TBM VERONICA DISASSEMBLING TBM VERONICA DISASEMBLING PROGRAMME 07-May-19 17:54

Activity ID Activity Name Original Start Finish 1 2


Duration May 12 May 19 May 26 Jun 02 Jun 09 Jun 16 Jun 23
Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun
Total 32 16-May-19 16-Jun-19 16-Jun-19, Total

Lifting Operation Using 80-ton Crane (Initial) 8 16-May-19 23-May-19 23-May-19, Lifting Operation Using 80-ton Crane (Initial)
Outer Telescopic Shield 3 16-May-19 18-May-19 18-May-19, Outer Telescopic Shield
01 Gouging of the weldings and bolts unscrew 2 16-May-19 17-May-19 Gouging of the weldings and bolts unscrew
02 Welding of lifting eyes on the two lateral sectors 2 16-May-19 17-May-19 Welding of lifting eyes on the two lateral sectors
03 Welding of lifting eyes on the Front Shield 1 17-May-19 17-May-19 Welding of lifting eyes on the Front Shield
04 Lifting operations of the two Outer Tele scopic Shield Lateral Sectors 3.4ton per side 1 18-May-19 18-May-19 Lifting operations of the two Outer Tele scopic Shield Lateral Sectors 3.4ton per side
Inner Telescopic Shield 1 19-May-19 19-May-19 19-May-19, Inner Telescopic Shield
05 Welding of lifting eyes 1 19-May-19 19-May-19 Welding of lifting eyes
06 Lifting operations of the Inner Telescopic Shield 9.2ton 1 19-May-19 19-May-19 Lifting operations of the Inner Telescopic Shield 9.2ton
TBM Tail Shield 2 19-May-19 20-May-19 20-May-19, TBM Tail Shield
07 Welding of lifting eyes on the Tail Shields 1 19-May-19 19-May-19 Welding of lifting eyes on the Tail Shields
08 Lifting operations of the Tail Shield 8ton 1 20-May-19 20-May-19 Lifting operations of the Tail Shield 8ton
TBM Auxiliary Parts 2 21-May-19 22-May-19 22-May-19, TBM Auxiliary Parts
09 Disassembling of 2 Main Thrust cylinders upper part 2ton each 2 21-May-19 22-May-19 Disassembling of 2 Main Thrust cylinders upper part 2ton each
10 Disassembling of electric motors 2.5ton each 2 21-May-19 22-May-19 Disassembling of electric motors 2.5ton each
Auxiliary Thust Cylinder 1 23-May-19 23-May-19 23-May-19, Auxiliary Thust Cylinder
11 Disassembly of Auxiliary Thrust Cylinder (8 pcs) Upper part 1 23-May-19 23-May-19 Disassembly of Auxiliary Thrust Cylinder (8 pcs) Upper part

Lifting Operation Using 280-ton Crane + 80-ton Crane 6 24-May-19 29-May-19 29-May-19, Lifting Operation Using 280-ton Crane + 80-ton Crane
Cutterhead 51.2ton (Tandem Lifting for Tailing) 1 24-May-19 24-May-19 24-May-19, Cutterhead 51.2ton (Tandem Lifting for Tailing)
12 Studs dismantling 1 24-May-19 24-May-19 Studs dismantling
13 Lifting eyes welding operation 1 24-May-19 24-May-19 Lifting eyes welding operation
14 Lifting of the cutterhead complete with cutting tools 1 24-May-19 24-May-19 Lifting of the cutterhead complete with cutting tools
Front Shield & Main Bearing (Tandem Lifting for Tailing) 3 25-May-19 27-May-19 27-May-19, Front Shield & Main Bearing (Tandem Lifting for Tailing)
15 Removal of bolts and gouging of antiroll arm 1 25-May-19 25-May-19 Removal of bolts and gouging of antiroll arm
16 Disassembly and lifting of antiroll cylinder / antiroll arm 1 25-May-19 25-May-19 Disassembly and lifting of antiroll cylinder / antiroll arm
17 Disassembling of 8 pcs Main Thrusts cylinders bottom part 2tons each 1 26-May-19 26-May-19 Disassembling of 8 pcs Main Thrusts cylinders bottom part 2tons each
18 Lifting operations of the Front Shield with main bearing & bottom outer telescopic shield 92tons 1 27-May-19 27-May-19 Lifting operations of the Front Shield with main bearing & bottom outer telescopic shield 92tons
TBM Hopper 1 26-May-19 26-May-19 26-May-19, TBM Hopper
19 Disassembly & lifting of hopper 1.8ton 1 26-May-19 26-May-19 Disassembly & lifting of hopper 1.8ton
Gripper Shield (Tandem Lifting for Tailing) 2 28-May-19 29-May-19 29-May-19, Gripper Shield (Tandem Lifting for Tailing)
20 Disassembling of 2 remaining auxiliary cylinder 1 28-May-19 28-May-19 Disassembling of 2 remaining auxiliary cylinder
21 Pulling and lifting of Gripper Shield with erector 2 28-May-19 29-May-19 Pulling and lifting of Gripper Shield with erector

Lifting Operation Using 80-ton Crane (Remaining) 19 29-May-19 16-Jun-19 16-Jun-19, Lifting Operation Using 80-ton Crane (Remaining)
TBM Conveyor 2 29-May-19 30-May-19 30-May-19, TBM Conveyor
22 Preparation of support of TBM Conveyor 1 29-May-19 29-May-19 Preparation of support of TBM Conveyor
23 Disconnection of the front part of the TBM belt Conveyor from the Rear part 1 30-May-19 30-May-19 Disconnection of the front part of the TBM belt Conveyor from the Rear part
24 Lifting operations of the TBM conveyor front part 7.5tons 1 30-May-19 30-May-19 Lifting operations of the TBM conveyor front part 7.5tons

25 Disconnection of the Towing cylinders 1 30-May-19 30-May-19 Disconnection of the Towing cylinders
26 Lifting operations of the Towing cylinders 1.75ton 1 30-May-19 30-May-19 Lifting operations of the Towing cylinders 1.75ton
27 Lifting operations of the TBM Conveyor Rear part 3.6ton 1 30-May-19 30-May-19 Lifting operations of the TBM Conveyor Rear part 3.6ton
Segment Feeder 1 31-May-19 31-May-19 31-May-19, Segment Feeder
28 Preparation for the lifting of the Segment Feeder 1 31-May-19 31-May-19 Preparation for the lifting of the Segment Feeder
29 Lifting operation of the Segment Feeder 3.5ton 1 31-May-19 31-May-19 Lifting operation of the Segment Feeder 3.5ton
Backup System 16 01-Jun-19 16-Jun-19 16-Jun-19, Backup System
30 Preparation for pulling TBM decks 1 01-Jun-19 01-Jun-19 Preparation for pulling TBM decks
31 Pulling operations of the "Deck 1" & "Bridge" 1 02-Jun-19 02-Jun-19 Pulling operations of the "Deck 1" & "Bridge"
32 Disconnection and construction of the support for Bridge 1 03-Jun-19 03-Jun-19 Disconnection and construction of the support for Bridge
33 Lifting operation of the "Deck 1" 13.5ton 1 04-Jun-19 04-Jun-19 Lifting operation of the "Deck 1" 13.5ton
34 Lifting operation of the "Bridge" 18ton 1 04-Jun-19 04-Jun-19 Lifting operation of the "Bridge" 18ton
35 Pulling operations of "Deck 2" & "Deck 3" & lifting operations of "Deck 2" 18tons & "Deck 3" 10tons 1 05-Jun-19 05-Jun-19 Pulling operations of "Deck 2" & "Deck 3" & lifting operations of "Deck 2" 18tons & "Deck 3" 10tons
36 Pulling operations of "Deck 4" & "Deck 5" & lifting operations of "Deck 4" 19tons & "Deck 5" 16tons 1 06-Jun-19 06-Jun-19 Pulling operations of "Deck 4" & "Deck 5" & lifting operations of "Deck 4" 19tons & "Deck 5" 16tons
37 Pulling operations of "Deck 6" & "Deck 7" & lifting operations of "Deck 6" 18tons & "Deck 7" 13.5tons 1 07-Jun-19 07-Jun-19 Pulling operations of "Deck 6" & "Deck 7" & lifting operations of "Deck 6" 18tons & "Deck 7" 13.5tons
38 Pulling operations of "Deck 8" & "Deck 9" & lifting operations of "Deck 8" 18tons & "Deck 9" 15.5tons 1 08-Jun-19 08-Jun-19 Pulling operations of "Deck 8" & "Deck 9" & lifting operations of "Deck 8" 18tons & "Deck 9" 15.5tons
39 Pulling operations of "Deck 10" & "Deck 11" & lifting operations of "Deck 10" 13tons & "Deck 11" 20tons 1 09-Jun-19 09-Jun-19 Pulling operations of "Deck 10" & "Deck 11" & lifting operations of "Deck 10" 13tons & "Deck 11" 20tons
40 Pulling operations of "Deck 12" & "Deck 13" & lifting operations of "Deck 12" 12.5tons & "Deck 13" 11tons 1 10-Jun-19 10-Jun-19 Pulling operations of "Deck 12" & "Deck 13" & lifting operations of "Deck 12" 12.5tons & "Deck 13" 11tons
41 Pulling operations of "Deck 14" & "Deck 15" & lifting operations of "Deck 14" 9tons & "Deck 15" 10tons 1 11-Jun-19 11-Jun-19 Pulling operations of "Deck 14" & "Deck 15" & lifting operations of "Deck 14" 9tons & "Deck 15" 10tons
42 Pulling operations of "Deck 16" & "Deck 17" & lifting operations of "Deck 16" 9tons & "Deck 17" 15tons 1 12-Jun-19 12-Jun-19 Pulling operations of "Deck 16" & "Deck 17" & lifting operations of "Deck 16" 9tons & "Deck 17" 15tons
43 Pulling operations of "Deck 18" & "Deck 19" & lifting operations of "Deck 18" 14tons & "Deck 19" 12.5tons 1 13-Jun-19 13-Jun-19 Pulling operations of "Deck 18" & "Deck 19" & lifting operations of "Deck 18" 14tons & "Deck 19"
44 Pulling operations of "Deck 20" & "Deck 21" & lifting operations of "Deck 20" 12tons & "Deck 21" 11tons 1 14-Jun-19 14-Jun-19 Pulling operations of "Deck 20" & "Deck 21" & lifting operations of "Deck 20" 12tons & "D
45 Pulling operations of "Deck 22" & "Deck 22BIS" & lifting operations of "Deck 22" 10tons & "Deck 22BIS" 8tons 1 15-Jun-19 15-Jun-19 Pulling operations of "Deck 22" & "Deck 22BIS" & lifting operations of "Deck 22" 1
46 Pulling operations of "Deck 23" & "Ramp" & lifting operations of "Deck 23" 17.5tons & "Ramp" 3tons 1 16-Jun-19 16-Jun-19 Pulling operations of "Deck 23" & "Ramp" & lifting operations of "Deck 23"

Project Baseline Bar Remaining Work Milestone Page 1 of 1 TASK filter: All Activities

Actual Work Critical Remaining Work Summary © Oracle Corporation