Wika Realty)
Ds. Puhu, Payangan, Ubud – Bali
Earthwork & Retaining wall
1. Site Preparation
1.1. Setting out work
The setting out work are an examine the situation and conditions at the site by using The
measuring instrument (TOPCON Total Station ) and is expected to produce technically
good drawing ( situation ) of the coordinates and elevation applied or plotted in the form of
working drawings.The measurement results data can also be as a reference in the payment
of achievement of work performed under the terms of the Project contract.
2.1. Site clearance of vegetation, loose rubbish and debris and remove from site
This work involve removal any Vegetation and debris at work area. Implementation of this
work include remove any Vegatation, loose rubbish and debris from site
The Equipment used in this work are
a. Excavator
b. Dump truk
2.4. Filling of excavated material in bulk in the open to form platforms including
compaction.
This work involve filling results of soil excavated and compacted to 90% of original soil
density.
Drilling Process
surface preparation
Before the spraying work, surface slope or field that needs to be cleaned. The
surface to be given a inject shotcrete need to be cleaned to a thickness shotcrete.
Construction of drainage on slopes At the lower end of the slope should be given
as a slope drainage channels drain water from the surrounding slopes. Slope
drainage systems need to be separated from the existing drainage system should
be designed separately.
Installation of wire mesh
Wire mesh which is the reinforcement of the shotcrete must be tied with a nail that
is attached to the slope field and the wire must be tied with concrete decking.
Surface shotcrete
o Setting the thickness of the shotcrete Shotcrete generally has a thickness
of about 75-100 mm. In practical use measuring stick.
o Placement or spraying shotcrete Shotcrete placement is done from the
bottom up to prevent excessive rebound. Nozzle sprays directed at the
work field up to a thickness of plans and conducted perpendicular
rebounds minimum and maximum density obtained. Reinforcement must
Anantara Ubud (PT. Wika Realty)
Ds. Puhu, Payangan, Ubud – Bali
Earthwork & Retaining wall
Ilustration Retaining wall Excavation and Remove to stock pile / Fill area
4.7. Rainforcement
This is part of the structure work. This work an important thing in the implementation of the
quality aspects of concrete work. Considering the reinforcement important function in the
strengh building structure
Rainforcement work.
iron should be clean of oil or sludge
The reinforcement installation should be arranged, so that there is still space available
for compaction concrete
If Rebar must be connected there should be an overlap in accordance with
specifications defined calculation or
The Rainfocement work can also be assembled outside before input into the concrete
formwork.
Anantara Ubud (PT. Wika Realty)
Ds. Puhu, Payangan, Ubud – Bali
Earthwork & Retaining wall
4.8. Formwork
o Material measure
o Hand tool
Anantara Ubud (PT. Wika Realty)
Ds. Puhu, Payangan, Ubud – Bali
Earthwork & Retaining wall
Anantara Ubud (PT. Wika Realty)
Ds. Puhu, Payangan, Ubud – Bali
Earthwork & Retaining wall
7. STORMWATER DRAINAGE
7.1. Excavation from existing ground level
This work involve the removal soil excavate to fill / stock pile area which determined by the
direction or owner
To work under the foundation floor is made with a thickness according to plan.
Create mortar to the floor working with a mixture of mortar 1pc: 3Psr: 5Krl or B-0.
Make sure that the location will be installed lean concrete already are working with the
thickness of the sand is according to plan and has leveled.
Clean the locations that will be installed floorspace of garbage or dirt. Install the wooden
peg and floor leveling work needed as a reference to determine the thickness. Pouring
Lean concrete mixture through a working floor area to cast gutter or bucket to the lean
concrete elevation by using a hand tool.