Вы находитесь на странице: 1из 7

`Job Safety Analysis Page 1

JOB SAFETY ANALYSIS (JSA)

Associated industrial JSA Number:


Company name: Date
furnaces Pvt. Ltd. HZL/FUMER/SCAFFOLDIING- 00

Supervisor name :Mr.


Site name: FUMER Project Permit to work required? :Yes

Plant / Area: HZL ,Fumer/STG Location: :

Scope of JSA :
1. To find out all hazards associated with each activity
2. To fix control measures to mitigate the hazard
3. To follow proper engineering / OHS guidelines to complete the job in safe manner to prevent any incident and property loss.

JSA team member names:

Sign. By AIFL/UNI7 Sign. By NFC Sign. BY CBRE

Version 1.0, April 2016


`Job Safety Analysis Page 2

Activity Hazards Controls


Provide a step-by-step List all hazards associated with each Measures that need to be taken to eliminate or minimise the risk associated with each
breakdown of the task step hazard
 Use Cut Resistance hand Gloves level-4.
1.1 Cut injury.
1. Area inspection and  Wear dust mask.
1.2 Dust inhalation.
levelling.  Area must be cleared of any obstacle.
1.3 Slip trip & falls.
 Proper housekeeping should be done before starting the job.
 Job specific TBT before starting the job.
 Material should be stored properly & not obstructed the passage.
1.1 Slippage of material.
 Proper barrier should be present to prevent slippage.

1.2 Cut injury by sharp edges.


2. Material Shifting and  Wears hand gloves. Use shoulder pad during Manual shifting.
Storage.
1.3 Fall of materials.
 Ensure Proper material handling procedure when shifting material manually.

1.4 Ergonomic Hazard.


 Don’t allow to shift excess load manually.
 Shift material using gin wheel or pull up / lower the material with rope & sack.
3.1 Scaffold may topple due to  Surface should be levelled & compacted.
uneven surface.

 Job Specific tool box meeting to be conducted before commence of the work.
3.2 Fall of materials.  Materials to be lift by certified rope pulley if required.
 Follow the sequence of scaffolding erection.
3. Scaffolding Erection.
 Right body position must be ensure while material handling
 Place tools in sack / toolbox.
 Tools to be tied with string.

3.3 Fall of person.


 Job specific PPE (safety harness with shock absorber if 6 meter &above) must be

Version 1.0, April 2016


`Job Safety Analysis Page 3

Activity Hazards Controls


Provide a step-by-step List all hazards associated with each Measures that need to be taken to eliminate or minimise the risk associated with each
breakdown of the task step hazard
provided to all workers involved with scaffolding erection.
 Proper anchorage point or if required life line to be provided.
 Only medically fit for height and trained worker must be deployed for erection work.
 Retractable fall arrestor to be used if required.
 Area must be barricaded and warning board will be displayed.

 Line of fire must be followed strictly.


3.4 Hit by scaffolding materials.
3.5 Collapse of scaffold.
 Scaffolding erection work should be maintained as per scaffolding standard and
certified scaffolder.
 During Erection Red Tag Should Be Displayed.
 Area must be barricaded and warning board will be displayed.
 Scaffolding height above 15meter, approved designed drawing should be available at
site before starting the job.
3.6 Overhead power cable.  Don’t use rusted & damaged material.
 Authorized and trained scaffolder for erected of scaffold.

 Avoid overhead cable area/zone.


3.7 Collapse of Mobile Scaffold.

 Parallel Job is not allowed during scaffolding Erection.


 Insure Lock the wheel of Mobile Scaffold to Avoid any sudden Move.
 Insure to fix out legs of mobile scaffold & Proper lock with Pin.
4.1 Fall of material.  Job specific Tool box Talk to be conducted before commence of the work.
 Dismantling scaffolding pipes should be bringing down by rope pulley.
 Using rope pulley/ chain pulley block must have TPIC with load test.
4. Dismantling of scaffolding.
 Use joint free PP rope with 19mm thickness.
 Place tools in sack / toolbox.
 Tools to be tied with string.
Version 1.0, April 2016
`Job Safety Analysis Page 4

Activity Hazards Controls


Provide a step-by-step List all hazards associated with each Measures that need to be taken to eliminate or minimise the risk associated with each
breakdown of the task step hazard

 Job specific PPE (safety harness with shock absorber if 6 meter &above) must be
provided to all workers involved with scaffolding erection.
 Only medically fit and trained worker must be deployed for dismantling work.
 Scaffolding dismantling work should be carried out in the presence of job supervisor
from top to bottom area also barricading with stand by person.
 Proper anchorage point or if required life line to be provided.
4.2 Fall of person.  Retractable fall arrestor to be used if required.

 Area must be barricaded and warning board will be displayed.

4.3 Hit by scaffolding material.


 Line of fire must be followed strictly, do not walk under suspended load.
 Red tag must be displayed at the time of dismantling.
 Follow the dismantling sequence of scaffolding.
4.4 Collapse scaffold.  Area must be barricaded and Cautionary board will be displayed.
4.5 Over head cable.  Don’t stand inside line of fire.

 Avoid over head cable area/zone.

Version 1.0, April 2016


`Job Safety Analysis Page 5

Activity Hazards Controls


Provide a step-by-step List all hazards associated with each Measures that need to be taken to eliminate or minimise the risk associated with each
breakdown of the task step hazard
5. Housekeeping/stacking of 5.1 Slip, trip & Fall injury. 5.1 Material should be stored properly & not obstructed the passage.
dismantled material. 5.2 Proper barrier should be present to prevent slippage.
5.3 Ensure Proper material handling procedure when shifting material manually.

5.2 Cut injury by sharp edges.


5.2 Use Cut Resistance (level-4) hand gloves.

1. Usage of job specific PPE’S.


1. Burn injury. 2. All electrical tools to be tested.
2. Cut injury. 3. All electrical tools connection through ELCB.
3. Fire. 4. Area to be free from combustible material.
4.Electric shock by Raining or 5. Wearied cutting and binding area to be barricaded.
Machine in open yard 6 .Fire extinguisher to be ensured at site.
7. Cutting and binding area to be barricaded.
8. Remove the scrap material.
Cutting and binding of TMT. 9. Electrical Machine and its accessories shall be keep under shade and protect these
by Raining.
10. Use specific Hand Gloves while handling and cutting/bending the Reinforcement

Bars to avoid the Electric Shock by Wet Reinforcement in Monsoon.

Version 1.0, April 2016


`Job Safety Analysis Page 6

11. Only Authorized Operator Must Operate the cutting and bending machine.

1. All workers on site shall wear proper PPE’S.


1. Slip of material. 2. Area Proper housekeeping.
2. Cut injury. 3. Safe access provided.
3. Tripping. 4. Area should be free from any inessential objects.
5. Shuttering material should not be in loose condition.
De-shuttering work 6. After removing of shuttering from height, it should not be thrown freely from
height.
7. People should not work under the scaffolding where de-shuttering work in
progress at height for Walls/Columns.
8. Area should be barricaded at ground level where de-shuttering work is going on at
height.
1.Fall injury - Specific tool box talk to be undertaken prior to work at height activities.
-Scaffolding inspection as per defined standards to ensured.
2.Cut injury
- Use of long handled tools where appropriate.
3.Slippage of material - Full body harness without shock absorber should be used upto 6.0 m height
and over 6.0 m full body harness with shock absorber should be used.
-Life line/Anchor point to be ensured to anchor safety harness.
Falls from height. - Close supervision to be ensured during the work.
- Consider use of fall arrest systems depending on nature of task, equipment
and duration.
-Walk platform to be secured.
-Safety nets should be used if working above 8.0 m.
- Adequate and appropriate signs in place to warn of hazards below work area.
- Ensure operatives trained to work at height.
-Area should be barricaded at ground level.

Version 1.0, April 2016


`Job Safety Analysis Page 7

1. Cut Injury 1. Wear cut resistant(LVL IV) hand gloves while manually shifting only.
Manually Material 2. Do not carry over load against man strength. Only carry suitable load.
2. Slipping
Shifting at site 3. Maintain safe distance from all workers while carrying.
4. Keep the area barricaded.

Version 1.0, April 2016

Вам также может понравиться