Contractor’s Representative

Package D

Dear Sir,

SUBJECT: Concrete Outline & Reinforcement Details of Approach Slabs & Parapet Walls of Viaduct
from 76+737 Km to 77+013 Km (Rev: 00)

Your letter # 429M (3381) 11674 dated 27th July 2019 that received by us on 29th July 2019 is referred.

Having reviewed your submission by our Structural Engineer, please find duly endorsed drawings for
your necessary action.