Auxiliary Mechanical Equipment Micro Schedule Data Date ; 09-May-19 1 of 1

Activity ID Activity Name Original Start Finish 2019 2020 2021


Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Auxiliary Mechanical Equipment Micro Schedule 644 09-May-19 10-Feb-21

General/Engineering Works 23 09-May-19 31-May-19


A1000 Contract Signing 0 09-May-19 Contract Signing,
A1020 Review and Approval of Detailed Design by DOHWA/MWSS 21 11-May-19 31-May-19 Review and Approval of Detailed Design by DOHWA/MWSS, 31-May-19
A1030 Detailed Design Approved 0 31-May-19 Detailed Design Approved, 31-May-19
Delivery Schedule 147 01-Jun-19 25-Oct-19
A1050 1st Shipment Arrived at Manila Port (Buried structure of new pool part/Bolts of column of Cleaning Machine) 70 01-Jun-19 09-Aug-19 1st Shipment Arrived at Manila Port (Buried structure of new pool part/Bolts of column of Cleaning Machine), 09-Aug-19
A1080 2nd Shipment Arrived at Manila Port (Electrical Power Generator) 130 01-Jun-19 08-Oct-19 2nd Shipment Arrived at Manila Port (Electrical Power Generator), 08-Oct-19
A1110 3rd Shipment Arrived at Manila Port (All Other Main Equipment) 140 01-Jun-19 18-Oct-19 3rd Shipment Arrived at Manila Port (All Other Main Equipment), 18-Oct-19
A1070 Delivery of 1st Shipment from Manila Port to Project Site 7 10-Aug-19 16-Aug-19 Delivery of 1st Shipment from Manila Port to Project Site, 16-Aug-19
A1100 Delivery of 2nd Shipment from Manila Port to Project Site 7 09-Oct-19 15-Oct-19 Delivery of 2nd Shipment from Manila Port to Project Site, 15-Oct-19
A1130 Delivery of 3rd Shipment from Manila Port to Project Site 7 19-Oct-19 25-Oct-19 Delivery of 3rd Shipment from Manila Port to Project Site, 25-Oct-19
Installation/Testing and Commissioning Schedule 453 25-Oct-19 20-Jan-21
Installation 67 25-Oct-19 31-Dec-19
Inlet Structure 67 25-Oct-19 31-Dec-19
A3270 Completion of Inlet Structure 0 25-Oct-19* Completion of Inlet Structure, 25-Oct-19*
A3200 Floating boom (13.62m) 10 26-Oct-19 04-Nov-19 Floating boom (13.62m), 04-Nov-19
A3210 Trashrack 3 - 3 pcs (1.904m x 2.56m) 12 26-Oct-19 06-Nov-19 Trashrack 3 - 3 pcs (1.904m x 2.56m), 06-Nov-19
A3220 Stoplog (3.0m x 2.0m) 19 05-Nov-19 23-Nov-19 Stoplog (3.0m x 2.0m), 23-Nov-19
A3230 Sluiceway Gate with Manual operating crank & pedestal stand (3.0m x 2.0m) 20 11-Nov-19 30-Nov-19 Sluiceway Gate with Manual operating crank & pedestal stand (3.0m x 2.0m), 30-Nov-19
A3240 Mechanical Rake 10 20-Nov-19 29-Nov-19 Mechanical Rake, 29-Nov-19
A3250 Generator set (30 kVA) 2 30-Nov-19 01-Dec-19 Generator set (30 kVA), 01-Dec-19
A3260 Electr. Distr. Line from Ipo dam to Tunnel 4 Intake 30 02-Dec-19 31-Dec-19 Electr. Distr. Line from Ipo dam to Tunnel 4 Intake, 31-Dec-19
Transition Basin 28 24-Nov-19 21-Dec-19
A3620 Stoplog (4.4m x 4.4m) 28 24-Nov-19 21-Dec-19 Stoplog (4.4m x 4.4m), 21-Dec-19
A3630 Flow Measuring Device for Open Channel 28 24-Nov-19 21-Dec-19 Flow Measuring Device for Open Channel, 21-Dec-19
Interconnection to Aqueduct No. 5 30 04-Nov-19 04-Dec-19
A3660 Completion of Interconnection to Aqueduct No. 5 0 04-Nov-19* Completion of Interconnection to Aqueduct No. 5, 04-Nov-19*
A3640 1.0m dia Gate Valve (it must be Sluice gate) 30 05-Nov-19 04-Dec-19 1.0m dia Gate Valve (it must be Sluice gate), 04-Dec-19
A3650 Sliding Gate (4.3m x 4.4m) 30 05-Nov-19 04-Dec-19 Sliding Gate (4.3m x 4.4m), 04-Dec-19
Testing and Commissioning 416 02-Dec-19 20-Jan-21
Electrical and Mechanical 45 02-Dec-19 15-Jan-20
A3760 Mechanical Equipment Testing & Commisioning 30 02-Dec-19 31-Dec-19 Mechanical Equipment Testing & Commisioning, 31-Dec-19
A3750 Electrical Equipment Testing & Commissioning 30 14-Dec-19 12-Jan-20 Electrical Equipment Testing & Commissioning, 12-Jan-20
A3770 Final Inspection Activities 15 01-Jan-20 15-Jan-20 Final Inspection Activities, 15-Jan-20
Operational Test 371 16-Jan-20 20-Jan-21
A3780 Operational Test 5 16-Jan-20 20-Jan-20 Operational Test, 20-Jan-20
A3790 Warranty Period (365 days) 365 21-Jan-20 19-Jan-21 Warranty Period (365 days), 19-Jan-21
A3800 Final Acceptance Certificate 1 20-Jan-21 20-Jan-21 Final Acceptance Certificate, 20-Jan-21
Payment Schedule 644 09-May-19 10-Feb-21
A1010 CEMEC Invoice for Downpayment (10%) Received 21 09-May-19 29-May-19 CEMEC Invoice for Downpayment (10%) Received, 29-May-19
A1040 CEMEC Invoice for Detailed Design Approval (30%) Received 21 01-Jun-19 21-Jun-19 CEMEC Invoice for Detailed Design Approval (30%) Received, 21-Jun-19
A1060 CEMEC Invoice for 1st Shipment (5%) Received 21 10-Aug-19 30-Aug-19 CEMEC Invoice for 1st Shipment (5%) Received, 30-Aug-19
A1090 CEMEC Invoice for 2nd Shipment (5%) Received 21 09-Oct-19 29-Oct-19 CEMEC Invoice for 2nd Shipment (5%) Received, 29-Oct-19
A1120 CEMEC Invoice for 3rd Shipment (30%) Received 21 19-Oct-19 08-Nov-19 CEMEC Invoice for 3rd Shipment (30%) Received, 08-Nov-19
A1140 CEMEC Invoice for Installation/Preliminary Acceptance (15%) Received 21 21-Jan-20 10-Feb-20 CEMEC Invoice for Installation/Preliminary Acceptance (15%) Received, 10-Feb-20
A1150 CEMEC Invoice for Final Acceptance (5%) Received 21 21-Jan-21 10-Feb-21 CEMEC Invoice for Final Acceptance

Remaining Level of Effort Remaining Work AUXILIARY MECHANICAL EQUIPMENT MICRO SCHEDULE Date Revision Checked Approved
09-May-19 Revision 0 CMC
Actual Level of Effort Critical Remaining Work
Actual Work Milestone