Abstract - Contractor selection is a strategic question of decision makers, information available, among
for the construction industry since the suppliers have an others.
important role in projects performance. Two essential issues Therefore, this paper proposed a contractor selection
in this process are the choice of adequate criteria and model in the construction industry. Therefore, it was
methods of supplier's evaluation. Therefore, this paper organized as follows: Section 2 gives a systematic review
proposes a model for contractor selection in the construction
of contractor selection criteria in the construction
industry. Normally, this selection is considering a group
decision problem, since various departments are influenced industry. Section 3 describes the model proposed and
for this choice and its managers participate of the process. Section 4 presents a numerical application. Finally,
Moreover, this paper focuses on the situation in which the Section 5 gives the final considerations of this research.
company wants to select a set of contractors, maximizing the
use of resources according with the constraints imposed. In
this context, the model proposed considers the interaction II. CONTRACTOR SELECTION CRITERIA
between a Group Decision and an Integer Programming
methods. Afterward, it was made a numerical application of Selecting the right contractor for a project is a critical
the proposed model. The criteria used in this simulation challenge for any construction company [3]. This
were identified from a literature review in papers related to selection is considered a decision-making problem that
the supplier's selection in the construction industry.
involves several aspects, including the sector of
Keywords – Construction industry, Contractor selection,
application, number of decision makers, selection criteria,
Group decision aid and selection methods. In this context, it is essential
employing criteria according with the real needs of the
company in order to contract suppliers that help the
I. INTRODUCTION enterprise to achieve its goals.
In this sense, this section presents the criteria used in
The selection of a capable contractor is essential to the stages of prequalification and final selection in
the good performance of any construction project [1], contractor selection in the construction industry. For this
since they are responsible by core activities in the process. purpose, it was made a Systematic Review to identify
In addition, selecting suitable suppliers significantly them. To found relevant articles in this area, research was
reduces material purchasing cost, improves the conducted in five academic databases: Web of Science,
competitiveness of businesses, increases flexibility and Science Direct, Scopus, Springer Link and Wiley Online
product quality and helps with speeding up the process of Library. Combinations of the following keywords are
material purchasing [2]. made to filter papers related with the theme: Construction,
In this way, according with [3], this process should Contractor Selection, Supplier Selection, Project,
detect a supplier to whom the customer can entrust the Industry, and Contract. The articles are select and
responsibility to perform the project adequately. In this examine according with the steps identified by [8] to
context, the selection criteria are very important for the Literature Review.
decision making, since which are strictly related with the
objectives of the client in relation to the contractor. If the A. Prequalification Criteria
criteria are wrong, the contractor selected may not be
according with the client needs, even if the role decision Contractor prequalification is performed to minimize
process is carried out in the right way. the risks and failures and to improve the performance
Normally, it is necessary the use of various criteria to levels of chosen contractors in order to establishing
achieve the companies’ goals ([4]; [5]) and it is necessary minimal capacities below which contractors will not be
to determine their relative importance [6]. Because of this, considered [9]. Due the importance of this stage, some
this process is a complex multicriteria problem in which authors focus in this phase in their papers. Only
various decision makers (DMs) evaluate the contractors’ prequalification criteria cited by two or more authors were
attributes to deliver the project considering numerous named in this subsection.
decision criteria [7]. Furthermore, the method of selection It was observed that the price criteria, that was
is strictly important to the successful choice and depends considered an essential issue in the past and sometimes
on the kind of criteria (qualitative or quantitative), number was the unique criteria of selection, principally by public
companies, did not appears in these papers, which 5) Experience in similar jobs (C5): it observes if the
demonstrate a change of vision of enterprises, that contractor works with similar projects before.
consider most important question like financial status 6) Quality (C6): Is the capacity of supply goods and
([10]; [11]) and financial stability ([12]; [13]) than the services according with the standards specifications to
simple price of bid. Additionally, it identified that the satisfy the client’s needs.
most part of criteria are related with organizational In this case, the aspects of cost, quality and time of
questions: responsiveness, responsibility, competency project are observed in the selection process.
([9]; [14]), reputation ([11]; [12]) and Health & Safety
policy ([11]; [15]; [16]). Finally, [11] and [13] cited
experience like prequalification criteria. III. PROPOSED SYSTEMATIC
B. Final Selection Criteria The proposed systematic is shown in Fig. 1. The first
phase is the identification of actors that influences this
A total of 25 articles mentioning selection criteria to process. In several situations, a unique DM, that knows
construction industry are listed in Table I. Only criteria the preferences and limits of others actors, is selected. In
mentioned by at least four authors are cited in the table. cases where there are higher divergences between
On the contrary of the idea of selection contractors based decision maker's preferences, it is necessary the use of
in only one criterion, mainly the price bid, the literature group decision procedures. This article considers the
shows that the contractor selection is considered a second option. In this way, it is should create a committee
multicriteria decision problem ([16]; [17]). In this context, of decision makers familiarized with the company's needs.
all the studied articles consider various criteria to the The number of decision makers and the area of operation
selection process. vary according with the type and size of the industry.
TABLE I
CONTRACTOR QUALIFICATION CRITERIA Creation of Committee
[1]; [2]; [3]; [7]; [10]; [17]; [18]; [19]; Order – qualifying
Price [20]; [21]; [22]; [23]; [24]; [25]; [26]; Contractor Pre-selection
criteria
[27]; [28]; [29].
Financial status [3]; [16]; [17]; [18]; [26]; [30].
Financial stability [1]; [7]; [30]; [31]. Did contractor
approve?
[1]; [3]; [17]; [20]; [22]; [23]; [25];
Duration
[26]; [27].
Management capability [3]; [7]; [27]; [30]; [31]; [32]. Yes
[1]; [3]; [7]; [16]; [18]; [20]; [21]; [27]; Order – winning Application of model with
Health and safety
[29]; [30]; [31]; [32]; [33]. criteria multiple decision makers
Reputation [2]; [20]; [31]; [32]; [34].
Technical capability [3]; [7]; [28]; [31].
Experience in similar jobs [1]; [3]; [16]; [17]; [20]; [25]; [26]; Ranking of Contractors
[33].
Experience [18]; [21]; [30]; [33]; [34].
Past Project Performance [17]; [20]; [25]; [27]; [28]; [29]; [30]; Application of an Integer
[32]; [34]. Restrictions Programming Method
[2]; [18]; [20]; [21]; [22]; [23]; [28];
Quality
[35].
Contractor Selection
Therefore, the most cited selection criteria in the Fig. 1. Proposed Systematic
literature review were:
1) Price (C1): is the numerical monetary expression Then, the committee should identify the potential
relative to a good transitioned in the market. contractors, which represents the alternatives in the
2) Health and safety (C2): is related with the proposed decision model. Later, the order-qualifying and
standards and norms of health and safety in the order winning criteria are firm. To determine them, each
organization, as well as educational actions, conscientious individual can establish your own criteria and, after, the
campaigns, among others. group meets to discuss the proposals and determines the
3) Past Project Performance (C3): is related with set of global criteria. In other cases, it can make a
the performance of the contractor in project finalized, brainstorming section or uses a literature review to
according with the owners and managers of its. identify the criteria.
4) Duration (C4): is measured by the time spent to In the pre-selection phase, a screening of contractors
deliver a product or project executed to the client. is held. In this way, the alternatives that have a
performance below the acceptable in the order-qualifying accordance with this preference. The criteria used in this
criteria are eliminated and those who obtain a simulation were exposed in sections II.A (pre-selection)
performance level specified continue to compete in the and II.B (selection).
process. Afterward, it was made the contractors pre-selection
Later, a model with multiple decision makers was from their performance in order-qualifying criteria. In
applied. In this case, the method used was PROMETHEE- this phase, the members of committee achieve accordance
GDSS, which make the ordering of the alternatives. The in respect of the supplier's evaluation regarding the
use of this method is related to several aspects. criteria, since in this phase it is observed if the alternatives
Primarily, due to "present non-compensatory have a minimum acceptable performance in respect to
evaluations” [36], this method avoid that contractors with them, while performances above the qualifier level do not
high performance in some criteria and very low interfere in the final selection. In this stage the potential
performance in others to be chosen, since in the contractor contractors Co4, Co6, Co7 and Co10 obtained performances
selection it is normally preferred suppliers with good lower than the qualifier level and were removed to the
balanced performance. Additionally, the interaction process.
between the analyst and managers are easy since the After the definition of the contractors that continue in
parameters are very intuitive. Also, this is a flexible the process, it was construct individuals evaluation matrix
model [37] in relation to the parameters used in the in which were generated the entries of the decision model.
process, which facilitates the elucidation of preferences Following, each decision makers determined the weights,
by the managers. preference functions and parameters for each criterion.
Secondly, PROMETHEE GDSS permits the Moreover, the committee decided that the weight of each
consideration of preferences of all the decision makers decision maker was the same since anyone have more
without needs a consensus, which facilitates the process in power than the others. Using the PROMETHEE.GAIA
cases of interest conflicts. Furthermore, the method software, the PROMETHEE GDSS was applied. The
admits the attribution of weights to the decision makers so global ranking is exposed in Table 2.
that the power of each individual in relation to the process
is portrayed. The result of the application of this method TABLE 2
GLOBAL RANKING
is a ranking of contractors.
In the final selection, to select a set of suppliers it Order Alternative Net flow
uses an Integer Programming method. In this case, it was 1º Co1 0.4397
employed PROMETHEE V adaptation, proposed by [38],
2º Co8 0.2313
which aims to insert all the alternatives that improve this
set, including those that have negative flows. In this 3º Co9 0.1257
method, the resources constraints are considered to 4º Co3 -0.0683
choose the group of suppliers in the final selection, since 5º Co2 -0.3393
the company’s normally have a limited amount of
6º Co5 -0.3890
resources to achieve their objectives.