Вы находитесь на странице: 1из 12

Seismic Design

Considerations for
Precast Concrete
Multistory Buildings
Robert E. Englekirk wenty-five years ago, the use of • Beams and girders (supporting non-
Ph.D., P.E.
Adjunct Professor
Department of Civil Engineering
T precast concrete in buildings
located in regions of high seis-
micity was more prevalent than it is
seismic loads only)
• Columns (posts)
Today, earthquake bracing systems
University of California today. (Reasons for this decline, to- composed of precast concrete ele-
at Los Angeles; and gether with ideas to alleviate this situ- ments are seldom attempted. This ex-
Chief Executive Officer ation, are given in Refs. 1 and 2.)
Englekirk & Hart, Inc.
clusion of precast concrete elements
Los Angeles, California Currently, most precast concrete from seismic load paths has not al-
used in buildings in high seismic ways been the case. In the early
zones, particularly on the West Coast, 1970s, a few precast concrete bracing
is confmed to: systems were attempted. Two basic
The precast concrete industry • Cladding building systems were built:
• Topped floor slab systems • Ductile frames using precast con-
is perceived by the author to
be at a crossroads - one
path leading to an uncertain
future, the other to a new in-
dustry with ever-expanding
horizons. The evolution of the
precast concrete industry in
seismically active regions of
the United States and other
parts of the world are dis-
cussed. Current innovative
system concepts are pre- CONCRETE
COLUMN
sented and the technological
needs of the industry are
identified. A program for in-
suring that the industry ex-
pands its horizons is outlined.
Fig. 1. Precast concrete shell for a ductile frame beam.

40 PCI JOURNAL
ism developed for cast-in-place con-
v crete. Additionally, all of the pre-
w: ~ ~
f:: scriptive provisions developed to
~'-r--- f5 I 16'
promote ductility in cast-in-place
r- 1- PANEL REINFORCING concrete are imposed on precast con-
Ill crete construction.
Ill
Ill The concrete details shown in Figs.
Ill I~
POUR SOLID POCK ET
AFTER WELDING "' :u
lfl
3 and 4 were considered "state of the
art" design concepts in the 1970s be-
ANGLE 2X2X3/16 Ill cause they exceeded code require-
FIELD WELDED TO BARS-1- Ill
Ill ments. They are taken from plans for
Ill a 10-story apartment building located
GRO
UT~ c -=- I I
I ~ 2-f5 I!
BOTTOM OF PANEL in Whittier, California, which was
I
t: :::: . . ... . ... . .......
..~ ~ , .. ,
subjected to an acceleration in excess
of 0.6g during the Whittier earth-
quake. The building experienced no
damage.
State of the practice (code comply-
c~ ing construction) details for frames
and shear walls are shown in Figs. 5
and 6. Clearly, they are not intended
for precast concrete construction.
(}
A recent (early 1980s) attempt at a
midrise (six-story) precast concrete
Fig. 2. Chord tie between two precast panels.
building was attempted by Rockwin
Corporation. Although all the com-
crete shells (Fig. 1), and absorption are provided." This ponents of the building are precast,
• Vertically assembled wall panel "equivalent ductility" option was the seismic technology is really a cast-
systems. A chord tie for such an as- never used - and is still not used - in-place mentality (Fig. 7). Rockwin
sembly is shown in Fig. 2. because a standard methodology for used this system to build their cor-
Unfortunately, the construction of establishing "energy absorption and porate office building. During the
the prototype was more difficult than ductility equivalence" does not exist. Whittier earthquake, this building
envisioned and neither approach was As a consequence, all load transfers was subjected to a full scale test at
developed into a standard building must be accomplished by a mechan- loads of probably 6 to 10 times code-
system. Precast concrete seismic
bracing systems were abandoned be-
cause the connectivity problems were
clearly overwhelming. Frame beam a: u
B'-4'
~Ul 0
shell to column connections and rein-
forcing placement requirements were
ZIIJ
HH
<1-
...
0
5'-B'
::E
11.111..
more difficult and time consuming a:o Ill
'J....._r

even though the objective was to em-


ulate the cast-in-place ductile frame
of the 1970s (Fig. 3).
Connecting panels using welded
.
.
CD

.
CD
I --,- 8

splices was expensive and the quality ..


CD

CD
2'
4'4'4~12'0R .12'0R .12'0R .12' IR .12'0R .12"0R .1 "OR

..,
control poor. The chord ties and shear 1B" 18' 18' 18 18" 18'
I
transfer details for cast-in-place C\1

'0 '0 ~
buildings built in the early 1970s did
not include boundary elements and,
as a consequence, were simple by
today' s standards. Fig. 4 is taken from
fffJ ji) I
the end of a shear wall designed to __.......J- I

1970 standards.
Precast concrete construction then,
as now, was required to conform to a
code developed for cast-in-place con-
crete unless "evidence is submitted
ct 1--

h.__ -
lc ELEVATION B-B
8

that equivalent ductility and energy Fig. 3. Ductile frame reinforcing (1970 vintage).

May-June 1990 41
ADDITIONAL -ru. '-
EXTERNAL COLUMN
REI~ORCING
2-#4 WITH
#3 TIES @ 18 f---8" END LONGITUDINAL
(OMITTED FROM SHEAR WALL LEVEL REINFORCING
ELEVATION ABOVE
FOR CLARITY)
• 1-4 14-#11
r---
r- 4-6 10-#11
• • ----#4 TI~S
2 @4 5 @ 6" 6-7 8-#11
REM . @' 10 " 0 . C .

• "•L ~ 7-8 6-#11

6" ARCH'L.
PROJECTION--· {Jh- • _ ~l
. =
ta ::hl
\__AS ADJACENT FACE
8-9

9-R
6-#10

4-#9

Fig. 4. Boundary element for a shear wall (1970 vintage).

prescribed load levels. No structural of seismic bracing systems. So long PRESSS (Precast Seismic Structural
damage occurred. The Rockwin head- as precast concrete elects to live in the Systems). The objectives of this pro-
quarters building is the only building shadow of cast-in-place concrete, it gram are to:
constructed using this system; unfor- will always remain the ''ugly (unbuild- 1. Develop comprehensive and ra-
tunately, the structural market for able) sister." tional design recommendations based
precast concrete is rapidly disappear- On the other hand, during the past on fundamental and basic research
ing in regions of high seismicity. decade the masonry industry has data which will optimize the viability
made enormous strides in developing of precast concrete construction in
a seismic design technology that seismic zones.
Creating a Viable recognizes how masonry is econom- 2. Develop new materials, concepts
Precast Concrete Industry ically constructed. The precast con- and technologies for precast concrete
If precast concrete is to become a crete industry must, and hopefully construction in seismic zones.
viable construction material, it must soon will, develop a seismic design Essential to the success of this pro-
address issues that are constraining its technology that permits its intelligent gram is direction from the precast
use in seismic as well as nonseismic use as a construction technique. concrete industry. Initially, the direc-
areas. The major constraint facing the The National Science Foundation, tion must come in the form of ideas.
precast concrete industry today is the in conjunction with PCI and the Pre- Broad conceptual ideas about where
requirement that it comply with a cast Concrete Manufacturers' As- the precast concrete industry should
technology developed for cast-in- sociation of California (PCMAC), be in the 21st century must be
place concrete and especially those has recently agreed to fund the first developed. Specific questions that
provisions which control the design three years of a program entitled need to be addressed are:

-+, 15 TIES @ 4" O.C .


r f 4 TIES@ 4 • o.c.

";::>

" ~12-#11
#5 TIES @ 4• o.c. 17 @ 6" o.c. 42-111
- ~ fl-'-

Fig. 5. Ductile frame reinforcing (1989 vintage). Fig. 6. Boundary element for a shear wall (1989 vintage).

42 PCI JOURNAL
• How must precast concrete build- In order to effectively accomplish prototypical of what should become a
ings be erected if they are to be this task, manufacturers, constructors standard approach.
competitive? and engineers must first purge their The program was conceived and
• What precast concrete products are systems of all prejudices and per- developed in accordance with the fol-
most versatile and competitive? ceived constraints which could inhibit lowing processes:
the creative accomplishment of the 1. A need was perceived for high
• What production techniques will be aforementioned tasks. The National rise precast concrete buildings whose
used to manufacture these precast Institute of Standards and Technol- seismic resistance was to be provided
concrete products? ogy, under the direction of H. S. Lew entirely by ductile frames (shear wall
• What connector concepts stream- and Geraldine Cheok, has already free).
line production and erection? embarked on a program which is 2. Erection needs were developed

CUTAWAY VIEW

. ... . . ~ ...


.. -!f+!'""-:.,.;jt~~-~-.--
• A·,

. ':tttt· f"-1 N S ER T S

f~l:n~j··~·~~·~~-~~+GROUTED
r -STANDARD
JOINT

tt-tt.,..··.-:-''tf:-:"""~h::tttt~
.. :· ~~~~~~~~ s
tt-tt,:-..:-,~-'--..,1\'-.....;-tfii-'_ +-- SHIM AS REQ'D.
itft.~~~...:...;--ttlt:·.. ._____THREAOE
DOWEL
0

CONFINEMENT
ANGLE WITH ANCHORS
*lt:--""'--":-:...-,~':-ittt~ r- THIN METAL

-'--~-r----~
· _
• _. ,·,_~··-~·~~~~~~VEE T~EBAR
FILL WITH
GR OUT

DETAIL A OETAI L B DETAIL C


BEAM TO BEAM CONFINED AREA AT COLUMN TO COLUMN
PRECAST COLUMN

Fig. 7. Precast building system developed by Rockwin Corporation.

May-June 1990 43
after consultation with a group of in- L6X6 SIM . TO BELOW
dustry advisors. The consensus was W/ 2-1"e BOLTS IN
OVERSIZE HOLES
that the structure must be erected
much as a steel frame building is FIBER REINFORCED
today. Essential elements of this type NON-SHRINK GROUT
10, 000 PSI
of erection procedure are:
• A two-floor erection process. 4"e CORRUGATED METAL
DUCT W/ PT STRANDS
• Alignment capability after erection.
• Early integration of the final brac-
ing system into the construction
process so as to minimize tempo-
rary bracing costs and constraints.
3. Product versatility dictated:
• The use of rectangular components
for beams and columns.
• Prestressing was strongly recom-
mended to improve handling, con-
trol member deflection, and reduce
SHIM AS REQ'D
cost.
L6X6X1X1'-6" LONG
4. Connector concepts were iden- W/ 2-112" THICK
tified as: GUSSETS W/ 1"e BOLTS
@ 6" D.C. (3 TOTAL)
• A void extensive welding and the IN SLOTTED HOLES
TEMPORARY CORBELS TO
associated embedded hardware. BE REMOVED AFTER
STRANDS ARE STRESSED
• Incorporate adequate tolerances. EACH SIDE
• Avoid large formed wet joints. Fig. 8. Precast beam and column connected by post-tensioning.
• Design joints that minimize crane
time.
Many engineering details requiring Behavior at or near ultimate for the The introduction of strand as ten-
extensive welding or complex assem- precast concrete beam is crushing of sion reinforcement reduces or elimi-
bling procedures were proposed by the toe. This type of failure is charac- nates the bar buckling problem at the
panel members as yet unable to purge teristic of the post yield behavior of expense of producing higher com-
perceptions of probable joint per- cast-in-place joints. The failure is ini- pressive stresses in the concrete. Ul-
formance. The panel decided to at- tiated by cover spalling generated by timately, toe deterioration will always
tempt the 21st century design shown cyclic yielding (elongation) and be the limit state for a ductile moment
in Fig. 8 because it most closely com- buckling of the now overstrained connection. The compression/shear
plied with the manufacturing/con- compression reinforcement. This transfer mechanism in the toe must be
struction criterion previously de- spalling and toe degeneration is fur- dealt with in an imaginative way.
scribed. More imaginative details ther aggravated by the high level of A fiber reinforced epoxy grout
should and, it is hoped, will be ex- compression and shear transfer in this coupled with a strain limiting bearing
plored. An epoxy bonding (similar to region. pad cast in either the beam or the
that shown in Fig. 9) should not be
presumed unreasonable given the fact
that we plan to land a person on Mars.
A connection similar to that pro-
posed in the National Institute of v

Standards and Technology's program


was tested successfully by Dr. Robert
Park in New Zealand over 10 years
ago. Fig. 10 shows the type of con-
struction Dr. Park envisioned. A full
~--------~-11-~--~-~--------~
scale beam-column test program was
developed. The moment displace-
ment relationship (Fig. 11), though
not cycled through intermediate duc-
tilities, clearly indicates that a rea-
sonable level of ductility is available.
The behavior of a cast-in-place joint
is shown in Fig. 12 for comparison. Fig. 9. Precast beam and column connected by epoxy binder.

44 PC! JOURNAL
- .... - PRETENSIONED TENDONS AND/OR
NONPRESTRESSED REINFORCEMENT---

MORTAR JOINT~' /~MORTAR JOINT

~
c I
\. ~
~
. I

\_POST TENSIONED
TENDONS MIDSPAN

NOTE:: ONLY LONGITUDINAL STEEL


IN MEMBERS SHOWN
Fig. 10. Structural configuration for constructing continuous frames from precast concrete elements.

BEAM END DISPLACEMENT, INCHES


-14 -12 -10 -8 -6 -4 -2 0 2 4 6 8 10 12 14
I I I I I
NEGATIVE MOMENT AND DISPLACEMENT
CORRESPOND TO DOWNWARD LOAD AT
I
,; v ~
-~
160
l.._
1- 120
BEAM END
/jVI
UJ
UJ
LL.
a. 80 I
1-1
~
/ )
....:
zw
40

L v .~I~.
w
2:
0
2:
0
v v
.. .
(!)

....z
:I:
-40

-eo /
v .,-N
.___
~
2:
~
w -120
I .. ~4-3/8" DIA. STRANOS
m

-160
) . ..
0!0
I I ~3/8" DIA. STIRRUP

l
v .. ....- ..........
~2-12w/0 . 276" DIA

11 x 's
.. ..
~ I~
.,-N
luL!j

Fig. 11. Measured beam end displacement vs . beam plastic hinge moment.

May-June 1990 45
5 x's

60

30

U)
Q. td+l
H
~

u.i
0
u
a:
0
I.J...
8/d -2.31
-30 p •1.031
s •3.25"
d •13"
VELOCITY •0 . 1 IN. /SEC .

-60
-1.0 -.5 0 .5 1.0
STROKE, IN.
Fig. 12. Measured beam displacement vs. applied load.

column would better distribute the form slabs. Seismic bracing is ly required by U.S. codes must be
strain and thereby control concrete provided by a ductile frame. All reduced to a subassembly behavior
deterioration (Fig. 13). The develop- beams contribute to the seismic brac- criterion as it is in Japan. Compara-
ment of imaginative cures must take ing of the building. This bracing sys- tive subassembly tests are the only
precedence over determining the limit tem is designed to emulate cast-in- logical way to determine whether the
state of unimaginative load transfer place construction. Features that are yield level prescribed for cast-in-
concepts. significantly different from U.S. prac- place concrete is appropriate for
tice include the splicing of all column precast concrete construction.
bars immediately above the floor with New Zealand codes, for example,
World Experience mechanical splices. require certain precast concrete brac-
Precast concrete construction is not The technical justification for ing systems to be designed to a higher
only being used, but it is also being precast systems in Japan is provided yield (1.25x) level than comparable
promoted in Japan on high rise build- by test. Japanese contractors test full cast-in-place systems. Clearly, there
ings. The Japanese counterpart to the scale subassemblies to a prescribed has been more focus abroad on the
U.S. PRESSS program is charged loading sequence in order to establish development of precast concrete
with developing a national design that the level of component ductility building systems and design criteria
standard for precast concrete con- exceeds that which is required by the than has occurred in the U.S.
struction by 1992. This lack of a na- design criterion used. The ultimate The U.S. precast concrete industry
tional standard has not kept Japanese design strength for precast systems is must promote a performance type
contractors from using precast con- essentially the same as comparable design philosophy if it is at all inter-
crete. Taisei Construction Company cast-in-place systems. ested in the structural system market
uses what they call "layered construc- The design criterion in Japan ap- in regions where seismicity is a con-
tion" to reduce construction time. pears to accept a prescribed level of sideration. Boston, Massachusetts,
This system consists of precast subassembly ductility as proof that and St. Louis, Missouri, are only two
columns, and a column joint shell sufficient building ductility exists. examples of places which now re-
developed so that it can receive a The equivalence of building "duc- quire seismic considerations. It is ex-
solid beam which in turn supports tility and energy absorption" current- pected that many other areas of the

46 PCIJOURNAL
_ ~ FIBRE REINFORCED
ELASTOMERIC L_GROUT
BEARING PAD

IN SITU CONCRETE

BONDED P/T STRAND

Fig. 13. Post-tensioned ductile beam-column connection.

(a) FLOOR SLAB BARS CONNECTED BY


OVERLAPPING LOOPS
(VERTICAL BAAS NOT SHOWN)

IN SITU CONCRETE

Fig. 14. Horizontal bars connected by overlapping loops.

(b) FLOOR SLAB BAAS CONNECTED BY WELDING


(VERTICAL BAAS NOT SHOWN)

aL !IECTIOII IHI

(c) POSSIBLE METHOD OF CONNECTING


VERTICAL BAAS

Fig. 16. Typical horizontal joints between prefabricated large


Fig. 15. Horizontal bars connected by welding. panels.

May-June 1990 47
BOLTED STEEL
HiiH STRENGTH GROUT OUTLET TUBE COUPLING ELEMENT
FOAM PLASTIC COLLAR
INLET TUBE
DRY PACK MORT

PLASTIC BEARING STRIP


(a) (b)

Fig. 17. Horizontal joints for prefabricated wall panels (hollow-core slab floor systems).

United States will require such wall panels for high rise construction more ductility than a wall which is
provisions. in seismic regions is impossible given over-reinforced by large boundary
the design constraints of current elements.
codes. The principal obstacles are: The connectivity of precast panels
The U.S. Scene • Boundary elements (Fig. 6)3 are re- has been studied in many countries
The U.S. construction industry quired when PulA+ Mu IS> 0.2 f~ which recognize the economic need
needs a viable precast concrete in- (always the case). for precast concrete residential build-
dustry if it is to meet the needs of so- • Two curtains of steel are re~red ings. The key to innovation in panel
ciety. Interest in the precast concrete in shear walls 3 when Vu > 2 --Jj(. construction, assuming that the
research necessary to establish a vi- The new masonry code ( 1988 design hangups of the preceding para-
able precast concrete industry is in- UBC, Chapter 24)3 does not require graph can be solved, lie in the devel-
creasing, but the application of this boundary elements, nor does it pre- opment of connectors which are ef-
research currently awaits code ap- scribe an arbitrary limit for single cur- fective from a cost and engineering
provals. tain shear reinforcement. The mason- perspective. Connections such as
Precast panel high rise construc- ry industry was able to establish by those shown in Figs. 14 through 17
tion, for example, should supply a test, as the concrete industry and the are suggested in the literature and
significant portion of our residential precast concrete industry could, that should get the job done, but the result-
needs. Marketing precast concrete distributed reinforcement provides ing system is probably not affordable.
What are the innovative concepts in
large panel construction that require
development? The transfer of flexural
capacity requires continuity of verti-
PRE LOAD cal reinforcement. Vertical post-
tensioning is an obvious candidate as
are coupled threaded bars. Post-
&ROUTED JOINT tensioning systems utilizing strand
SPACE---...
should have a decided advantage
since the introduction of any rigid bar
0 or connector in the end of a thin panel
CD
APPLIED ....
([) will undoubtedly promote toe failure
SHEAR LOAD and, as a consequence, reduce the
strength and ductility of the system.
The viability of distributed boundary
reinforcement must be established.
Shear transfer along horizontal and
vertical joints must be provided. Most
recently, shear transfer was studied
by Foerster, Rizkalla and Heuvel. 4
THICKNESS • 200 mm 25.4 mm • 1 inch The specimens were tested as shown
in Fig. 18. Sliding friction along an
Fig. 18. Specimen configuration for shear transfer test program. unreinforced joint subjected to a con-

48 PCI JOURNAL
improve joint performance. Strain
controlling bearing pads might also
1600 APPLIED COMPRESSIVE 290 0 SP 11 be the answer to the toe failure
STRESS 580 e SP 21 mechanism.
1400
Shear wall reinforcement concepts
1200 and continuity requirements devel-
oped for cast-in-place concrete need
z 1000 700 psi to be discarded and replaced by con-
~ cepts which are appropriate for
0 800 precasting.
< 500 psi
0 The most encouraging step toward
...J 600 developing a viable precast concrete
structural system is the initial phase
400 of the NIST program discussed pre-
200 25.4 1111 • 1 inch viously. The test program was devel-
1 kN • 0 . 225 kips oped with a stated goal of demon-
0 strating and comparing "equivalent
-2 2 6 10 14 22 ductility and energy absorption" of
DISPLACEMENT (mm) comparable cast-in-place concrete
subassemblies and precast assemblies
Fig. 19. Load-displacement relationship for smooth joint. connected as shown in Fig. 8. The
beam/column assemblies were devel-
oped from actual designs of a 15-
stant compression is higher than one percent but post-slip shear transfer by story structure located in Seismic
might expect [85 percent of the ap- only 20 percent. Keyed joints seem Zone 4 (Fig. 21).
plied compressive load (Fig. 19)]. hardly worth the effort especially if, The results of these initial tests will
Whether or not this can be translated as is the usual case, a floor system soon be available,5 but the encourag-
into a shear transfer criterion for the must interrupt panel continuity (Figs. ing aspect is that the precast concrete
compression region of flexing panel 16 and 17). system was able to sustain larger dis-
needs to be established. Interestingly, Room for innovation exists. Ad- placements and displacement duc-
a keyed joint (Fig. 20) increased the hesive grouts or grouts which allow tilities than their cast-in-place compa-
pre-slip shear transfer by about 50 for controlled deformability should rables. Load-displacement curves for

IN SITU CONCRETE
PROTRUDING STEEL

WALL PANEL
DIAGONAL STRUT
(b) PLAN SECTION

en
en CASTELLATED JOINT
~
l-
en
~
UJ
:I:
en
(a) ELEVATIONS
SHEAR SLIP
(NOTE: REINFORCING BARS NOT SHOWN
-SEE PLAN SECTION)
(c) TYPICAL SHEAR STRESS-SHEAR SLIP
RELATION FOR MONOTONIC LOADING
Fig. 20. Typical castellated joint between prefabricated large panels.

May-June 1990 49
Loading direction
North-South
l

8
r
r-A L ~ 32.

16" ® ®
j_
L t
-A 26"

8 l
41 3/4"
(37") •

47 3/4"
(43").
_j .
1" Post-tensioning bar
1-112" Corrugated duct

8- #3,
9-13 -V'"i w [0 ·--4-#4
Top & Bottom

0.207" smih. wire ~


8 - 0.207"
@ 3 1/3" O.C. smth. wire

0.207" smth. wire


5- 13
2- #4
- ~- ,.,?,
@ 1 1/3" O.C.

MONOUTHIC POST-TENSIONED
• Numbers in parenthesis are for
the post-tensioned specimens. SECTION A-A SECTION B-B

Fig. 21. Test specimen for ductile frame (NIST program).

66.0

39.6 45

'[ 13.2 Cii' 15


a.
;g, ;g.
0 0
~
c(
g -13.2 ...J -15

-39.6 -45

-66.0 -75 '-=.._......jl......<:..L.:...._ _....u...._ ___._ _ _..___ ___.

-2.10 -1.26 -0.42 0 .42 1.26 2.10 -1.75 -0.85 -0.05 0.95 1.85 2.75

DISPLACEMENT (inches) DISPLACEMENT (inches)

Fig. 22. Load-displacement curves (cast-in-place joint). Fig. 23. Load-displacement curves (precast joint).

50 PCIJOURNAL
the two subassemblies are shown in Innovation is synonymous with REFERENCES
Figs. 22 and 23. precast concrete. Given some lati-
The precast concrete system was tude, precasters will surely develop 1. Englekirk, R. E., "Towards a More Effec-
also capable of sustaining signifi- innovative systems. It remains then to tive Use of Precast Concrete Cladding,"
cantly more cycles to failure than the be able to establish a technology Proceedings, Architectural Precast Con-
cast-in-place specimen. Consequent- which promotes this innovation. crete Cladding - Its Contribution to
Lateral Resistance of Buildings, Precast/
ly, the total energy absorbed, despite Prestressed Concrete Institute, Chicago,
the pinching of the precast beam hys- IL, 1990,pp. 4-13.
teresis loops, was equivalent. Many Conclusion 2. Englekirk, R. E., "An Analytical Ap-
more specimens will be tested in this Precast concrete buildings can and proach to Establishing the Seismic Resis-
program so we should not rush to should be constructed in seismic tance Available in Precast Concrete
Frame Structures," PCI JOURNAL, V.
judgment, but rather be encouraged to areas. A technology compatible with 34, No. l, January-February 1989, pp.
try new concepts. precast concrete construction needs 92-101.
Industry leaders continue to ad- must be developed. This can be ac- 3. Uniform Building Code, Section 2625
vance the innovative use of precast complished only if constructors and (f), International Conference of Building
precasters take an active, open Officials, Whittier, CA, 1985.
concrete. Lloyd Compton of L.A.
4. Foerster, H. R., Rizkalla, S. H., and
Compton Group is in the process of minded, and yet stubborn part in the Heuvel, J. S., "Behavior and Design of
developing a ductile fascia panel to be development of forthcoming research Shear Connections for Loadbearing Wall
used to brace midrise (4 to 6 story) programs. The thrust must be to Panels" PCI JOURNAL, V. 34, No. 1,
buildings. The concept is developed develop imaginative systems that im- January-February 1989, pp. 102-119.
prove performance and solve prob- 5. Cheok, Geraldine S., and Lew, H. S.,
about an adjustable casting capable of
"Seismic Performance of 1;3 Scale Post-
dealing with the tolerances which lems as opposed to merely establish- Tensioned Precast Beam-Column Con-
must be provided for in precast con- ing limit states for poor design con- nections;· : to be submitted to the PCI
crete construction. cepts. JOURNAL for publication consideration.

May-June 1990 51

Вам также может понравиться