ID Task Name Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

31 1 2 3 4 5 6 7 8 9 1011 12131415161718192021 22232425 2627282930 1 2 3 4 5 6 7 8 9 1011


1 DRILLING OF ADDITIONAL BOREHOLE IN GUMSURI, 29 days
REHABILITATION OF GUMSURI-DAMBOA WATER PIPELINE AND
SOLARIZATION OF DAMBOA RESERVIOR WATER SUPPLY SYSTEM
AT DAMBOA, DAMBOA LGA, BORNO STATE

2 SITE MOBILISATION/DEMOBILISATION 3 days


3 SITE LAYOUT 2 days
4 DRILLING OF SHALLOW AQUIFER BOREHOLE 11 days
5 GEOPHYSICAL SURVEY 1 day
6 DRILLING OF BOREHOLE 2 days
7 PIPE WORK 2 days
8 BOREHOLE DEVELOPMENT 1 day
9 PUMPING TEST 2 days
10 PLACEMENT OF GRAVELS 1 day
11 WATER QUALITY TEST 1 day
12 WELL HEAD INSTALLATION 1 day
13 SOLAR PUMP INSTALLATION 3 days
14 SECURITY FENCING 4 days
15 FETCHING POINTS AT GUMSURI 2 days
16 REHABILITATION OF GUMSURI-DAMBOA PIPELINE 25 days
17 EXCAVATION 14 days
18 PIPE REPLACEMENT 21 days
19 ADDITIONAL REPAIRE WORKS 7 days
20 BACKFILLING 7 days
21 PROTECTION OF EXPOSED PIPES 7 days
22 ANIMAL WATER TROUGH AND CONCRETE WORKS 12 days
23 FETCHING POINTS AT DAMBOA TOWN 4 days
24 SOLARIZATION (HYBRID SYTSEM) OF DAMBOA WATER SUPPLY 5 days
NETWORK

25 CHLORINATION SYSTEM, WATER TREATMENT AND 2 days


ASSOCIATED WORKS AT DAMBOA RESERVOIR

26 SITE CLEANING 1 day


27 SITE HAND OVER 1 day

Page 1