Data provided:

Type of vessel Bulk carrier


Location Bhavnagar
Tidal Data:
HLWS HLWN MLWS MLWN Depth of water
meter meter meter meter meter
11 9 3.5 1.5 17
Site condition Sheltered
Berarthing condition Favourable
Mean velocity of current 1 m/s
Wave height 1 meter
wave time period 6 seconds
soil condition Loose
DWT 15000 tons
No. of vessels 1
No of sides Single side

Vessel Data:
Length Width Depth Draught Possible for vessel?
meter meter meter meter
163 20.7 12 9 YES

Surge Allowance Clearence Free height


meter meter meter
1.5 0.5 2

Jetty dimensions:
Length Width Width Depth Pile
Length required provided required provided Depth Provided diameter
meter meter meter meter meter meter meter
187.45 200.15 20.5 32.5 33.75 1.5

Loadings:
Dead Load Selfweight
Object C/s area Length No.s Density Load
sq. meter meter KN/m3 KN
Primary beam 0.75 20.5 9 25 3.459375

Secondary beam 0.4325 45.5 10 25 7.194688


Deck slab 4.1 50 1 25 7.625
Wearing Coat 1.5375 50 1 22 3.89125
Pile Muf 1.25 2.5 36 25 2.9375
Full length pile 1.767144 31.048 27 25 38.58715

Pile under fender block 1.767144 18.667 9 25 8.355489


Fender Block 6.25 12.381 9 25 18.02983
Total 90.08028

Live Load 50 KN/m2

Wind Load
Vb K1 K2 K3 Vz Pz
m/s m/s KN/m2
50 1 1.05 1 52.5 1.65375
Surface ar Load to be applied
For piles 2.356194 3.896557 KN/m
For fender piles 2.5 4.134375 KN/m
For deck 1.275 2.108531 KN/m

Earthquake Load:

Direction Z I R T Sa/g Ah
second
X 0.16 1.5 3 0.6363961031 2.5 0.100
Z 0.16 1.5 3 0.4074923312 2.5 0.1

Bearthing Force

Velocity of Approching vessel g Cm ᶿ Y R b


m/s m/s2
0.1 9.81 1.869565 20 40.75 42.04385 0.248728

Mooring Force

Dm
(height of F ( due to
P Cw vessel) Dl Ld Aw wind)
kg/m2 meter meter meter sq. meter kg
168.5779816514 1.3 12 9 163 574.575 125918.9

Current Force

Height of
applicatio
n for High
W V g P High Tide Low Tide tide
tons/m3 m/s m/s2 tons/m2 tons tons m
1.03 1 9.81 0.0524974516 1.1024464832 0.728402 9.333333
Wave Force
High Tide (From SPM chart)
Due to drag
Cd r H g D d/gT2 Hb/gT2
0.53 1.03 1 9.81 1.5 0.079284 0.029
Low Tide
Due to drag
Cd r H g D d/gT2 Hb/gT2
0.53 1.03 1 9.81 1.5 0.052384 0.025
Load on
Load on non
Non Fender Block fender fender
W Vb Fender block W W Total W block pile block pile
KN KN KN KN KN KN KN
115.0803 11.50803 26.3853201608 38.5871515246 64.97247 0.519268 0.253134
115.0803 11.50803 26.3853201608 38.5871515246 64.97247 0.519268 0.759402

l/r Ce Cs E Impact facFinal forceAlong lengAway from length


tons tons tons tons
0.826679 0.641479 0.95 8.710419399 1.4 12.19459 11.45916 4.170794

F (due to
current No. of
forces) Total F Force per mooring line No. of lines bollards
kg tons tons
0.515 125.9194 45 2.7982092655 3

Height of
applicatio
n for Low
tide
m
6.166667
(From SPM chart)
e to drag
Hb H/Hb Kdm Sdm Fdm Mdm Cm r
10.24164 0.097641 0.144 1 0.57837 16.19436 2 1.03

e to drag
Hb H/Hb Kdm Sdm Fdm Mdm Cm r
8.829 0.113263 0.167 1 0.670749 12.40885 2 1.03
Away from length
Due to inertia
H g D d/gT2 Hb/gT2 Hb H/Hb Kim Sim Fim
1 9.81 1.5 0.079284 0.029 10.24164 0.097641 0.48 0.66 7.275096

Due to inertia
H g D d/gT2 Hb/gT2 Hb H/Hb Kim Sim Fim
1 9.81 1.5 0.052384 0.025 8.829 0.113263 0.48 0.62 7.275096
F M
Mim
88.82892 7.853466 105.0233

Mim
83.44535 7.945845 95.8542