Академический Документы
Профессиональный Документы
Культура Документы
FOR
HIA-J029-APC-ME-SPEC-0114
HIA-J029-APC-ME-SPEC-0012 Page 1 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 2 of 49
2
HIA-J029-APC-ME-SPEC-0012 Page 3 of 49
Fabrication and Installation of Carbon Steel Pipework
2. DESIGN
2.1. WELDING END AND BRANCH ATTACHMENT JOINT DESIGN
2.1.1 Each piping branch reinforcement pad or segment therefore shall be provided with one
hole (at the side and not at the crotch) drilled and tapped 1/4 NPT.
2.2. PROXIMITY OF WELDS
2.2.1 The minimum distance between toes of adjacent welds shall be the lesser of 40mm or
twice the wall thickness of the thickest pipe/fitting.
2.2.2 Dimensions less than those specified above are not permitted except where Company
agreement has been obtained and the following additional requirements met:
(a) Dependent on material, thickness and configuration, the Company may require
an intermediate stress relief to be carried out.
(b) Care shall be taken to minimise stress concentrations. Weld profiles shall be as
smooth as possible; at the discretion of the Inspector welds may be dressed.
(c) When branch welds cross or are located closer than the allowable to main
seams, such seams shall be radiographed or U/S tested for a distance on either
side of the hole of not less than the opening diameter.
(d) When attachments are located closer than the allowable to main seams they
shall cross the seam completely. The seam shall be radiographed to the extent
which will be covered by the attachment, plus on either side of the attachment, a
distance of twice the pipe wall thickness.
2.3. THERMAL RELIEF PROVISION
2.3.1 All protection sections of pipelines where locked in legs of product can exist shall be
protected with thermal relief. Thermal Relief assemblies should straddle the isolation
point closest to storage. it is likely that on one pipeline a series of thermal relief
assemblies will be required. It is essential that the set pressure on the relief valves are
properly selected to ensure the cascade effect valves limits the maximum line pressure
to below the design rating of the pipeline and/or any underated piece of equipment that
may be present on the particular system. Thermal relief assemblies cascade back
towards storage. Each thermal relief assembly shall consist of flanged thermal relief
valve. The contractor shall ensure all pipelines are adequately protected against
thermal expansion of product throughout the phase of the work.
HIA-J029-APC-ME-SPEC-0012 Page 4 of 49
3
HIA-J029-APC-ME-SPEC-0012 Page 5 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 6 of 49
4
HIA-J029-APC-ME-SPEC-0012 Page 7 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 8 of 49
5
HIA-J029-APC-ME-SPEC-0012 Page 9 of 49
Fabrication and Installation of Carbon Steel Pipework
5. FLANGED JOINTS
5.1. GENERAL
5.1.5 Prior to welding on a slip-on flange the bore of the flange and the pipe end for a distance
equal to the flange thickness plus 25mm minimum shall be cleared free from any
protective coating, oil, grease, loose scale or rust. The difference between the diameter
of the flange bore and the outside of the pipe shall not exceed 5mm. Care shall be
taken when applying the inside fillet weld to avoid damaging the facing. The flange shall
be positioned such that the distance from the face to the pipe end is equal to the pipe
wall thickness plus 3mm.
5.1.2 Flange bolt holes shall straddle the vertical or NS centre line as applicable, except
where otherwise specified on the piping drawings, and shall match the orientation of the
mating flanges.
5.1.3 Loose flanges shall be bolted to an adjacent flanged piece for shipment or supplied in
hessian or canvas sacks securely attached to that part of the fabrication.
5.1.4 Flange facing shall be in accordance with the applicable Piping Class document. Should
warping take place during the fabrication the joint contact surfaces may be restored by
machining to their original accuracy provided the flange thickness dimensions are not
reduced below the minimum required by the relevant ANSI flange specification.
5.1.5 Pipe ends connected to threaded flanges shall not project through to form part of the
gasket surface.
6. WELDING
6.1. GENERAL
6.1.1 The Fabricator shall provide adequate and systematic supervision by competent
personnel to ensure that the required quality levels are maintained. At the discretion of
the Inspector, any welder who consistently fails to meet the standard shall be required to
undergo re-training, re-testing or shall be removed from the job completely.
6.1.2 All welding shall be carried out in accordance with qualified and approved weld
procedures by welders who have been qualified to the relevant testing code.
6.1.3 The Fabricator shall make maximum effort to ensure that arc strikes outside the welding
groove are avoided. When these occur outside of the finished weld the arc strike shall
be carefully removed by grinding, followed by a magnetic particle or dye penetrant
inspection of the ground area to confirm it is defect free. Care shall be taken to ensure
the ground area blends in smoothly with the surrounding material such that no sharp
notch results and the thickness is not reduced below the required minimum wall
thickness shall be carried out in accordance with an approved repair procedure. The
acceptance of arc strikes outside of the welding groove shall be at the sole discretion of
the Inspector who shall be requested to inspect the damage and approve the repair
procedure or reject the damage material as appropriate.
6.1.4 Weld stops and starts shall be staggered by 50mm minimum such that adjacent passes
or layers do not coincide. Weld stops and starts shall be ground or chipped prior to
laying subsequent passes.
6.1.5 The number of weld shall be minimised. Pipe lengths smaller than 1m shall not
normally be welded together.
6.1.6 Internals of inline valves and equipment which may be damaged due to heat transfer
from the welding process shall be removed prior to welding wherever possible.
HIA-J029-APC-ME-SPEC-0012 Page 10 of 49
6
HIA-J029-APC-ME-SPEC-0012 Page 11 of 49
Fabrication and Installation of Carbon Steel Pipework
6.5.1 Care shall be taken during the assemble of socket weld joints to ensure there is a
1.5mm gap between the pipe end and root face of the fitting.
6.5.2 Welds shall be fillet welds deposited by the MMA or TIG process, with a minimum of two
runs. The weld surface shall be free from marked irregularities.
HIA-J029-APC-ME-SPEC-0012 Page 12 of 49
7
HIA-J029-APC-ME-SPEC-0012 Page 13 of 49
Fabrication and Installation of Carbon Steel Pipework
6.6.1 Where attachments are to be made thin walled piping i.e. less than 5mm thick, care
shall be taken to avoid excessive oxidation or burn through. An inert gas purge shall be
applied to the bore necessary. Where access to the bore surface for cleaning and
inspection is not possible the inert gas purge is mandatory.
6.6.2 In order to demonstrate the suitability of the weld procedure the Company may require a
test weld to be made on pipe of the minimum contract thickness. Similarly the Company
may require Welders to be tested on their ability to weld attachments to the thin wall
pipes even if their qualification range apparently covers the thin wall situation.
6.7. ALIGNMENT
6.7.1 The ends of piping components to be butt welded shall be accurately aligned in
accordance with the requirements on ANSI B31.3. The maximum internal misalignment
shall be 1.5mm except that where the pipe wall thickness is less than 6mm the internal
misalignment shall not exceed 25% of the wall thickness.
6.7.2 Where mis-match of the bores results in misalignment greater than that permitted
above, this shall preferably be corrected by taper or counterboring in accordance with
ANSI B31.3. Permitted alternatives to machining are:
(a) Roller expanding for pipes up to 4 nb.
(b) Cold drifting with a slow taper drift provided the diameter is not increased more
than 3%.
6.7.3 Care shall be taken to ensure that the wall thickness after machining, expanding or
drifting is not reduced below 87.5% of the nominal thickness.
6.8. FIT-UP & TEMPORARY ATTACHMENTS
6.8.1 Parts to be welded shall be carefully aligned and held securely in position by clamps,
tack welds in the welding groove, bridge pieces or wedges.
6.8.2 All welding of fit-up tacks and temporary attachments shall be performed by qualified
welders using qualified procedures and the preheat level specified by the procedure.
6.8.3 Where tack welds are to be incorporated into the main welds they shall be of a length
such that they become part of the proposed root pass and their ends shall be ground.
Defective tack welds, and those which are not to be incorporated into the root pass, shall
be completely removed by grinding, following completion of welding.
6.8.4 Temporary attachments shall be of the same nominal composition as the parent
material. They shall be removed by cutting 3mm above the surface followed by grinding
flush. The area shall then be surface crack detected to confirm the absence of defects.
6.9. PROTECTION FROM WEATHER
6.9.1 The welder and welding area shall always be adequately protected from the weather so
that the weld integrity is not detrimentally affected by wind, rain or snow or from the
decline of the welder s ability when working at low temperatures or other adverse
conditions. The continuation of welding indoor weather conditions shall be at the
discretion of the inspector.
6.9.2 Weld areas shall be kept dry throughout the complete welding cycle until after the weld
has cooled. Metal surfaces which are damp or below 5 degrees the commencement for
a minimum of 100mm on either side of the weld, taking care to avoid hot spots.
6.9.3 Where gas shielded welding is employed, special care shall be taken to protect the
welding area from draughts.
HIA-J029-APC-ME-SPEC-0012 Page 14 of 49
8
HIA-J029-APC-ME-SPEC-0012 Page 15 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 16 of 49
9
HIA-J029-APC-ME-SPEC-0012 Page 17 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 18 of 49
1
0
HIA-J029-APC-ME-SPEC-0012 Page 19 of 49
Fabrication and Installation of Carbon Steel Pipework
9. FABRICATION TOLERANCES
9.1 Fabrication tolerances shall be in accordance with the specified codes and standards,
supplemented by the requirements given below.
9.2 Flattening of a bend, as measured by the difference between the maximum and
minimum outside diameter at any cross section shall not exceed 8% of the original
outside diameter of the pipe for internal pressure and 3% for external.
9.3 Flange alignment tolerances shall be as stated in Appendix A figure 1.
9.4 The tolerances on linear dimensions involved in the relative positions of branches,
bosses, flanged ends, flow instrument tappings and changes of direction shall be as
stated in Appendix A figure 2. Also given in this figure are tolerances on pipe bending
and across the land of prepared welding ends.
10. INSPECTION AND TESTING
10.1. GENERAL
10.1.1 The Inspector shall have free access to all parts of the Fabricator s Works engaged in
the manufacture of pipework and shall have the right to inspect any aspect of the work
during fabrication, installation, testing or an completion. The Fabricator shall afford the
Inspector all reasonable facilities to allow these inspection functions to be fulfilled. All
tests and inspections shall be conducted at the place of fabrication unless otherwise
stated.
10.1.2 The Fabricator is required to have an identification system such that each component
part can be identified against the Mill Test Certificates and that all weld seems can be
identified with the welder or welding operator and welding procedure specification.
10.2. INSPECTION CLASSES
10.2.1 Piping Systems are classified on the basis of service and material.
10.2.2 The extent of inspection to be carried out for each inspection class is shown in table
10.2.3.1.
10.2.3 Inspection Class stated in table 10.2.3.1 should be in accordance with the following
HIA-J029-APC-ME-SPEC-0012 Page 20 of 49
11
HIA-J029-APC-ME-SPEC-0012 Page 21 of 49
Fabrication and Installation of Carbon Steel Pipework
11 PRESSURE TESTING
11.1 All flanged piping assemblies shall be hydrostatically tested in the Fabricator s works
prior to shipment. The test medium shall be potable water, unless otherwise specified.
The water temperature shall be maintained above 7 degrees celsius or the ductile/brittle
transition temperature, whichever is the higher, throughout the test.
11.2 Other piping assemblies, such as those with Welding ends, do not require to be
hydrostatically tested at the Fabricator s works. In this case however the Fabricator
remains responsible for any defects causing leakage or failure in his fabrication found
during the site test of the erected pipework.
11.3 Erected pipework shall be pressure tested in accordance with ANSI B31.3 Chemical
Plant and Petroleum Refinery Piping.
11.4 All pressure tests shall be carried out in the pressure of the Inspector and shall be to his
satisfaction. The test pressure shall be maintained for a sufficient time to enable a
HIA-J029-APC-ME-SPEC-0012 Page 22 of 49
thorough examination to be
made for leakage and
defects, with a minimum of 2
hours.
1
2
HIA-J029-APC-ME-SPEC-0012 Page 23 of 49
Fabrication and Installation of Carbon Steel Pipework
11.5 Prior to pressure testing being carried out the inside of the pipework shall be clean and
free from loose millscale and foreign matter.
12. QUALITY CONTROL
12.1 GENERAL
12.1.1 The Fabricator shall afford the Company and/or the Certifying Authority adequate
opportunity and facility to verify that the design, material, construction and performance
of the equipment is in accordance with Company requirements.
12.1.2 Any verification of quality carried out by the Company and/or the Certifying Authority
shall not relieve the Fabricator of his obligations under the contract nor shall it preclude
any subsequent rejection of items.
HIA-J029-APC-ME-SPEC-0012 Page 24 of 49
1
3
HIA-J029-APC-ME-SPEC-0012 Page 25 of 49
Fabrication and Installation of Carbon Steel Pipework
14. INSTALLATION
14.1 GENERAL
14.1.1 All pipework shall be inspected prior to erection to ensure it is free from dirt, scale, weld
spatter and other foreign matter.
14.1.2 Except where cold springing is specified on the piping drawings, all piping shall be
installed in place without springing or forcing.
14.1.3 Field run piping is restricted to line sizes below 50 ns. It shall be run generally in
accordance with the routing indicated on the piping drawings, in a neat and orderly
manner consistent with good operation, safety of personnel and economy of material,
with adequate provisions for expansion and flexibility.
14.2 FLANGED JOINTS
14.2.1 Flanged faces shall be cleaned of all dirt, grease and protective coating and shall be
inspected for defects such as scratches or dents prior to installation.
14.2.2 Flanges shall be properly aligned prior to the insertation of gaskets and bolts to avoid
stresses or uneven gasket loads. See Appendix A figure 1 for flange alignment
tolerance.
14.2.3 Where specified by the Company, bolts shall be tightened by means of suitable torque
wrenches or tensioning devices to ensure the correct bolt stress is obtained and the
gasket is properly compressed in accordance with the design principals applicable to the
gasket type.
14.2.4 All bolts shall extend completely though their nuts. The use of washers or spacers to
take up excess bolt length shall not be permitted.
14.2.5 Stud bolts cut from length of studding shall have the material grade stamped on the cut
ends.
14.2.6 Steel to cast iron flanged joints shall be assembled with care to prevent damage to the
cast iron flange.
14.2.7 Joint Rings shall be non-asbestos 1.6m thick in accordance with the general
specification.
14.3 EQUIPMENT FLANGE CONNECTIONS
14.3.1 Flange covers shall not be removed from equipment flange connections until ready to
connect the mating piping.
14.3.2 Connections to strain sensitive equipment shall not be made until the mating piping has
been fully erected complete with permanent supports. Prior to bolting up to the
equipment flange the connection shall be checked for correct alignment.
14.4 SCREWED PIPEWORK
14.4.1 Pipe ends cut shall be cut square, threaded, reamed and cleaned to remove cuttings
from internal and external surfaces. All threading shall be carried out after bending,
forging or heat treatment but where this is not possible suitable thread protection must
be provided. All screwed connections shall have taper threads in accordance with API
unless otherwise stated.
14.4.2 All joints shall be tightened using a suitable wrench; connection 50 ns and larger shall be
tightened using a RIGID compound leverage pipe wrench or equivalent. Excessive
wrench markings on pipe and fittings shall be cause for rejection of the fabrication at the
discretion of the Inspector.
14.4.3 The joints shall be assembled using a suitable Petroleum resistant pipe jointing
compound which shall be applied to the male thread only, taking care to ensure the
compound does not reach the inside of the pipe. PTFE tape shall not be used.
HIA-J029-APC-ME-SPEC-0012 Page 26 of 49
1
4
HIA-J029-APC-ME-SPEC-0012 Page 27 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 28 of 49
1
5
HIA-J029-APC-ME-SPEC-0012 Page 29 of 49
Fabrication and Installation of Carbon Steel Pipework
15.3 BENDING
All bends shall be true to radius and the bore of the pipe at any point after bending shall
not vary be more than plus or minus 1/8 from the bore of the pipe before bending.
Lobster back or gusseted bends will not be accepted. The bend centreline radius shall
be 5 times the normal pipe diameter unless stated otherwise.
15.4 BOLTING
The contractor shall include in his supply for all studbolts, bolts, nuts etc. All bolts shall
be the correct length to ensure that all thread on nuts are engaged and that the end of
the bolt does not project more than 3mm from the upper face of the nut when tightened.
15.5 TESTING
Test pressures shall be held steady at the required pressure for a period of four hours,
without further use of the test pressurising pump.
Testing shall not be carried out when there is any likelihood of the water freezing in the
pipework, the Contractor shall be responsible for repairing and re-testing the damaged
pipework and fittings.
For all tests, vents shall be located at the high points in the system, or of the section to
be tested, in order to ensure compete displacement of air from the system.
All equipment likely to sustain damage during the test is to be removed from the
pipeline, control valves are to be left in the open position.
Records are to be kept of each test. The information to be recorded is to be as follows:
i) Pipeline or system tested
ii) Testing Medium
iii) Test Pressure
iv) Temperature of Testing Medium
v) Date of Test
vi) Signature of the Company s Engineer
vii) Signature of Agent or Contractors Supervisor
HIA-J029-APC-ME-SPEC-0012 Page 30 of 49
16
HIA-J029-APC-ME-SPEC-0012 Page 31 of 49
Fabrication and Installation of Carbon Steel Pipework
16.3 General
Field run piping shall be run generally in accordance with the routing indicated on the
piping drawings, in neat and orderly manner consistent with good operation safety of
personnel and economy of material.
16.4 Connections
All joints except where butt welded to change from tube, in nominal pipe size shall be
gauge cable double ferrule compression tube fittings in 316 stainless steel Swagelok or
approved equivalent, complete with gap inspection gauge. A thread sealant shall be
applied when assembling threaded fittings, Liquid PTFE or approved equivalent.
Flanges shall be drilled to ANSI class 150 to match existing. Flange bolts shall straddle
the vertical or NS centreline as applicable.
Joint rings shall be non asbestos 1.6mm thick in accordance with the General
Specification.
16.5 Supports
Pipework shall be adequately supported in trays. Pipework shall be fixed to horizontal
trays with Stauff polypropelene clamps or equivalent. Pipework shall be adequately
supported and securely fixed immediately before and after a bend or offset and at 0.5m
maximum pitch.
All carbon steel supports shall be isolated from pipe to prevent electrolytic corrosion.
16.6 Identification
Each pipe shall be clearly identified, labels shall be fitted during erection or pipework.
HIA-J029-APC-ME-SPEC-0012 Page 32 of 49
1
7
HIA-J029-APC-ME-SPEC-0012 Page 33 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 35 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 36 of 49
19
HIA-J029-APC-ME-SPEC-0012 Page 37 of 49
Fabrication and Installation of Carbon Steel Pipework
17 BLANK
HIA-J029-APC-ME-SPEC-0012 Page 38 of 49
20
HIA-J029-APC-ME-SPEC-0012 Page 39 of 49
Fabrication and Installation of Carbon Steel Pipework
18 MATERIAL SPECIFICATION
Maximum Pressure 19.2 Bar for class 150 systems
Maximum Temperature 50C
Piping Design Code ASME B31.3
Line Pipe Seamless A.P.I. 5L Gr B (Carbon Content 0.23% Max)
Size Range (NPS) Description
15 40 Schedule 80 P.E.
50 150 Schedule 40 B.E.
200 350 Schedule 40 B.E.
Flanges Forged MATL ASTM A105 N (Carbon Content 0.23% Max)
DIMN ANSI B 16.55 CLASS 150
Finish
MSS SP 44
Incl
Welding Neck
Note: To Match Pipe Wall Thickness
Slip-on
Blind
L
Butt Weld Fittings
DIMN ANSI B16.9
Incl
Eccentric Weld Reducer
Concentric Weld Reducer
Equal Tee
90% Long Radius Weld Elbow
45% Long Radius Weld Elbow
NOTE All To Match Pipe Wall Thickness
Reinforced Branch Fittings MATL ASTM A105 N (Carbon Content 0.25% Max)
Spec Bonney Forge Or Equal
Incl
Weldolet
Sockolet
Elbolet
Thredolet
Latrolet
5
6
HIA-J029-APC-ME-SPEC-0012 Page 40 of 49
Minimum pipe size 15nps
All forgings shall be
normalised & tempered
Carbon content shall be
limited to 0.23% max for
pipe & 0.25% max for
other items (carbon
equivalent shall be
limited to 0.45% max)
Where flanges mate with
cast iron equipment the
mating flange face shall
be a smooth
finish
All unconnected
branches 40 nps and
below shall be class
6000 1b / schedule 160
For selection of
reinforced branch
connections see detail
drgs
Buried lines shall be
coated & wrapped in
accordance with
specification. All aviation
product pipes lines shall MAT ASTM A234 WPB (Carbon Content 0.23% Max)
be internally lined in
accordance with the
specification 3326-0025.
Material test certificates
to din 50049.3.1b
2
1
HIA-J029-APC-ME-SPEC-0012 Page 41 of 49
Fabrication and Installation of Carbon Steel Pipework
Header Size
15 RB RB RB RB RB RB RB RB RB RB RB RB T
B
20 RB RB RB RB RB RB RB RB RB RB RB T
R
25 RB RB RB RB RB RB RB RB RB RB T
A
40 RB RB RB RB RB RB RB RB W T
N
50 B B B B B B B W T
C
65 B B B B B B W T
H
80 B B B B B W T
S 100 B B B B W T
I 150 B B B W T
LEGEND
Z 200 B B W T
RB RE-INFORCED BRANCH
E 250 B W T B UN RE-INFORCED BRANCH
W - WELDOLET
300 W T T BUTT WELD EQUAL TEE
350 T
HIA-J029-APC-ME-SPEC-0012 Page 42 of 49
22
HIA-J029-APC-ME-SPEC-0012 Page 43 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 44 of 49
F
I
L
E
R
E
F
:
0
0
2
0
0
0
1
2
F
HIA-J029-APC-ME-SPEC-0012 Page 45 of 49
Fabrication and Installation of Carbon Steel Pipework
A1.7 The term make screwed joint shall mean the unit of measurement per end of pipe or
fitting for making a screwed joint, including all fitting work and preparing ends with
specified jointing material.
A1.8 The term make 90 degrees branch shall mean to include for the cutting of holes in the
main pipe, shaping of branch ends, fitting, bevelling tacking and the finished welding of
the branch.
No distinction has been made in the description between main pipes of differing
diameter. Only the branch diameter has been stated. The Contractor should make any
allowance necessary in his prices for this lack of distinction.
A1.9 The term make weld joint shall mean the unit of measurement per end of pipe or fitting
for making a socket weld joint. To include all cutting of pipe end, preparing pipe end, all
fitting work and finished welding of the joint.
HIA-J029-APC-ME-SPEC-0012 Page 46 of 49
F
I
L
E
Pipe Diameter Number of Bolts Dia Stud Length Bolt Length
R
E (mm) (mm)
F
15mm 4 : 1/2 55 44
0
0
20mm 4 2 1/2 55 51
0
25mm 4 0 1/2 65 51
0
40mm 4 1 1/2 70 57
2
F
50mm 4 5/8 75 70
80mm 4 5/8 90 76
100mm 8 5/8 90 76
150mm 8 3/4 95 83
200mm 8 3/4 100 89
250mm 12 7/8 115 85
300mm 12 7/8 115 102
350mm 12 1 125 108
400mm 16 1 130 114
450mm 16 1 1/8 150 121
HIA-J029-APC-ME-SPEC-0012 Page 47 of 49
Fabrication and Installation of Carbon Steel Pipework
HIA-J029-APC-ME-SPEC-0012 Page 48 of 49
FILE REF:00200012F
HIA-J029-APC-ME-SPEC-0012 Page 49 of 49