Activity ID Activity Name Original Duration Start Finish Budgeted Labor Total Float September 2019 October 2019 November 2019
Units
24 31 07 14 21 28 05 12 19 26 02 09
Montaje de Taller de Auxiliar & Semipesado 79 23-Aug-19 09-Nov-19 39904.85 0 09-Nov-19, Montaje de Taller de Auxiliar & Semipesado
Actual Level of Effort Remaining Work Milestone Page 1 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Montaje de Taller de Auxiliar Semipesado Schedule Layout WBS 25-Aug-19 09:39
Activity ID Activity Name Original Duration Start Finish Budgeted Labor Total Float September 2019 October 2019 November 2019
Units
24 31 07 14 21 28 05 12 19 26 02 09
A1270 Cobertura Eje 3@4 7 12-Oct-19 18-Oct-19 416.67 3 Cobertura Eje 3@4
A1280 Cobertura Eje 4@5 7 05-Oct-19 11-Oct-19 416.67 3 Cobertura Eje 4@5
A1290 Cobertura Eje 5@6 5 30-Sep-19 04-Oct-19 416.67 3 Cobertura Eje 5@6
A1300 Cobertura Eje 6@7 & Eje 5 25-Sep-19 29-Sep-19 416.67 3 Cobertura Eje 6@7 & Eje
A1310 Cobertura Eje 7@8 & Eje 5 02-Nov-19 06-Nov-19 833.33 3 Cobertura Eje 7@8 & Eje
Taller Equipo Auxiliar 74 28-Aug-19 09-Nov-19 23978.02 0 09-Nov-19, Taller Equipo Auxiliar
Actual Level of Effort Remaining Work Milestone Page 2 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Montaje de Taller de Auxiliar Semipesado Schedule Layout WBS 25-Aug-19 09:39
Activity ID Activity Name Original Duration Start Finish Budgeted Labor Total Float September 2019 October 2019 November 2019
Units
24 31 07 14 21 28 05 12 19 26 02 09
A3120 Elementos eje F@4/5 4 16-Sep-19 19-Sep-19 203.12 13 Elementos eje F@4/5
A3130 Elementos eje F@5/6 4 18-Sep-19 21-Sep-19 195.04 2 Elementos eje F@5/6
A3140 Elementos eje F@6/7 4 20-Sep-19 23-Sep-19 203.12 0 Elementos eje F@6/7
A3150 Elementos eje F@7/8 4 22-Sep-19 25-Sep-19 193.35 19 Elementos eje F@7/8
A3160 Elementos eje F@8/9 4 24-Sep-19 27-Sep-19 203.12 21 Elementos eje F@8/9
A3170 Elementos eje F@9/10 4 26-Sep-19 29-Sep-19 193.35 19 Elementos eje F@9/10
A3180 Elementos eje F@10/11 4 01-Oct-19 04-Oct-19 206.12 18 Elementos eje F@10/11
A3190 Elementos eje F@11/12 4 06-Oct-19 09-Oct-19 14.04 16 Elementos eje F@11/12
A3200 Elementos eje B@1/2 4 09-Sep-19 12-Sep-19 320.84 11 Elementos eje B@1/2
A3210 Elementos eje B@2/3 4 11-Sep-19 14-Sep-19 332.30 12 Elementos eje B@2/3
A3220 Elementos eje B@3/4 4 13-Sep-19 16-Sep-19 263.91 13 Elementos eje B@3/4
A3620 Elementos eje B@4/5 4 15-Sep-19 18-Sep-19 332.22 14 Elementos eje B@4/5
A3630 Elementos eje B@5/6 4 17-Sep-19 20-Sep-19 312.76 3 Elementos eje B@5/6
A3640 Elementos eje B@6/7 4 19-Sep-19 22-Sep-19 287.84 1 Elementos eje B@6/7
A3650 Elementos eje B@7/8 4 21-Sep-19 24-Sep-19 308.30 20 Elementos eje B@7/8
A3660 Elementos eje B@8/9 4 23-Sep-19 26-Sep-19 325.68 22 Elementos eje B@8/9
A3670 Elementos eje B@9/10 4 25-Sep-19 28-Sep-19 265.14 20 Elementos eje B@9/10
A3680 Elementos eje B@10/11 4 27-Sep-19 30-Sep-19 331.68 22 Elementos eje B@10/11
MONTAJE DE ESCALERAS Y OTROS 16 17-Sep-19 02-Oct-19 574.18 38 02-Oct-19, MONTAJE DE ESCALERAS Y OTROS
A3230 Montaje de Escalera 4 17-Sep-19 20-Sep-19 41.61 38 Montaje de Escalera
A3240 Montaje de barandas 6 21-Sep-19 26-Sep-19 193.73 38 Montaje de barandas
A3250 Montaje de Grating 6 27-Sep-19 02-Oct-19 338.84 38 Montaje de Grating
MONTAJE DE CORREAS 30 22-Sep-19 21-Oct-19 4944.39 16 21-Oct-19, MONTAJE DE CORREAS
A3260 Correa Eje 1@2 4 22-Sep-19 25-Sep-19 611.77 10 Correa Eje 1@2
A3270 Correa Eje 2@3 4 24-Sep-19 27-Sep-19 431.69 11 Correa Eje 2@3
A3280 Correa Eje 3@4 4 26-Sep-19 29-Sep-19 456.08 12 Correa Eje 3@4
A3290 Correa Eje 4@5 4 28-Sep-19 01-Oct-19 437.54 13 Correa Eje 4@5
A3300 Correa Eje 5@6 4 30-Sep-19 03-Oct-19 442.85 15 Correa Eje 5@6
A3310 Correa Eje 6@7 4 02-Oct-19 05-Oct-19 435.08 0 Correa Eje 6@7
A3320 Correa Eje 7@8 4 04-Oct-19 07-Oct-19 442.23 19 Correa Eje 7@8
A3700 Correa Eje 8@9 4 06-Oct-19 09-Oct-19 438.15 21 Correa Eje 8@9
A3710 Correa Eje 9@10 4 08-Oct-19 11-Oct-19 439.23 19 Correa Eje 9@10
A3720 Correa Eje 10@11 4 13-Oct-19 16-Oct-19 461.46 18 Correa Eje 10@11
A3770 Correa Eje 11@12 4 18-Oct-19 21-Oct-19 348.31 16 Correa Eje 11@12
Obras de Arquitectura 35 06-Oct-19 09-Nov-19 5833.36 0 09-Nov-19, Obras de Arquitectura
A2380 Cobertura Eje 1@2 3 06-Oct-19 08-Oct-19 1458.33 0 Cobertura Eje 1@2
A2390 Cobertura Eje 2@3 3 09-Oct-19 11-Oct-19 466.67 0 Cobertura Eje 2@3
A2400 Cobertura Eje 3@4 3 12-Oct-19 14-Oct-19 466.67 0 Cobertura Eje 3@4
A2410 Cobertura Eje 4@5 4 15-Oct-19 18-Oct-19 466.67 0 Cobertura Eje 4@5
A2420 Cobertura Eje 5@6 4 19-Oct-19 22-Oct-19 466.67 0 Cobertura Eje 5@6
A2430 Cobertura Eje 6@7 4 23-Oct-19 26-Oct-19 466.67 0 Cobertura Eje 6@7
A2440 Cobertura Eje 7@9 4 27-Oct-19 30-Oct-19 466.67 0 Cobertura Eje 7@9
A3410 Cobertura Eje 9@10 4 31-Oct-19 03-Nov-19 466.67 0 Cobertura Eje 9@10
A3730 Cobertura Eje 10@11 3 04-Nov-19 06-Nov-19 466.67 0 Cobertura Eje 10@11
A3740 Cobertura Eje 11@12 3 07-Nov-19 09-Nov-19 641.67 0 Cobertura Eje 11@12
Units
Budgeted Labor
Actual Labor
Remaining Labor
10000.00h 40000.00h
8000.00h 32000.00h
6000.00h 24000.00h
4000.00h 16000.00h
2000.00h 8000.00h
0.00h
24 31 07 14 21 28 05 12 19 26 02 09
September 2019 October 2019 November 2019
Actual Level of Effort Remaining Work Milestone Page 3 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation