Вы находитесь на странице: 1из 7

Distribution Feeder Voltage Regulation

Control
W. H. Kersting, Life Fellow, IEEE
Milsoft Utility Solutions


used to determine the location of the needed regulators and
Abstract – Step voltage regulators are the work horse of the control settings. The power flow program must be capable
distribution feeders for maintaining the voltage at every of modeling both the shunt capacitors and the step voltage
customer’s meter to be within the ANSI standards. A step regulators. The modeling of step voltage regulators can be
voltage regulator can be viewed as a tap changing complex. It is critical that the program is able to model the
autotransformer. This paper will apply a model of the step compensator circuit since this is the control that determines
voltage regulator. The IEEE 13 Node Test Feeders will be when a tap change is necessary. The compensator model will
used to demonstrate how the regulator is controlled in order include the desired voltage to be held within a specified
to maintain the desired voltage for full load, light load and bandwidth at the “regulation point” and the R and X settings.
future load conditions. The coordination of step voltage The R and X settings model that line impedance from the
regulators with shunt capacitors will be included. location of the regulator to the regulation point. This paper
will utilize a distribution power flow program
Index Terms – Step voltage regulators, shunt capacitors, (Windmil™[2]) to demonstrate how the locations of
compensator settings, ANSI voltage standards, IEEE Test regulators can be determined and then how the compensator
Feeders setting are determined.

II. THE ANSI VOLTAGE STANDARD


I. INTRODUCTION
The two critical voltages in the ANSI standard are the
Every customer on a distribution feeder must be supplied a “Maximum Utilization Voltage” and the “Minimum Service
voltage that is within ANSI standards [1]. The ANSI Voltage”. Both of these voltages are measured at the
standards give the distribution engineer a range of “normal customer’s meter. The “Maximum Utilization Voltage” will
steady-state” voltages (Range A) and a range of “emergency” be the metered voltage at the customer closest to the
steady-state voltages (Range B) to be supplied to all substation. Typically this voltage is measured at the meter
customers. The two ranges are: under a no-load condition. This implies that there is no
voltage drop through the transformer, secondary and service
1. Range A drop. The “Minimum Service Voltage” will occur when the
a. Nominal Utilization Voltage = 115 volts customer has the maximum load on and will include the
b. Maximum Utilization Voltage = 126 volts transformer, secondary and service drop voltage drops.
c. Minimum Service Voltage = 114 volts In addition to the Range A and B requirements, the ANSI
d. Minimum Utilization Voltage = 110 volts Standard recommends that the feeder should be operated so
2. Range B that the voltage unbalance at three-phase loads will not
a. Nominal Utilization Voltage = 115 volts exceed 3%. Voltage unbalance is defined as:
b. Maximum Utilization Voltage = 127 volts
c. Minimum Service Voltage = 110 volts Voltageunbalance =
Max. deviation from average voltage

100% (1)
d. Minimum Utilization Voltage = 107 volts Average voltage

As the load on the feeder changes, every customer’s voltage The task for the distribution engineer is to design and
will vary so that the ANSI standard may not be satisfied. The operate the distribution feeder so that under normal steady-
regulation of the voltages requires some method to regulate state conditions the voltages at the meters will lie within
the voltages as the load change. The two most common Range A and the voltage unbalance will not exceed 3%.
methods are the application of switched shunt capacitors and The ANSI voltage standards provide the basis for
step voltage regulators. The step voltage regulators may be establishing guidelines for an acceptable voltage profile from
located in the distribution substation or downstream from the the substation to the most remote customer. An example of a
substation. The distribution planning engineer must have a typical voltage profile is shown in Fig. 1.
means of analyzing the feeder voltages in the present and into
the future. A distribution system power flow program can be


W. H. Kersting is a consultant to Milsoft Utility Solutions and a partner in
WH Power Consultants, Las Cruces, NM.
Corresponding e-mail for this paper: bjkersting@zianet.com
Laterals
Preventive
Autotransformer N1
Sub Reg
IS
R Reversing
128 S Switch
126 Max Load + Series L
Winding
124
IL
122
Min Load L
120
VS N2 +
Control
118 CT
116
Shunt
Winding
Control VL
114 PT

- -
Reg First Reg. Last Last
Output Customer Point Xfm Customer
SL
Figure 1 – Voltage Profiles
Figure 2 – Type B Step Voltage Regulator
Fig. 1 shows a typical voltage profile from the substation to
the most remote customer for both maximum and minimum Note that the input to the Type B step voltage regulator is
load conditions. Under maximum load conditions it is across the series and shunt windings. The Type A step
usually assumed, on a 120 volt base, that there will be a one voltage regulator would have the load side connected across
volt drop through the service drop, a two volt drop through the series and shunt windings. In Fig. 2 when a change in
the secondary and a three volt drop through the transformer. taps is required the preventive autotransformer changes the
With an acceptable low voltage of 114 volts at the customer’s number of turns on the series winding ( N 2 ).
meter, this requires that the input voltage to the transformer
should not be lower than 120 volts under the maximum load IV. THE STEP VOLTAGE REGULATOR MODEL
condition. When running a power flow study that models
down to the primary of the distribution transformers all The model for a step regulator is developed in
voltages must lie between 126 and 120 volts. Notice in Fig. 1 Reference[4]. For a single-phase type B regulator the
that a “regulation point” has been defined. The idea here is relationships between the source voltage and current to the
that as load varies, the regulation point becomes the pivot output voltage and current are given by:
point for the profile. In other words, the voltage at the
regulation point will remain constant as the load varies. In 1
Fig. 1 it is shown that during minimum load conditions the VL = �
VS
aR
output of the regulator has been reduced and the voltage at
the last customer is greater. This is the desired operating I L = aR �
IS (2)
condition that is the basis for determining the settings for the N2
control circuit (compensator) of the substation voltage where: aR = 1 m
regulator. Note also in Fig. 1 that there are laterals tapped off N1
the main feeder so that the current leaving the regulator will In (2) the minus sign is when the regulator is in the raise
not be the same as the current arriving at the regulation point. position and the plus sign for the lower position.
The actual number of turns on the series and shunt
III. THE STEP VOLTAGE REGULATOR windings is not known, however, each change in tap changes
the voltage by 5/8% or 0.00626 per unit. Therefore the
A step voltage regulator consists of an autotransformer and effective regulator ratio can be given by:
a load tap changing mechanism. The voltage change is
obtained by changing taps on the series winding of the aR = 1 m0.00625 �
Tap (3)
autotransformer. The position of the tap is controlled by the
compensator circuit. Standard step-regulators contain a In (2) and (3) the minus sign is for the regulator in the
reversing switch enabling a ±10% regulator range, usually in raise position, the plus sign is when the regulator is in the
16 steps up and 16 steps down. This amounts to a 5/8% lower position.
change per step or 0.75 volts change per step on a 120 volt Single-phase regulators can be connected in wye, delta and
base. Step regulators can be connected in a Type A or Type B open delta for three-phase lines. For all of the connections
connection according to the ANSI/IEEE C57.15-1986 the general three-phase model is shown in Fig. 3. [4]
standard [3]. The more common Type B connection is shown
in Figure 2.
 I S  abc  I L  abc
MVA rating
Iline R line  jXline
CTp  CTs

Ic
 VS  abc  VL  abc kVLLhi  kVLLlow
R c + jX c Reg. Point

 VS  abc = a   VL  abc
1:1
 I S  abc = d   I L  abc + Vdrop -

+ +
Figure 3 – Three Phase Voltage Regulator Model N PT :1 VR
Voltage
Vreg Relay
- -
In Fig. 3 if the regulators are connected in wye the voltages
will be the line-to-neutral voltages. If the regulators are
connected in delta (open or closed) the voltages will be line-
F Figure 4 – Compensator Circuit
to-line. In all cases the currents will be the line currents by
phase.
The goal of the compensator circuit is such that the voltage
The general equations for three regulators connected in
across the compensator voltage relay will be a scale model of
grounded wye are:
the actual voltage at the regulation point. Another way of
looking at it is to have the per-unit voltage of the
� VAG � � aR _ a 0 0 �� Vag � compensator voltage relay equal to the per-unit voltage at the
� � � �� � regulation point. In order to make this happen the per-unit R
� VBG �= � 0 aR _ b 0 �� �Vbg �
� �� � (4) and X settings must equal the per-unit equivalent line
� V �
�CG � � 0 0 aR _ c ��Vcg � impedance from the regulator output to the regulation point.
The compensator settings are input in units of volts and are
 VLG  ABC =  a  �
 VLG  abc determined according to Equation 6.

�1 � CT
� 0 0 � Zcomp = Zline � Volts (6)
aR _ a N pt
� �
� IA � � ��Ia �
1 Zline = equivalent line impedance in ohms
� IB � � ��I �

� �= � 0 aR _ b
0
��b � (5) where: CT = current transformer primary rating

� IC �� � ��
�Ic �

1 � N pt = potential transformer ratio
�0 0
� aR _ c �
� � The potential transformer ratio is determined by
 I ABC  =  d  �
 I abc 
VLN rated
N pt = (7)
Note in (4) and (5) that each regulator can have different 120
tap settings.
The primary rating of the current transformer ( CT p ) is
V. THE COMPENSATOR CIRCUIT
selected to be at least equal to the rated feeder current. For
The changing of taps on a regulator is controlled by the most compensator controls the secondary current ( CTs ) is
“line drop compensator”. A simplified circuit of an analog 0.2 amps.
compensator and how it is connected to the feeder through a The “voltage level” setting is the voltage on a 120-volt base
potential transformer and a current transformer is shown in that will be held at the regulation point. To limit the number
Fig. 4. of tap changes made as load changes a “bandwidth” is set so
There are four settings that are required for the that the taps are only changed when the relay voltage is
compensator circuit. Whether the compensator is analog or outside of the bandwidth. This is illustrated in Fig. 5. The
digital, the following settings must be made. bandwidth is two times the allowed deviation above or below
1. Compensator R and X settings the set voltage level.
2. Voltage Level: the desired voltage to hold at the In Fig. 5 the voltage level has been set at 122 volts with a
regulation point 2 volt bandwidth. Since each tap changes the voltage by 0.75
3. Bandwidth: defines the allowed variance of the volts, it is possible (and not unusual) that two different tap
regulation point voltage centered on the desired settings can occur for the same load condition.
Voltage Level.
4. Time Delay: the time delay before a tap change is
made when the voltage relay voltage is not within
the bandwidth
1

2
Voltage Level

123
122 Bandwidth = 2 V
121 9 8 3 6 7

Figure 5 – Voltage Level and Bandwidth

The major concern now is what is the value of the line 13 12 4 10 11


impedance that is to be set? There are many ideas on how to
determine the impedance. A quick surfing of the Web. found
three different approaches. [5]-[7]. The method that will be
used in this paper differs from the references. This method
computes the equivalent impedance from the regulator to the
regulation point under a maximum load condition with no 14 5
shunt capacitors connected. Figure 6 – IEEE 13 Node Test Feeder
The first decision that has to be made is to identify the
feeder node that will be the reference point. Again, there are The IEEE 13 Node Test Feeder was originally developed to
many ways of selecting this node. One approach that can be test the convergence capabilities of different software
used for a voltage regulator located in the substation is to use programs. The feeder is highly unbalanced and is a good test
the “load center” node. This would be a node on the system for convergence. For this paper the feeder is modified to
where one half of the feeder load has been dropped off to the balance the system better so that a straight forward
upstream laterals. Another method is to set the substation application of the substation voltage regulators can be
voltage to 126 volts and then find the downstream node demonstrated. The modifications are:
where the voltage has dropped to 120 volts. This becomes a  Line 4-12 changed to phases B-C
logical node to define as the “regulation point”.  Transformer 6-7 changed to ungrounded wye – delta
With the regulation point identified, the R and X settings with the same voltages, kVA rating and impedance
are computed by:
 Load at 7 converted to a delta – PQ
 Load at 8 changed to delta – PQ
For i = a,b,c
 Load at 14 changed to phase B wye-PQ
Vregi  Vreg _ pti (8)  Load added to 5 of wye – PQ of 300 + j145.3 kVA
Zlinei = Ohms
Iregi The nominal voltage rating of the feeder is 4160 line-to-
line volts. The regulation point was determined by setting the
where: source line-to-neutral voltage at node 1 to 1.05 per-unit
Vreg = actual line-to-neutral voltage at the regulator (2401.8 volts). The power flow program was run for a full
load. All three phase voltages dropped below 120 volts at
Vreg _ pt = actual line-to-neutral volage at the regulation point Node 4. A profile for phase C (the lowest) is shown in Fig. 7.
I reg = actual line current leaving the regulator 130

127.5
With the potential transformer ratio and current
transformer ratings determined and line equivalent line 125
impedance computed for each phase, Equation 13 is used to
determine the R and X settings in volts. 122.5
Node Voltage

Vc 120
VI. THE IEEE 13-NODE TEST FEEDER
117.5
The IEEE 13 Node Test Feeder [8] is modified to
demonstrate how the compensator settings are determined. 115
The one-line diagram is shown in Fig. 6.
112.5

110
1 2 3 4 5
Node

Figure 7 – Phase C Voltage Profile


The voltage profile shows that the phase C voltages at impedances is used to compute the R and X used in the
Nodes 3,4 and 5 are below the minimum primary transformer compensator circuit.
voltage. There is also a slight voltage rise on the line from 4 The next stop is to set the compensator R and X with
to 5. Since the load at node 5 is just a phase B load, the desired voltage of 121 volts and a band width of 2 volts.
voltage rise is caused by the unbalanced currents flowing on The voltage profile for this case is shown in Figure 8.
the line. With node 4 selected as the regulation point, the
equivalent line impedances per phase were computed using
the source voltages, regulation point voltages and source line Full Load with Regs, No Caps
135
currents from the power flow run.
132.5
Define CT rating and PT ratio: 130
127.5

Node Voltage
2400 125
CT p = 700 N pt = N pt = 20
120 Vc 122.5
120
Define voltages and currents at 1.05 PU and no 117.5
Reg. 115
 2521.87 ej 0  112.5

Vreg = 2521.87 e j 120 deg
 110
  1 2 3 4 5
 2521.87 ej 120 deg 
  Node

Figure 8 – Phase C Voltage Profile with Regulators


 2347 e j 3.1 deg 
Note in Figure 8 that the source voltage at Node 1 has been
Vreg_pt =  2361.2 e j 124.2 deg  set to 120 volts. The voltage at Node 2 is the output voltage
  of the regulator. For this case the taps on the phase regulators
 2261.6 ej 115.2 deg  were found to be:
 
Phase A: 11
 537.5 e 
 j 34.4 deg Phase B: 12
Phase C: 15
Ireg =  633.9 e j 150.4 deg 
  It is first seen that the phase C tap is almost to the
 703.1 ej 81.5 deg  maximum position of 16. The profile also shows that the
 
output voltage of the regulator is well above the maximum
Compute equivalent line impedance per desired voltage of 126 volts.
phase: At this point shunt capacitor banks are added to assist in
the voltage regulation. The power flow output for the case of
i = 1  3 no regulators shows the reactive power supplied by phase is:
Vreg  Vreg_pt  0.1403  0.3823j  Phase A: 765 kvar
i i
Zline i = Zline =  0.0892  0.3686j  Phase B: 809 kvar
Ireg  0.131  0.4481j  Phase C: 1105 kvar
i  
Compute average line With that much reactive power being supplied by the
impedance: source, shunt capacitor banks of approximately 800 kvar per
Z avg = mean( Zline ) Z avg = 0.1202  0.3997j phase can be added to the system. After several power flow
runs, shunt capacitors were placed as:
Compute compensator R and X settings:
Node 3: 100 kvar per phases A, B and C
CT p Node 4: 600 kvar per phases A, B and C
Z set = Z avg Z set = 4.2  14j Node 13: 150 kvar on phase C
N pt
With these capacitor banks installed the regulator taps are:
Because of the load unbalance, the phase equivalent
impedances are not the same. Since the regulator Phase A: 5
compensator circuits are set with the same R and X values for Phase B: 6
each phase an average value of the equivalent line Phase C: 7
300 kvar per phase is switched off at Node 4 with the
The voltage profile for phase C with the shunt capacitors resulting Phase C voltage profile shown in Figure 11.
installed is shown in Figure 9.
50% with Switched Caps
Full Load with Regs and Caps 135
135 132.5
132.5 130
130 127.5

Node Voltages
127.5 125
Vc 122.5
Node Voltage

125
Vc 120
122.5
117.5
120
115
117.5 112.5
115 110
1 2 3 4 5
112.5
Node
110
1 2 3 4 5
Node

Figure 9 – Voltage Profile with Regs and Caps Figure 11 – Full Load and 300 kvar Switched Off

Figure 9 demonstrates that with the regulator and the shunt For this condition, the reactive powers supplied by the
capacitors all node voltages are within the desired limits. The source are:
next concern is what happens when the load is reduced to its
daily minimum? For this example it will be assumed that the Phase A: -59 kvar
minimum load for the feeder is 50% of full load. The phase Phase B: -40 kvar
C voltage profile is shown in Figure 10. Phase C: -59 kvar

The voltage rise displayed in Figure 10 is a result of the


50% Load with Regs and Caps leading power factor operating condition for the feeder.
135
The final study is to look into the future. A 10% load
132.5 growth is assumed with the resulting voltage profile shown in
130 Figure 12.
127.5
Node Voltage

125 10% Load Growth


Vc 122.5 135
120 132.5
117.5 130
115 127.5
Node Voltage

112.5 125
Vc 122.5
110
1 2 3 4 5 120
Node 117.5
115
Figure 10 – 50% of Full Load
112.5
For this case the reactive powers supplied by the source 110
1 2 3 4 5
are:
Node
Phase A: -361 kvar
Phase B: -345 kvar Figure 12 – 10% Load Growth
Phase C: -368 kvar
It is noted that the output voltage of the regulator exceeds
This indicates that approximately 300 kvar per phase the maximum allowed voltage of 126 volts. Once again this
should be switched off during this minimum load condition.
problem can be corrected by installing additional shunt
capacitors. This paper has demonstrated how wye connected step
The reactive powers supplied by the source are: voltage regulators located in the substation can be set to hold
a desired voltage at the regulation point. The application of
Phase A: 97 kvar shunt capacitors is included to demonstrate that the regulators
Phase B: 142 kvar and capacitors work together to hold the desired voltage at
Phase C: 308 kvar the regulation point for full load, minimum load and future
load conditions.
This study indicates that 100 kvar per phase of shunt
capacitors can be added to the feeder. Node 4 capacitor bank The methods demonstrated in this paper are used to
will be increased by 100 kvar per phase. regulate the voltages on the IEEE 34 Node Test Feeder [9].

Figure 14 – Composite Voltage Profiles


10% Growth with Added Caps
135
132.5
130 VIII. REFERENCES
127.5
1. American National Standard for Electric Power –
Node Voltage

125
Vc
Systems and Equipment Voltage Ratings (60) Hertz,
122.5
ANSI C84.1-1995, National Electrical
120 Manufacturers Association, Rosslyn, Virginia, 1996.
117.5 2. Milsoft Utility Solutions, Inc. Product Documents
115 [Online}, Available: http://www.milsoft.com/
112.5 3. IEEE Standard Requirements, Terminology and Test
Code for Step-Voltage and Induction Regulators,
110
1 2 3 4 5 ANSI/IEEE C57.15-1996, Institute of Electrical and
Electronic Engineers, New York, 1988.
Node 4. W. H. Kersting, Distribution System Modeling and
Analysis, 2007, CRC Press, Baca Raton, Florida.
Figure 13 – 10% Growth with Additional Caps 5. Voltage Regulators 225-10, [Online], Available:
http://www.cooperpower.com/Library/Literature/secti
With the additional capacitors all node voltages are within on-asp?ProductLineID=17
the ANSI limits. 6. Setting the Control, [Online], Available:
Even though the plots are busy, it is interesting to display http://beckwithelectric.com/Instruction-Books/M-
each of the profiles on one graph. Figure 14 demonstrates 6200-IB-01MC2%20(7-08)%20Screen.pdf
how well the voltage regulation has held the desired voltage 7. SEL-2431 Voltage Regulator Control, [OnLine],
level at Node 4 for all of the cases studied. Because all of Available:
these have only plotted the Phase C voltages it is seen that the https://customer.selinc.com/metadot/index.pl?
pivot point lies between Nodes 3 and 4. This is a result of id=5799&isa=Category&op=show
using an average value of the equivalent impedance between 8. IEEE Radial Test Feeders [Online], Available:
the regulator and the regulation point. http://ewh.ieee.org/soc/pes/dsacom/testfeeders.html
9. W. H. Kersting, The Modeling and Analysis of Step
VII. SUMMARY Voltage Regulators, 2009 IEEE Power Systems
Conference and Exposition, March 2009, Seattle,
Composite Profies WA.
135

V1 132.5

130
X. BIOGRAPHY
V2
127.5 W. H. Kersting (SM’64, F’89, Life Fellow 2003) was born in
Node Voltage for Each Case

V3 Santa Fe, NM. He received the BSEE degree from New


125 Mexico State University, Las Cruces, and the MSEE degree
V4 from Illinois Institute of Technology. He joined the faculty at
122.5 New Mexico State University in 1962 and served as Professor
V5 of Electrical Engineering and Director of the Electric Utility
120 Management Program until his retirement in 2002. He is
V6 currently a consultant for Milsoft Utility Solutions. He is also
117.5 a partner in WH Power Consultants, Las Cruces, NM.
V7
115

112.5

110
1 2 3 4 5
Node

Вам также может понравиться