Excavation Works for the Intake Structure Page 1 of 1

Activity ID Activity Name Original Start Finish May 2019 June 2019 July 2019 August 2019
Duration
28 05 12 19 26 02 09 16 23 30 07 14 21 28 04
Excavation Works for the Intake Structure 69.00 02-May-19 09-Jul-19

Phase 01 1.50 02-May-19 03-May-19


A1000 Excavate 0.8m width along basin side up to Elev. 95.7 by Hydromill rig 1.50 02-May-19 03-May-19 Excavate 0.8m width along basin side up to Elev. 95.7 by Hydromill rig

Phase 02 1.00 03-May-19 04-May-19


A1010 Excavate until 1.50m deep from top of diaphragm wall by Back hoe/Breaker 1.00 03-May-19 04-May-19 Excavate until 1.50m deep from top of diaphragm wall by Back hoe/Breaker

Phase 03 6.25 04-May-19 10-May-19


A1020 1st Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 04-May-19 04-May-19 1st Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1030 1st Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 04-May-19 05-May-19 1st Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
A1040 2nd Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 05-May-19 05-May-19 2nd Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1050 2nd Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 06-May-19 06-May-19 2nd Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
A1060 3rd Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 07-May-19 07-May-19 3rd Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1070 3rd Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 07-May-19 08-May-19 3rd Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
A1080 4th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 08-May-19 08-May-19 4th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1090 4th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 08-May-19 09-May-19 4th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
A1100 5th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 09-May-19 09-May-19 5th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1110 5th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 09-May-19 10-May-19 5th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
Phase 04 5.25 10-May-19 15-May-19
A1180 Place Concrete Lego blocks & wood blocks between TBM gripper shoes/diaphragm wall 1.50 10-May-19 12-May-19 Place Concrete Lego blocks & wood blocks between TBM gripper shoes/diaphragm wall
A1120 6th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 12-May-19 12-May-19 6th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1130 6th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 12-May-19 13-May-19 6th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
A1140 7th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 13-May-19 13-May-19 7th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1150 7th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 13-May-19 14-May-19 7th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
A1160 8th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m 0.25 14-May-19 14-May-19 8th Thrust by TBM - Excavate 1.3m by TBM / Retract TBM by 1.3m
A1170 8th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer 1.00 15-May-19 15-May-19 8th Thrust - Mechanical excavation remaining portion by Back hoe/jack hammer
Phase 05 55.00 16-May-19 09-Jul-19

TBM Disassembly and removal 52.00 16-May-19 06-Jul-19


A1190 Installation of Truck Crane and other Equipment 1.00 16-May-19 16-May-19 Installation of Truck Crane and other Equipment
A1200 TBM dismante & removal 9.00 17-May-19 25-May-19 TBM dismante & removal
A1220 Installation of inverter and rails 4.00 26-May-19 29-May-19 Installation of inverter and rails
A1210 Backup dismantle and removal 36.00 30-May-19 04-Jul-19 Backup dismantle and removal
A1230 Removal of inverter and rails 2.00 05-Jul-19 06-Jul-19 Removal of inverter and rails
Final Excavation 3.00 07-Jul-19 09-Jul-19
A1240 Excavation to final elevation of 94.70m by mechanical means 2.00 07-Jul-19 08-Jul-19 Excavation to final elevation of 94.70m by mechanical means
A1250 Cleaning / removal of all excess materials 1.00 09-Jul-19 09-Jul-19 Cleaning / removal of all excess materials

Level of Effort Critical Remaining ... EXCAVATION WORKS FOR THE INTAKE STRUCTURE
Actual Level of Effort Milestone
Primary Baseline SCHEDULE OF WORKS
Actual Work
Remaining Work