Al Fardan - Work Schedule (6th july to 30th july)

Sr No. Location Work Details Qty UOM

1 Chilled water valve package( V.P) with piping 28 No's


10th Floor
2 Installing Flexible pipe, Air vent of V.P 50 No's

122 No's
9th Floor
3 Installation of Pendant Sprinklers
4 Ajustment of Corridor Sprinklers 10 No's

10 No's
5 GF, 9th, 10th Floor Hose Reel Installation
6 65mm CHW Pipe installation 10 Mtrs
10th Floor
7 Riser connections 2 Set
8 CHW pipe installation
9 Basement-1 32mm 10 Mtrs
10 25mm 12 Mtrs
11 100mm with Riser connection 12 Mtrs
12 7th floor FCU Valve package 3 No's
13 Installing Air vent of V.P 25 No's

Note: Work which was not included in report before


Ground floor Drain pipe installation
25mm 80/90 Mtrs
Main line 50mm 12 Mtrs
Fire fighting testing 1 Set
Pendant droppers in critical area 20 Nos
basement-1 FCU Valve package 1 No's
Installation of Gate valves in main Line 2 No's
Re- work of 32mm CHW Piping 8 Mtrs
32mm pipe installed 10 Mtrs
7th Floor AHU valve package with piping 1 Set
FF branch line Re-work 4 Mtrs
9th Floor Sprinklers Re- work 3 Nos
10th Floor Sprinklers & Branch Re- work 3 Nos
50mm FF pipe re- work 7 Mtrs
3/4" CHW PIPE re- work 7 Mtrs
Riser connection Re-work 1 Set
(6th july to 30th july)

Pending Qty

2 (Max 1 day it will take for 2 people) It took time


20 because more length of piping work is done.

Done

10 Ceiling not fixed yet

5 Pipes are dropped down, Only cabinet Fixing is


pending. Didn’t get clearance from stream.
Done
20% connecting work is pending
Done

Done
Done
12
3 Fcu machine not installed
25

Done
Done
Done
Done (More 50% work require to finish completely)
Done
Done
Done
Done
Done
Done
Done
Done
Not yet We removed pipe need to install back
Done
Done