Академический Документы
Профессиональный Документы
Культура Документы
INTRODUCTION
Sheet pile walls are retaining walls constructed to retain earth, water or any other fill
material
These walls are thinner in section as compared to masonry walls
A sheet pile wall consist of a series of sheet piles driven side by side into the ground, thus
forming a continuous vertical wall for the purpose of retaining an earth bank
Example Want to build a structure in the sea waterfront structures we can use sheet piles
to retain sea water from flowing to the required area, and then withdraw the water confined
between sheet piles and thereby build the required structures, finally remove sheet piles
because there functions were end
2. USES
Water front structures, for example, in building wharfs, quays, and piers
Building diversion dams, such as cofferdams
River bank protection
Retaining the sides of cuts made in earth
Temporary construction
Light weight construction where sub-soil is poor for supporting a retaining wall.
Timber
•Timber sheet piling is used for short spans, light lateral loads, and commonly for temporary
structures in the form of braced sheeting.
•Wooden sheet piles may be considered permanent if they are permanently under water,or if they
are impregnated with preservatives.
•They are heavy and bulky, and require heavier equipment to drive and handle.
Steel
•Steel sheet piling is the most common type because it is resistant to high diving stresses, light
weight, can be used several times, long service, easier to increase the pile length.
4 ADVANTAGES
6. TYPES
Cantilever sheet piling
Anchored sheet piling
The sequence of construction for a backfilled structure is as follows (see Figure 3):
Dredge the in situ soil in front and back of the proposed structure.
Drive the sheet piles.
Backfill up to the level of the anchor, and place the anchor system.
Backfill up to the top of the wall.
For a cantilever type of wall, only Steps 1, 2, and 4 apply
(a) (b)
Figure 3: Sequence of construction fora (a) backfilled structure (b) dredged structure
The sequence of construction for a dredged structure is as follows (see Figure 9.6):
Drive the sheet piles.
Backfill up to the anchor level, and place the anchor system.
Backfill up to the top of the wall.
Dredge the front side of the wall.
With cantilever sheet pile walls, Step 2 is not required.