COURT 2 PROGRESS (INSIDE BUILDING)

H.V.A.C

Item Types Ground Floor First Floor ROOF Top Roof Remarks

Fan coil units installation (Indoor


1 95% 100% 0% Not applicable
units)
No Material to start
2 Duct works for Indoor units 0% 0% Not applicable Not applicable work on site

3 Thermal insulation 0% 0% 0% Not applicable Not started

Copper pipes and connection


4 1% 0% 0% Not applicable In process
between them
Installation of condensate piping
5 0% 0% 0% Not applicable Not started
for indoor units
No Material to start
6 Installation of Airoutlets 0% 0% Not applicable Not applicable work on site
Installation of Compressors
7 Not applicable Not applicable 0% Not applicable Not started
(Outdoor units)
Installation of Toilet exhaust No Material to start
8 0% 0% 0% Not applicable
ducts work on site
No Material to start
9 Installation of Exhaust fans 0% 0% 0% 0% work on site
Installation of Fresh Air Handling
10 Not applicable Not applicable 0% Not applicable
unit FAHU not approved
yet
11 Duct works for Fresh air supply 0% 0% 0% Not applicable
FIRE FIGHTING

Item Types Ground Floor First Floor ROOF Top Roof Remarks

1 MAIN LINE 0% 0% Not applicable Not applicable

2 CROSS LINE 0% 0% Not applicable Not applicable In progress

3 BRANCHES 5% 5% Not applicable Not applicable In progress

Material not
4 Z.C.V 0% 0% Not applicable Not applicable delivered to site

5 SPRINKLERS 0% 0% Not applicable Not applicable Not approved

6 DRY LINE 0% 0% Not applicable Not applicable Not started

Material not
7 FIRE EXTINGUSHER 0% 0% 0% Not applicable delivered to site
Material not
8 CO2 SYSTEM 0% 0% 0% Not applicable delivered to site
Material not
9 FM 200 SYSTEM 0% 0% 0% Not applicable delivered to site
PLUMBING
Item Types Ground Floor First Floor ROOF Top Roof Remarks

1 FIRST FIX OF DRAINAGE 90% 90% 0% 0% Work in progress

2 FIRST FIX OF WATER SUPPLY 90% 90% 0% 0% Work in progress

Material not
3 SANITRY FIXTURE 0% 0% Not applicable Not applicable delivered to site

4 POLY ETHELYNE TANK Not applicable Not applicable Not applicable 0% Not approved

Material not
5 FLOOR DRAIN 0% 0% Not applicable delivered to site