Fracturing for Oil and Gas: Impacts from the Hydraulic Fracturing Water
Cycle on Drinking Water Resources in the United States (Final Report), Washington,
DC, EPA/600/R-16/236F,2016. ."
https://cfpub.epa.gov/ncea/hfstudy/recordisplay.cfm?deid=332990.
—. 2018. "Inventory of U.S. Greenhouse Gas Emissions and Sinks: 1990-2016." United States
Environmental Protection Agency. Accessed August 16, 2018.
https://www.epa.gov/ghgemissions/inventory-us-greenhouse-gas-emissions-and-sinks-
1990-2016.
—. 2018. "Inventory of U.S. Greenhouse Gas Emissions and Sinks: 1990-2016." EPA
Greenhouse Gas Emissions. Accessed 11 9, 2018.
130
May 2019
https://www.epa.gov/sites/production/files/2018-
01/documents/2018_complete_report.pdf.
—. 2011. "Lessons Learned from Natural Gas STAR Partners." Reduced Emissions Completions
for Hydraulically Fractured Natural Gas Wells. Accessed March 23, 2018.
https://www.epa.gov/sites/production/files/2016-
06/documents/reduced_emissions_completions.pdf.
—. 2018. NAAQS Table. Accessed August 16, 2018. https://www.epa.gov/criteria-air-
pollutants/naaqs-table.
—. 2018. National Emission Standards for Hazardous Air Pollutants (NESHAP). Accessed
August 16, 2018. https://www.epa.gov/stationary-sources-air-pollution/national-
emission-standards-hazardous-air-pollutants-neshap-9.
—. 2018. National Emission Standards for Hazardous Air Pollutants Compliance Monitoring.
Accessed August 16, 2018. https://www.epa.gov/compliance/national-emission-
standards-hazardous-air-pollutants-compliance-monitoring.
—. 2011. "National Interagency Memorandum of Understanding Among USDA, USDI and
EPA, Regarding Air Quality Analysis and Mitigation for Federal Oil and Gas Decisions
Through the NEPA Process." United States Environmental Protection Agency. Accessed
August 16, 2018. https://www.epa.gov/sites/production/files/2014-08/documents/air-
quality-analyses-mou-2011.pdf.
—. 2018. "New Source Review (NSR) Permitting. Prevention of Significant Deterioration Basic
Information. ." Accessed March 23, 2018. https://www.epa.gov/nsr/prevention-
significant-deterioration-basic-information.
—. 2018. Oil and Gas Extraction Sector (NAICS 211). Accessed August 16, 2018.
https://www.epa.gov/regulatory-information-sector/oil-and-gas-extraction-sector-naics-
211.
—. 2018. Oil and Gas Extraction Sector (NAICS 211). Accessed March 23, 2018.
https://www.epa.gov/regulatory-information-sector/oil-and-gas-extraction-sector-naics-
211.
—. 2018. Oil and Natural Gas Production Facilities: National Emission Standards for
Hazardous Air Pollutants (NESHAP). Accessed March 23, 2018.
https://www.epa.gov/stationary-sources-air-pollution/oil-and-natural-gas-production-
facilities-national-emission.
—. 2018. Overview of Greenhouse Gases. Accessed August 16, 2018.
https://www.epa.gov/ghgemissions/overview-greenhouse-gases.
—. 2017. "Ozone Designations - 2015 Standards - Utah State Recommendations and EPA
Response." United States Environmental Protection Agency. December 20. Accessed
August 16, 2018. https://www.epa.gov/sites/production/files/2017-12/documents/ut-epa-
resp-ozone.pdf.
—. 2018. Prevention of Significant Deterioration Basic Information. Accessed August 16, 2018.
https://www.epa.gov/nsr/prevention-significant-deterioration-basic-information.
131
May 2019
132
May 2019
McGrew, John C. 1977. "Distribution and Habitat Characteristics of the Kit Fox (Vulpes
Macrotis) in Utah." All Graduate Theses and Dissertations. 3252.
https://digitalcommons.usu.edu/etd/3252.
NABCI. 2000. "North American Bird Conservation Initiative Bird Conservation Region
Descriptions, A Supplement to the North American Bird Conservation Initiative bird
Conservation Regions Map." 38.
NASA. 2018. "Earth Observatory." NASA. Accessed August 16, 2018.
https://earthobservatory.nasa.gov/images/91604.
NCDC. 2018. Climate at a Clance. Accessed 11 9, 2018. https://www.ncdc.noaa.gov/cag/.
NPS. 2010. "Federal land managers’ air quality related values work group (FLAG): phase I
report—revised (2010)." Accessed August 16, 2018. doi:Natural Resource Report
NPS/NRPC/NRR—2010/232.
—. 2018. Park Conditions and Trends. Accessed November 09, 2018.
https://www.nps.gov/subjects/air/park-conditions-trends.htm.
Olendorff, R. R. 1993. Status, biology, and management of ferruginous hawks: a review. Special
Report, Boise, Idaho: Raptor Research and Technical Assistance Center, Bureau of Land
Management, U. S. Department of the Interior.
Pardieck, K.L., D.J. Ziolkowski Jr., M. Lutmerding, K. Campbell and M.-A.R. Hudson. 2017.
North American Breeding Bird Survey Dataset 1966 - 2016, version 2016.0. U.S.
Geological Survey, Patuxent Wildlife Research Center.
<www.pwrc.usgs.gov/BBS/RawData/>. 2017. North American Breeding Bird Survey
Dataset 1966 - 2016, version 2016.0. U.S. Geological Survey, Patuxent Wildlife
Research Center. doi:10.5066/F7W0944J.
Parrish, J. R., F. P. Howe, and R. Norvell. 2002. "The Utah avian conservation strategy, version
2.0. ." Salt Lake City, UT: Utah Partners in Flight Program, Utah Division of Wildlife
Resources.
Paton. Peter W.C. and Dalton, Jack. 1994. "Breeding ecology of Long-billed Curlews at Great
Salt Lake, Utah." Great Basin Naturalist 54 (1): 79-85. Accessed 11 5, 2018.
https://scholarsarchive.byu.edu/gbn/vol54/iss1/4.
RINS. 2017. Raptor Inventory Nest Survey database. RINS.org.
Romin, L.A. and J.A. Muck. 2002. "Utah field office guidelines for raptor protection from
human and land use disturbances." Salt Lake City, UT: U.S. Fish and Wildlife Service.
State of Utah. 2018. State of Utah Resource Managment Plan. Salt Lake City, Utah: State of
Utah. Accessed August 2018. http://publiclands.utah.gov/current-projects/rmp/.
—. 2016. "Utah 2015 8-Hour Ozone Designation Recommendation." State of Utah, Utah
Division of Air Quality. September 29. Accessed August 16, 2018.
https://documents.deq.utah.gov/air-quality/planning/air-quality-policy/DAQ-2017-
002764.pdf.
133
May 2019
Team, CRCT Coordination. 2006. "CRCT Coordination Team. 2006. Conservation strategy for
Colorado River cutthroat trout (Oncorhynchus clarkia pleuriticus) in the States of
Colorado, Utah, and Wyoming. Colorado Division of Wildlife, Fort Collins. 24p."
UDAQ. 2018. General Approval Orders. Accessed August 16, 2018.
https://deq.utah.gov/legacy/permits/general-approval-orders/.
—. 2018. "News and Announcements, Utah Division of Air Quality 2017 Annual Report." Utah
Department of Environmental Quality Air Quality. Accessed August 16, 2018.
https://documents.deq.utah.gov/air-quality/annual-reports/DAQ-2018-001005.pdf.
—. 2016. "Utah Area Designation Recommendations for teh 2015 8-Hour Ozone National
Ambient Air Quality Standard." State of Utah, Utah Division of Air Quality. September.
Accessed August 16, 2018. https://documents.deq.utah.gov/air-quality/planning/air-
quality-policy/DAQ-2017-002501.pdf.
UDOGM. 2018. Production Volumes. Accessed September 21, 2018.
https://oilgas.ogm.utah.gov/oilgasweb/statistics/statistics-main.xhtml.
—. 2017. Utah Natural Gas Production by County (past 5 years). Accessed August 13, 2018.
https://oilgas.ogm.utah.gov/oilgasweb/statistics/gas-prod-by-cnty.xhtml.
—. 2018. "Utah Oil Production by County (past 5 years)." State of Utah, Division of Oil, Gas
and Mining. Accessed August 16, 2018.
https://oilgas.ogm.utah.gov/oilgasweb/statistics/oil-prod-by-cnty.xhtml.
UDWQ. 2016. Utah’s Final 2016 Integrated Report. Salt Lake City, Utah: Utah Department of
Environmental Quality.
UDWR. n.d. Mexican Spotted Owl.
https://dwrcdc.nr.utah.gov/rsgis2/Search/Display.asp?FlNm=striocci.
UDWR. 2000. Range-wide Conservation Agreement and Strategy for Bonneville Cutthroat Trout
(Oncorhynchus clarki utah). Publication Number 00-19, Salt Lake City, UT: Utah
Division of Wildlife Resources.
UDWR. 2013. Utah Natural Heritage Program. http://dwrcdc.nr.utah.gov/ucdc/.
UDWR. 2009. Utah Pronghorn Statewide Management Plan. Utah Department of Wildlife
Resources, Division of Wildlife Resources, 21.
United States Department of the Interior and United States Department of Agriculture. 2007.
Surface Operating Standards and Guidelines for Oil and Gas Exploration and
Development. BLM/WO/ST-06/021+307/REV 07. . Denver, Colorado: Bureau of Land
Management.
USDI and USDA. 2007. "The Gold Book." Vers. Fourth Edition - Revised 2007. Bureau of Land
Management. Accessed August 29, 2018. https://www.blm.gov/programs/energy-and-
minerals/oil-and-gas/operations-and-production/the-gold-book.
USFWS. 2007. Biological Opinion for the Existing Utah BLM Resource Management Plans
(RMP). West Valley City, Utah: United States Department of Interior, Fish and Wildlife
Service, Ecological Services, Utah Field Office, 255.
134
May 2019
USFWS. 2008. Birds of Conservation Concern 2008. Arlington, Virginia: United States
Department of Interior, Fish and Wildlife Service, Division of Migratory Bird
Management, 85. http://www.fws.gov/migratorybirds/.
USFWS. 2004. "Environmental assessment for designation of critical habitat for the Mexican
spotted owl. Region 2."
—. 2012. Final Recovery Plan for the Mexican Spotted Owl (Strix occidentalis lucida), First
Revision. U.S. Fish and Wildlife Service: Albuquerque, New Mexico, USA.
—. 2008. "Mexican Spotted Owl (Strix occidentalis lucida)."
https://www.fws.gov/southwest/es/arizona/Documents/Redbook/Mexican%20Spotted%2
0Owl.pdf.
USGCRP. 2017. Climate Science Special Report: Fourth National Climate Assessment. Edited
by D J Wuebbles, D W Fahey, K A Hibbard, D J Dokken, B C Stewart and T K
Maycock. Vol. 1. Washington, DC: U.S. Global Change Research Program.
doi:10.7930/J0J964J6.
USGS. 2018. "Federal Lands Greenhouse Gas Emissions and Sequestration in the United States:
Estimates for 2005–14." 11 23. https://pubs.er.usgs.gov/publication/sir20185131.
Utah. 2016. "Utah Division of Air Quality Home Page." Governor's Recommendation to EPA
Regarding Ozone Nonattainment Areas. Accessed March 23, 2018.
https://documents.deq.utah.gov/air-quality/planning/air-quality-policy/DAQ-2017-
002764.pdf.
WRI. 2018. "Understanding the IPCC Reports, The Carbon Budget." World Resources Institute.
Accessed August 16, 2018. http://wriorg.s3.amazonaws.com/s3fs-public/WRI13-
IPCCinfographic-FINAL_web.png.
135
May 2019
Appendix F – Acronyms/Abbreviations
AO Authorized Officer NESHAP National Emission Standards For
Hazardous Air Pollutants
APD Application for Permit to Drill NHPA National Historic Preservation Act
ARMPA Approved Resource Management NRHP National Register of Historic Places
Plan Amendments
BCR Bird Conservation Region NSO No Surface Occupancy
BLM Bureau of Land Management O.O. Onshore Oil and Gas Order
BMP Best Management Practice PLPCO Public Lands Policy Coordinating Office
CAA Clean Air Act PARFDS GRSG Population Area Reasonably
Foreseeable Development Scenario
CFR Code of Federal Regulations RFDS Reasonably Foreseeable Development
Scenario
CIAA Cumulative Impact Analysis Area RMP Resource Management Plan
COA Condition of Approval ROD Record of Decision
CWCS Comprehensive Wildlife ROW Right of Way
Conservation Strategy
DR Decision Record S Stipulation
EA Environmental Assessment SHPO State Historic Preservation Office
EAR Environmental Analysis Record SITLA State Institutional Trust Lands
Administration
EIS Environmental Impact Statement
EOI Expression of Interest UDAQ Utah Division of Air Quality
EPA Environmental Protection Agency UDWR Utah Division of Wildlife Resources
ESA Endangered Species Act USFS United States Forest Service
FFO Fillmore Field Office USFWS United States Fish & Wildlife Service
FLPMA Federal Land Policy and UT Utah
Management Act
FONSI Finding of No Significant Impact UTSO Utah State Office
GIS Geographical information System
GWP Global Warming Potential WO Washington Office
H Handbook
IDPRT Interdisciplinary Parcel Review
Team
IM Instruction Memorandum
LN Lease Notice
MBTA Migratory Bird Treaty Act
Mcf One Million Cubic Feet
MLA Mineral Leasing Act
MOU Memorandum of Understanding
136
May 2019
137
May 2019
138
May 2019
the surface as the hole deepens; circulating drilling fluids to cool the drill bit and remove the drill
cuttings; pulling the drill pipe from the hole to replace worn drill bits; and setting strings of casing and
cementing them in place. Air and/or water-based drilling fluid may be used to drill the hole. Prior to
setting the production casing, open-hole well logs may be run to identify potentially productive horizons.
If the evaluation concludes that sufficient natural gas and/or oil are present and recoverable, steel
production casing would be installed and cemented in place. Drilling activities on a well would typically
occur 24 hours per day, seven days per week, and would require approximately 20 workers. Depending
on the depth and complexity of the well, drilling could last from a few days to one week.
Once a well has been drilled and evaluated to have sufficient oil and/or natural gas, completion operations
would begin. Well completion involves perforating the production casing in target zones, followed by
hydraulic fracturing (also known as, fracking) of the formation (see below for more information on
hydraulic fracturing). The next phase of completion would be to flow and test the well to determine rates
of production.
Typical equipment and vehicles used during completion activities might include carbon dioxide tanker
trucks; sand transport trucks; water trucks; oil service trucks used to transport pumps and equipment for
fracking; flat beds and gin trucks to move water tanks, rigs, tubing, and fracking chemicals; logging
trucks (cased hole wireline trucks); pickup trucks to haul personnel and miscellaneous small materials;
and workover rigs.
Completion activities on individual wells may occur 24 hours per day, seven days per week, and would
require approximately 20 to 40 workers. Completion of an individual well could take from 7 to 30 days,
depending on the number of completion zones.
Hydraulic Fracturing
Hydraulic fracturing (also known as fracking) is a well stimulation technique used to increase oil and gas
production from underground rock formations. Fracking would also be evaluated at the APD stage should
the lease parcel be sold/issued and a development proposal submitted. The following paragraphs provide
a general discussion of the fracking process that could potentially be implemented if development were to
occur, including well construction information and general conditions encountered.
Fracking involves the injection of fluids through a wellbore under pressures great enough to fracture the
oil and gas producing formations. The fluid is generally comprised of a liquid such as oil, carbon-dioxide
or nitrogen, and proppant (commonly sand or ceramic beads), and a minor percentage of chemicals to
give the fluid desirable flow characteristics, corrosion inhibition, etc. The proppant holds open the newly
created fractures after the injection pressure is released. Oil and gas flow through the fractures and up the
production well to the surface.
Fracking has been used by oil and natural gas producers since the late 1940s and for the first 50 years was
mostly used in vertical wells in conventional formations. Fracking is still used in these settings, but the
process has evolved. Technological developments (including horizontal drilling) have led to the use of
fracking in unconventional hydrocarbon formations that could not otherwise be profitably produced.
The use of horizontal drilling through unconventional reservoirs combined with high-volume water based
multi-stage fracking activities has led to an increase in oil and gas activity in several areas of the country
which has, in turn, resulted in a dramatic increase in domestic oil and gas production nationally. However,
along with the production increase, fracking activities are suspected of causing contamination of fresh
water by creating fluid communication between oil and gas reservoirs and aquifers. The Environmental
Protection Agency (EPA) recently conducted an assessment of fracking on drinking water resources
(https://www.epa.gov/hfstudy) [EPA 2016]. Presently, there are no unconventional reservoirs that are
being exploited using high-volume water based hydraulic fracturing techniques.
139
May 2019
140
May 2019
Therefore, at this time it appears that induced seismicity from water injection is not a problem in the oil
fields of Utah (BLM 2018).
5.1.4 Maintenance Operations
Traffic volumes during production would be dependent upon whether the wells produced natural gas
and/or oil, and for the latter, the volume of oil produced. Well maintenance operations may include
periodic use of work-over rigs and heavy trucks for hauling equipment to the producing well, and would
include inspections of the well by a pumper on a regular basis or by remote sensing. The road and the
well pad would be maintained for reasonable access and working conditions. Portions of the well pad not
needed for production of the proposed well, including the reserve pit, would be re-contoured and
reclaimed, as an interim reclamation of the site.
5.1.5 Plugging and Abandonment
If the wells do not produce economic quantities of oil or gas, or when it is no longer commercially
productive, the well would be plugged and abandoned. The wells would be plugged and abandoned
following procedures approved by a BLM Petroleum Engineer, which would include requiring cement
plugs at strategic positions in the well bore. All fluids in the reserve pit would be allowed to dry prior to
reclamation work. After fluids have evaporated from the reserve pit, sub-soil would be backfilled and
compacted within 90 days. If the fluids within the reserve pit have not evaporated within 90 days (weather
permitting or within one evaporation cycle, i.e. one summer), the fluid would be pumped from the pit and
disposed of in accordance with applicable regulations. The well pad would be re-contoured, and topsoil
would be replaced, scarified, and seeded within 180 days of the plugging the well.
141
May 2019
142