ESTIMATING & COSTING OF EXTRA WORKS OF INDOOR SPORTS HALL AT Gr.

FLOOR WITHIN PANSKURA BANAMALI COLLEGE,


DIST. - PURBA MEDINIPUR
[AS PER PWD SOR Vol-I w. e. f. 1.12.2015]

S.NO Ref.From Description Of Work Unit Quantity Rate Amount


1 P-1 Earth work in excavation of foundation trenches or drains, in all cum 135.203 73.77 9,973.93
(A) sorts of soil (including mixed soil but excluding laterite or
2/(a) sandstone) including removing, spreading or stacking the spoils
within a lead of 75 m. as directed. The item includes necessary
trimming the sides of trenches, levelling, dressing and ramming
the bottom, bailing out water as required complete.
(a) Depth of excavation not exceeding 1,500 mm.

For Foundation
i) 2150 x 3150 - Q - (25.100 x 3.750 x 0.45) x 2 = 84.713
ii) 2150 x 2150 - Q - (20.40 x 2.750 x 0.45) x 2 = 50.490

3 P-2 A) Filling in foundation or plinth by silver sand in layers not cum 410.919 404.52 166,224.95
(A) exceeding 150 mm as directed and consolidating the same by
4/(A) thorough saturation with water, ramming complete including the
cost of supply of sand. (payment to be made on measurement of
finished quantity)

i) Sand Filling - Q - (135.503/3) = 45.068


i) Floor - Q - (30.150 x 18.00 x 0.425) = 230.648
ii) For Foundation
i) 2150 x 3150 - Q - (25.10 x 3.750 x 0.45) x 2 = 84.713
ii) 2150 x 2150 - Q - (20.40 x 2.750 x 0.45) x 2 = 50.490

5 P - 15 Ordinary Cement concrete (mix 1:1.5:3) with graded stone cum 0.150 5,720.00 858.00
(C) chips (20 mm nominal size) excluding shuttering and
7/a reinforcement if any, in ground floor as per relevant IS codes.
(i) Pakur Variety
i) For Floor
Q - (30.150 x 18.00 x 0.025) = 13.568
i) For Column
a) 500 x 300 - Q - (0.50 x 0.30 x 0.05) x 14 = 0.105
b) 300 x 300 - Q - (0.30 x 0.30 x 0.05) x 10 = 0.045

Page no. - 01 of 02 P.T.O.

ESTIMATING & COSTING OF EXTRA WORKS OF INDOOR SPORTS HALL AT Gr. FLOOR WITHIN PANSKURA BANAMALI COLLEGE,
DIST. - PURBA MEDINIPUR
[AS PER PWD SOR Vol-I w. e. f. 1.12.2015]

S.NO Ref.From Description Of Work Unit Quantity Rate Amount


6 P - 28 Reinforcement for reinforced concrete work in all sorts of MT 0.02 55,954.40 1,119.09
(c) structures including distribution bars, stirrups, binders etc
15/a/II initial straightening and removal of loose rust (if necessary),
cutting to requisite length, hooking and bending to correct
shape, placing in proper position and binding with 16 gauge
black annealed wire at every intersection, complete as per
drawing and direction.
(a) For works in foundation, basement and upto roof of 1st.
floor/upto 4 m
ii (other than SAIL/ TATA/RINL)

i) For Column
Q = (0.150 x 1.5 x 7850)/10000 = 0.02

7 P - 27 Hire and labour charges for shuttering with centering and sqm 1.720 347.00 596.84
(C) necessary staging upto 4 m using approved stout props and
12/(a) thick hard wood planks of approved thickness with required
bracing for concrete slabs, beams and columns, lintels curved
or straight including fitting, fixing and striking out after
completion of works at 1st. Floor
(a) 25 mm to 30 mm thick wooden shuttering as per decision &
direction of Engineer-In-Charge.

i) For Column
a) 500 x 300 - Q - (2 x [0.50 + 0.30] x 0.05) x 14 = 1.120
b) 300 x 300 - Q - (2 x [0.30 + 0.30] x 0.05) x 10 = 0.600

8 Extra cost for carring materials 366,000.00

Total = 178,772.81

Page no. - 02 of 02 End of Page