Вы находитесь на странице: 1из 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/302480179

Contractor selection in construction industry: A multicriteria model

Conference Paper · December 2015


DOI: 10.1109/IEEM.2015.7385701

CITATIONS READS

3 1,650

3 authors, including:

Maria Creuza Borges De Araújo Caroline Maria de Miranda Mota


Federal University of Pernambuco Federal University of Pernambuco
9 PUBLICATIONS   44 CITATIONS    50 PUBLICATIONS   495 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Modelo multicritério para avaliação e gestão de projetos em desenvolvimento nas organizações View project

All content following this page was uploaded by Maria Creuza Borges De Araújo on 10 July 2016.

The user has requested enhancement of the downloaded file.


Contractor Selection in Construction Industry: a Multicriteria Model

M. C. B. Araújo, L. H. Alencar, C. M. M. Mota


Department of Management Engineering, Universidade Federal de Pernambuco, Recife, Brazil
(mariacreuzaborges@yahoo.com.br)

Abstract - Contractor selection is a strategic question of decision makers, information available, among
for the construction industry since the suppliers have an others.
important role in projects performance. Two essential issues Therefore, this paper proposed a contractor selection
in this process are the choice of adequate criteria and model in the construction industry. Therefore, it was
methods of supplier's evaluation. Therefore, this paper organized as follows: Section 2 gives a systematic review
proposes a model for contractor selection in the construction
of contractor selection criteria in the construction
industry. Normally, this selection is considering a group
decision problem, since various departments are influenced industry. Section 3 describes the model proposed and
for this choice and its managers participate of the process. Section 4 presents a numerical application. Finally,
Moreover, this paper focuses on the situation in which the Section 5 gives the final considerations of this research.
company wants to select a set of contractors, maximizing the
use of resources according with the constraints imposed. In
this context, the model proposed considers the interaction II. CONTRACTOR SELECTION CRITERIA
between a Group Decision and an Integer Programming
methods. Afterward, it was made a numerical application of Selecting the right contractor for a project is a critical
the proposed model. The criteria used in this simulation challenge for any construction company [3]. This
were identified from a literature review in papers related to selection is considered a decision-making problem that
the supplier's selection in the construction industry.
involves several aspects, including the sector of
Keywords – Construction industry, Contractor selection,
application, number of decision makers, selection criteria,
Group decision aid and selection methods. In this context, it is essential
employing criteria according with the real needs of the
company in order to contract suppliers that help the
I. INTRODUCTION enterprise to achieve its goals.
In this sense, this section presents the criteria used in
The selection of a capable contractor is essential to the stages of prequalification and final selection in
the good performance of any construction project [1], contractor selection in the construction industry. For this
since they are responsible by core activities in the process. purpose, it was made a Systematic Review to identify
In addition, selecting suitable suppliers significantly them. To found relevant articles in this area, research was
reduces material purchasing cost, improves the conducted in five academic databases: Web of Science,
competitiveness of businesses, increases flexibility and Science Direct, Scopus, Springer Link and Wiley Online
product quality and helps with speeding up the process of Library. Combinations of the following keywords are
material purchasing [2]. made to filter papers related with the theme: Construction,
In this way, according with [3], this process should Contractor Selection, Supplier Selection, Project,
detect a supplier to whom the customer can entrust the Industry, and Contract. The articles are select and
responsibility to perform the project adequately. In this examine according with the steps identified by [8] to
context, the selection criteria are very important for the Literature Review.
decision making, since which are strictly related with the
objectives of the client in relation to the contractor. If the A. Prequalification Criteria
criteria are wrong, the contractor selected may not be
according with the client needs, even if the role decision Contractor prequalification is performed to minimize
process is carried out in the right way. the risks and failures and to improve the performance
Normally, it is necessary the use of various criteria to levels of chosen contractors in order to establishing
achieve the companies’ goals ([4]; [5]) and it is necessary minimal capacities below which contractors will not be
to determine their relative importance [6]. Because of this, considered [9]. Due the importance of this stage, some
this process is a complex multicriteria problem in which authors focus in this phase in their papers. Only
various decision makers (DMs) evaluate the contractors’ prequalification criteria cited by two or more authors were
attributes to deliver the project considering numerous named in this subsection.
decision criteria [7]. Furthermore, the method of selection It was observed that the price criteria, that was
is strictly important to the successful choice and depends considered an essential issue in the past and sometimes
on the kind of criteria (qualitative or quantitative), number was the unique criteria of selection, principally by public
companies, did not appears in these papers, which 5) Experience in similar jobs (C5): it observes if the
demonstrate a change of vision of enterprises, that contractor works with similar projects before.
consider most important question like financial status 6) Quality (C6): Is the capacity of supply goods and
([10]; [11]) and financial stability ([12]; [13]) than the services according with the standards specifications to
simple price of bid. Additionally, it identified that the satisfy the client’s needs.
most part of criteria are related with organizational In this case, the aspects of cost, quality and time of
questions: responsiveness, responsibility, competency project are observed in the selection process.
([9]; [14]), reputation ([11]; [12]) and Health & Safety
policy ([11]; [15]; [16]). Finally, [11] and [13] cited
experience like prequalification criteria. III. PROPOSED SYSTEMATIC

B. Final Selection Criteria The proposed systematic is shown in Fig. 1. The first
phase is the identification of actors that influences this
A total of 25 articles mentioning selection criteria to process. In several situations, a unique DM, that knows
construction industry are listed in Table I. Only criteria the preferences and limits of others actors, is selected. In
mentioned by at least four authors are cited in the table. cases where there are higher divergences between
On the contrary of the idea of selection contractors based decision maker's preferences, it is necessary the use of
in only one criterion, mainly the price bid, the literature group decision procedures. This article considers the
shows that the contractor selection is considered a second option. In this way, it is should create a committee
multicriteria decision problem ([16]; [17]). In this context, of decision makers familiarized with the company's needs.
all the studied articles consider various criteria to the The number of decision makers and the area of operation
selection process. vary according with the type and size of the industry.

TABLE I
CONTRACTOR QUALIFICATION CRITERIA Creation of Committee

Criterion Article Identification of Contractors

[1]; [2]; [3]; [7]; [10]; [17]; [18]; [19]; Order – qualifying
Price [20]; [21]; [22]; [23]; [24]; [25]; [26]; Contractor Pre-selection
criteria
[27]; [28]; [29].
Financial status [3]; [16]; [17]; [18]; [26]; [30].
Financial stability [1]; [7]; [30]; [31]. Did contractor
approve?
[1]; [3]; [17]; [20]; [22]; [23]; [25];
Duration
[26]; [27].
Management capability [3]; [7]; [27]; [30]; [31]; [32]. Yes
[1]; [3]; [7]; [16]; [18]; [20]; [21]; [27]; Order – winning Application of model with
Health and safety
[29]; [30]; [31]; [32]; [33]. criteria multiple decision makers
Reputation [2]; [20]; [31]; [32]; [34].
Technical capability [3]; [7]; [28]; [31].
Experience in similar jobs [1]; [3]; [16]; [17]; [20]; [25]; [26]; Ranking of Contractors
[33].
Experience [18]; [21]; [30]; [33]; [34].
Past Project Performance [17]; [20]; [25]; [27]; [28]; [29]; [30]; Application of an Integer
[32]; [34]. Restrictions Programming Method
[2]; [18]; [20]; [21]; [22]; [23]; [28];
Quality
[35].
Contractor Selection

Therefore, the most cited selection criteria in the Fig. 1. Proposed Systematic
literature review were:
1) Price (C1): is the numerical monetary expression Then, the committee should identify the potential
relative to a good transitioned in the market. contractors, which represents the alternatives in the
2) Health and safety (C2): is related with the proposed decision model. Later, the order-qualifying and
standards and norms of health and safety in the order winning criteria are firm. To determine them, each
organization, as well as educational actions, conscientious individual can establish your own criteria and, after, the
campaigns, among others. group meets to discuss the proposals and determines the
3) Past Project Performance (C3): is related with set of global criteria. In other cases, it can make a
the performance of the contractor in project finalized, brainstorming section or uses a literature review to
according with the owners and managers of its. identify the criteria.
4) Duration (C4): is measured by the time spent to In the pre-selection phase, a screening of contractors
deliver a product or project executed to the client. is held. In this way, the alternatives that have a
performance below the acceptable in the order-qualifying accordance with this preference. The criteria used in this
criteria are eliminated and those who obtain a simulation were exposed in sections II.A (pre-selection)
performance level specified continue to compete in the and II.B (selection).
process. Afterward, it was made the contractors pre-selection
Later, a model with multiple decision makers was from their performance in order-qualifying criteria. In
applied. In this case, the method used was PROMETHEE- this phase, the members of committee achieve accordance
GDSS, which make the ordering of the alternatives. The in respect of the supplier's evaluation regarding the
use of this method is related to several aspects. criteria, since in this phase it is observed if the alternatives
Primarily, due to "present non-compensatory have a minimum acceptable performance in respect to
evaluations” [36], this method avoid that contractors with them, while performances above the qualifier level do not
high performance in some criteria and very low interfere in the final selection. In this stage the potential
performance in others to be chosen, since in the contractor contractors Co4, Co6, Co7 and Co10 obtained performances
selection it is normally preferred suppliers with good lower than the qualifier level and were removed to the
balanced performance. Additionally, the interaction process.
between the analyst and managers are easy since the After the definition of the contractors that continue in
parameters are very intuitive. Also, this is a flexible the process, it was construct individuals evaluation matrix
model [37] in relation to the parameters used in the in which were generated the entries of the decision model.
process, which facilitates the elucidation of preferences Following, each decision makers determined the weights,
by the managers. preference functions and parameters for each criterion.
Secondly, PROMETHEE GDSS permits the Moreover, the committee decided that the weight of each
consideration of preferences of all the decision makers decision maker was the same since anyone have more
without needs a consensus, which facilitates the process in power than the others. Using the PROMETHEE.GAIA
cases of interest conflicts. Furthermore, the method software, the PROMETHEE GDSS was applied. The
admits the attribution of weights to the decision makers so global ranking is exposed in Table 2.
that the power of each individual in relation to the process
is portrayed. The result of the application of this method TABLE 2
GLOBAL RANKING
is a ranking of contractors.
In the final selection, to select a set of suppliers it Order Alternative Net flow
uses an Integer Programming method. In this case, it was 1º Co1 0.4397
employed PROMETHEE V adaptation, proposed by [38],
2º Co8 0.2313
which aims to insert all the alternatives that improve this
set, including those that have negative flows. In this 3º Co9 0.1257
method, the resources constraints are considered to 4º Co3 -0.0683
choose the group of suppliers in the final selection, since 5º Co2 -0.3393
the company’s normally have a limited amount of
6º Co5 -0.3890
resources to achieve their objectives.

The global ranking of contractors was coherent with


IV. NUMERICAL APPLICATION the individuals' rankings. The first alternative (Co1) is the
first for all decision makers. Co8 and Co9 vary between
It was made a numerical simulation of the proposed the second and third position according with the DM. Co 3
model aiming demonstrate its use. For this application, it ranks fourth for DM1 and DM2 and is indifferent to Co 8
was structured a typical problem of contractor selection in (third position) to DM3. Finally, Co 2 and Co5 vary
the construction industry, in which the company would between the fifth and sixth positions for all DMs.
select a group of suppliers for a project, considering the For the final selection, the global net flows, obtained
need of contractors with balanced performance in the in PROMETHEE GDSS were used as an entry for
criteria and the power of decision makers. The PROMETHEE V, which identifies the better set of
PROMETHEE.GAIA and EXCEL software were used in contractors, considering the imposed constraints. In this
the simulation. case, it was used the adaptation proposed by [38] for
Initially, it was defined a simulate committee, PROMETHEE V, which accepts the inclusion of
composed by three members (DM1, DM2 and DM3), in alternatives with negative flows since their choice bring
order to select a group of contractors, among ten potential improvements in the results. In this way, it was
suppliers (Co1, Co2, Co3, Co4, Co5, Co6, Co7, Co8, Co9, considered the optimization of sets of the same size and
Co10). defined the c-optimal sets for each number c of items.
Following, it was defined the order-qualifying and Following, the ranking of sets was made, according with
order-winning criteria which are related to the objectives the results of objective functions and constraint. The
of the decision maker with respect to the contractors. The constraint imposed was the cash flow (308,000.00 dollars)
contractors select by the model only will be adequate to to the contract of suppliers. The input data for the problem
the preferences of the company with the criteria is in was:
TABLE 3 incorporate the preferences of DMs in the Integer
INPUT DATA FOR PROMETHEE V Programming.
In this way, the major differential of the proposed
Alternative Price Net flow model is the integration of the PROMETHEE GDSS and
PROMETHEE V for the contractor selection.
Co1 100,000.00 0.4397
The need of a structured systematic derivates from
Co2 106,000.00 -0.3393 the fact that unstructured selection processes can be
Co3 105,000.00 -0.0683 results in the contract of suppliers that are not adequate to
Co5 110,000.00 -0.3890 the company’s needs. Moreover, this model facilitates the
interaction between the analyst and manager, due the
Co8 102,000.00 0.2313
simplicity of the parameters, and is very flexible in the
Co9 105,000.00 0.1257 identification of contractor’s preferences.
Finally, it was made a numerical application. In order
Using the tool Solver of Excel, with a tolerance of to use criteria normally consider by real companies, it was
0,1%, it was obtained that the optimal set was Co1, Co3 made a literature review to identify the criteria mainly
and Co8. Although Co3 have a negative net flow, this used in contractor’s selection and employee the most cited
alternative does not have a negative value, but its in the simulation. In this way, it was observed the
outranking from the others. In this way, the alternative importance of choose criteria and determinate weights
will be incorporated to the set to improve its global adequate for the problem, since if they are determined in a
performance. As a result, the set of suppliers selected wrong way, the result does not be satisfactory.
were Co1, Co3 and Co8. Although the application was be made in construction
For the robustness verification of proposed model, it industry, the proposed model do not restrict to this sector,
was made a sensitivity analysis, in which the weights of but would be used for the supplier selection in various
determined criteria and decision makers vary and the types of organizations, as a form of improve the
others are modified proportionally. In the first analyze it management of supplier, aiming achieve the strategic
was made an increase and decrease of 5% in the weights objectives of company and acquire more competitiveness
of C2 and C4 for each DM. In the second, the weight of in the market.
criteria is the same for each DM. And finally, it was made
an increase of 10% in the weight of each DM. As a result,
it was observed that the variation of weights does not REFERENCES
influence the results of the final selection, which implies
that the model is robust for small variations in the [1] M. S. El-Abbasy, T. Zayed, M. Ahmed, H. Alzraiee, and M.
weights. Abouhamad, "Contractor selection model for highway
projects using Integrated Simulation and Analytic Network
Process", Journal of Construction Engineering and
Management, vol. 139, no. 7 , pp. 755-767, 2013.
V. FINAL CONSIDERATIONS [2] S. H. Zolfani, I. Chen, N. Rezaeiniya, and J. Tamošaitienė,
"A hybrid MCDM model encompassing AHP and COPR
The contractor selection is a very important issue AS-G Methods for selecting company supplier in Iran",
in the construction industry since the contractor has an Technological and economic development of economy, vol.
essential role in the success or failure of projects in this 18, no. 3, pp. 529–543, 2012.
sector. Thereby, it is imperative identify criteria and [3] J. R. S. Cristóbal, "Contractor selection using multicriteria
methodologies adequate to this selection problem in order decision-making methods", Journal of Construction
to choose satisfactory suppliers to the projects. Engineering and Management, vol. 138, no. 6, pp. 751-758,
In this context, this paper proposed a multicriteria 2012.
model for the selection of contractors in this sector. This [4] R. Lin, “An integrated FANP-MOLP for supplier
model considers the existence of various decision makers evaluation and order allocation”, Applied Mathematical
Modeling, vol. 33, no. 6, pp.2730-2736, 2009.
with different preference systems and a possible difficult [5] O. Senvar, G. Tuzkaya, and C. Karahman, “Multi criteria
of consensus. Due this, employee PROMETHEE GDSS supplier selection using Fuzzy PROMETHEE Method"
method, which consider the preferences of each decision (Book style with paper title and editor), in Supply Chain
maker individually and following aggregate this Management under Fuziness: Recent Developments and
preference. Furthermore, it is possible consider different Techniques, C. Kahraman, and B. Oztaysi, New York:
weights to the decision makers which represents their Springer, 2014, pp. 20-34.
power in the organization. [6] M. Cheshmberah, A. Makui, S. M. Seyedhoseini, and S.
Moreover, the model aims to select a set of Yousefi, “Analysing the impact of the product life cycle on
contractors with maximum utilization of the available the importance of outsourcing decision-making criteria: a
manufacturing case study”, South African Journal of
resources, considering the existent constraints. Because of Industrial Engineering, vol. 22, no. 2, pp.216-226, 2011.
this, it was used an adaptation of PROMETHEE V for the [7] D. Singh, and R.L.K. Tiong, "A fuzzy decision framework
final selection. The net flows of PROMETHEE GDSS for contractor selection", Journal of Construction
were used as the entries of the method as a form of
Engineering and Management, vol. 131, no. 1, pp. 62-70, Economic Development of Economy, vol.14, no. 2, pp.
2005. 224-239, 2008.
[8] S. Seuring and S. Gold, “Conducting content-analysis based [25] E. K. Zavadskas and Z. Turskis and J. Tamošaitienė,
literature reviews in supply chain management”, Supply "Contractor selection of construction in a competitive
Chain Management: An International Journal, vol. 17, no.5, environment", Journal of Business Economics and
pp. 544 – 555, 2012. Management, vol. 9, no. 3, pp. 181-187, 2008.
[9] E. Palaneeswaran and M. M. Kumaraswamy, "Recent [26]S.S. Padhi and P. K. J. Mohapatra, "Centralized construction
advances and proposed improvements in contractor contractor selection considering past performance of
prequalification methodologies", Building and contractors: a case of India", Operation Research: An
Environment, vol. 36, pp. 73-87, 2001. International Journal, vol. 9, pp. 199–224, 2009.
[10] Y. I. Topcu, "A decision model proposal for construction [27]A.A. Oladapo, "Multi-criteria contractor selection – a
contractor selection in Turkey", Building and Environment, practical application of analytic hierarchy process",
vol. 39, pp. 469 – 481, 2004. Management, Procurement and Law, vol.164, no. 2, 2011.
[11] E. Plebankiewicz, "Construction contract prequalification [28]W. Wang and W. Yu and I. Yang and C. Lin and M. Lee
from Polish Clients' Perspective", Journal of Civil and Y. Cheng, "Applying the AHP to support the Best-
Engineering and Management, vol. 16, no. 1, pp. 57-64, Value contractor selection - Leassons learned from two
2010. case studies in Taiwan", Journal of Civil Engineering and
[12] M. Darvish and M. Yasaei, and A. Saeedi, "Application of Management, vol. 1, pp. 24-36, 2013.
the graph theory and matrix methods to contractor ranking", [29]B. Liu and T. Huo and P. Liao and J. Gong and B. Xue, "A
International Journal of Project Management, vol. 27, no. 6, group decision-making aggregation model for contractor
pp. 610–619, 2009. selection in large scale construction projects based on Two-
[13] G. D. Holt, "Which contractor selection methodology?", Stage Partial Least Squares (PLS) Path Modelling", Group
International Journal of Project Management, vol. 16, no. 3, Decision and Negotiation, 2014.
pp. 153-164, 1998. [30]L. Y. Wei and C. Shouyu and N. Xiangtian, "Fuzzy pattern
[14] E. Palaneeswaran and M. M. Kumaraswamy, "Contractor recognition approach to construction contractor selection",
selection for design/build projects", Journal of Construction Fuzzy Optimization and Decision Making, vol. 4, pp. 103 –
Engineering and Management, vol. 126, no. 5, pp. 331-339, 118, 2005.
2000. [31]B. Vahdani and S. M. Mousavi and H. Hashemi and M.
[15] G. D. Holt and P. O. Olomolaiye and F. C. Harris, Mousakhani and R. Tavakkoli-Moghaddam, "A new
"Evaluating prequalification criteria in contractor compromise solution method for fuzzy group decision-
selection", Building and Environment, vol. 29, no. 4, pp. making problems with an application to the contractor
437-448, 1994. selection", Engineering Applications of Artificial
[16] D. Singh and R. Tiong, "Contractor selection criteria: Intelligence, vol. 26, pp. 779–788, 2013.
Investigation of opinions of singapore construction [32]C.H. Wong, "Contractor performance prediction model for
practitioners”, Journal of Construction Engineering and the United Kingdom construction contractor: a study of
Management, vol. 132, no. 9, pp. 998–1008, 2006. Logistic Regression Approach", Journal of Construction
[17] S. S. Padhi and P. K. J. Mohapatra, "Centralized bid Engineering and Management, vol. 130, pp. 691-698, 2004.
evaluation for awarding of construction projects – a case of [33]H. Abbasianjahromi and H. Rajaie and E. Shakeri, "A
India government", International Journal of Project framework for subcontractor selection in the construction
Management, vol. 28, pp. 275–284, 2010. industry", Journal of Civil Engineering and Management,
[18] L. F. Alarcón and C. Mourgues, "Performance modeling for vol. 19, no. 2, pp. 158-168, 2013.
contractor selection", Journal of Management in [34]D. J. Watt and B. Kayis and K. Willey, "Identifying key
Engineering, vol. 18, no. 2, pp. 52-60, 2002. factors in the evaluation of tenders for projects and
[19]W. Lo and M. Yan, "Evaluating qualification-based services", International Journal of Project Management, vol.
selection system: a simulation approach", Journal of 27, no. 3, pp. 250–260, 2009.
Construction Engineering and Management, vol. 135, pp. [35]E. Eshtehardian and P. Ghodousi and A. Ghodousi, "Using
458-465, 2009. ANP and AHP for the supplier selection in the construction
[20] F. Waara and J. Bröchner, "Price and nonprice criteria for and civil engineering companies; case study of iranian
contractor selection", Journal of Construction Engineering company", Journal of Civil Engineering, vol. 17, no. 2, pp.
and Management, vol. 132, no. 8, pp. 797-804, 2006. 262-270, 2013.
[21]M. M. Marzouk and A. A. El-Kherbawy and M. Khalifa, [36]A. T. ALMEIDA, “O Conhecimento e o Uso de Métodos
"Factors influencing sub-contractors selection in Multicritério de Apoio à Decisão”. Recife, Editora
construction projects", HBRC Journal, vol. 9, no.2, pp. Universitária UFPE, 2011.
150–158, 2013. [37]L. F. GOMES and M. C. G. ARAYA and C.CARIGNANO,
[22]G. Arslan, “Web-based contractor evaluation system for “Tomada de Decisões em Cenários Complexos; Introdução
mass-housing projects in Turkey", Journal of Civil aos Métodos Discretos do Apoio Multicritério à Decisão.”
Engineering and Management, vol.18, pp.323-334, 2012. São Paulo, Pioneira Thomson Learning, 2004.
[23]M. Abdelrahman and T. Zayed, and A. Elyamany, "Best- [38] A. T. Almeida and R. Vetschera, “A Note on Scale
value model based on project specific characteristics", Transformation in the PROMETHEE V Method”, European
Journal of Construction Engineering and Management, vol. Journal of Operational Research, vol. 219, pp. 198-200,
134, no. 3, pp. 179-188, 2008. 2012.
[24]Z. Turskys, "Multi‐attribute contractors ranking method by
applying ordering of feasible alternatives of solutions in
terms of preferability technique", Technological and

View publication stats

Вам также может понравиться