Вы находитесь на странице: 1из 4

“Sharing Information to Improve Reliability”

TMG
Premature Failures
News Eliminated

April 15, 2004 The Manufacturing Game®


A t a Manufacturing Game®
workhop at Michelin in New
Glasgow on February 28,
2003, an action team was created to
Benefits of Planned Domain address the problem of premature fail-
ure of drum inflation membranes that

W e have spent considerable


time in the newsletter focus-
ing on the benefits and exe-
cution of the precision domain – remov-
The model is organized around the flow
of equipment. The equipment can flow
from a state of full functionality into
either the Breakdown or Planned mainte-
were causing a loss of production and
excessive membrane costs. This prob-
lem had been going on for quite a
while but no one had paid much atten-
ing the defects at the source. Our philos- nance process. Equipment enters the tion to it. There was a general consen-
ophy has evolved based on working with Breakdown maintenance process when it sus that no one would resolve the
clients and modeling reliability; most breaks down and remains there until it is problem.
organizations would be advised to focus repaired. Breakdowns are caused by Although the situation was not fully
first on eliminating defects and then on equipment defects that are introduced by understood by the team members,
making the defect removal process more the operation of the equipment, poor Mark MacKinnon, Mike Vienneau and
efficient with a planning and scheduling materials, poor design, or poor workman- Martin Cummings had discussions at
process. However, there are significant ship. The time to repair the broken equip- the TMG workshop and determined
benefits to the Planned Domain and this ment depends on the number of mechan- that an investigation was in order.
article focuses on the specific benefits ics allocated to Breakdown maintenance During this investigation, Mark
that are generated through the Planned and the productivity of the mechanics in MacKinnon, an Operator, was rum-
domain and the keys to a successful tran- executing repairs. Equipment moves into maging through failed and cut mem-
sition to the planned domain. Using our the Planned maintenance process when branes and found repeat failures at the
Dynamic Benchmarking model and data an inspection identifies a defect in the inflation groove close to the air inlet.
from a hypothetical chemical plant we equipment. Some of the equipment The big question the group had to ask
modeled at DuPont, we were able to cal- inspections are required by law and are themselves was "Why were the mem-
culate the benefits. mandatory. Other inspections, typically branes consistently failing around the
those involved in a predictive mainte- inlet port?" The root cause analysis
The Model nance program, are discretionary in the forced the team to investigate all of
The model represents a chemical sense that maintenance managers deter- the possible causes for the failure and
plant that has a replacement value of mine their frequency. The inspections are one of the possibilities was a defective
$444 millions. The plant employs 91 valuable because they identify problems vendor product.
mechanics who complete approximately before the equipment suffers a costly Mike Venotte, the Maintainer, con-
500 work orders per week. The plant breakdown. Scheduling involves setting a tacted the supplier to discuss the fail-
operates at an average of 83.5% of full time when the equipment can be discon- ures and the Reliability Responsible
capacity but could sell more product if nected from the manufacturing process investigated the installation procedure.
the plant ran better. flow so that it can be worked on. A poor Remarkably, two causes were discov-
The model was built during a one year Scheduling process can cause a discon- ered. Mark found that the inflation
process and contains dynamic relation- nect between inspections and repairs. pressure being used was two times the
ships that characterize the maintenance Once it is taken off-line, the defective recommended operating pressure and
operation. The data for the model was equipment can be repaired. The time to further discussions with the supplier
drawn from internal DuPont reports, complete Planned maintenance depends revealed that there was also a design
benchmarking studies, maintenance litera- on the number of mechanics allocated to flaw in the rubber consistency around
ture, interviews, and managerial judgment. Planned maintenance and the productivity the inlet.
What’s Inside? Benefits continued on Page 2 Premature Failures continued on Page 3

Benefits of Planned Domain 1-3 Elimination of Vessel Draining 3


Premature Failures Eliminated 1,3 Action Team Exhibits Fierce Determination 4
Public Workshop Calendar 2

1
Benefits continued from Page 1

of the mechanics in completing the ning program is unsuccessful. First, in the


Public Workshop repair. Planning is one of the factors that reactive case, most of the work is break-
Calendar effects the efficiency of the mechanics in down work. By definition, breakdown
Throughout the year, The Manu- completing Planned or Breakdown main- work is difficult to plan and adding plan-
facturing Game® holds workshops tenance. Planning refers to the process of ning has a small impact on the efficiency
for the general public at various creating an explicit plan for doing a spe- of doing Breakdown work. Turning
universities and/or professional cific task, planning increases mechanic mechanics into planners is wasteful if the
organizations across the country. productivity by standardizing work prac- plans don’t add much to productivity.
tices and by making sure that the materi- Second, with a reactive strategy, the
als and necessary skills are available to plants are typically overstaffed and there
TMG Pub lic Wor kshops
finish the job. In the base case simulation, is not enough work to do on a day to day
May 6-7, 2004
the plant does mostly Breakdown mainte- basis. Improving efficiency in their work
Knoxville, TN
nance. There is almost no manpower causes mechanics to complete work faster
May 24, 2004 allocated to doing discretionary inspec- when work is available but also lengthens
MARTS Conference tions or to creating job plans, the mainte- the gaps when there is no work available.
Chicago, IL nance strategy can be described as reac- The net effect is a very small increase in
Additional workshops for 2004 tive in the sense that the maintenance mechanic productivity and uptime.
may be announced at a later date. organization reacts to breakdowns instead
To register and for more of preventing them. 2. Scheduling
information, please visit our web site:
www.manufacturinggame.com/inaction.html The second simulation implements a
Results of the Modeling more efficient scheduling system. The
In this section, three of the mainte- first element of the scheduling program
nance programs are implemented in the is to shorten the delay between the time a
Conf er ences of Inter est simulation model. The results of the sim- defective equipment piece is identified
Offshore Technology ulations are compared to the reactive and the time it can be worked on. The
Conference maintenance strategy that is used in the second element of the program is to
May 3-6, 2004 base case simulation. Although the model improve the scheduling system’s memory.
Houston, TX
generates a variety of performance meas- When a piece of defective equipment is
For more information, visit:
http://www.otcnet.org ures, for simplicity, the simulations will be identified, often no action will be taken
compared on the basis of plant uptime. on it immediately because operations
Maintenance and Reliability Using other measures, such as net present needs the equipment on-line. In this situ-
Technology Summit
value or cost to compare the simulations ation, the scheduling system may not
May 24 - 27, 2004
does not change the basic results. remember that the equipment was defec-
Rosemont (Chicago) IL
To register and for more information tive unless there is an explicit record
please visit: 1. Planning keeping system. The second element of
www.marts-2004.com The first simulation implements more the policy implements an efficient record
extensive job planning. This policy is keeping system.
NPRA Maintenance Conference implemented by increasing the number of The rationale for the scheduling policy
May 25-28, 2004
job planners by reallocating seven is straight-forward. Better scheduling
San Antonio, TX
To register and for more
mechanics to planning and by adding a should increase the efficiency of Planned
information please visit: library of plans. The library increases the maintenance and lead to fewer break-
www.npra.org/meetings/maintenance/ productivity of the job planners by mak- downs. Fewer breakdowns increases
ing it unnecessary to create a new plan uptime. However, the results of the
for every job. scheduling policy are disappointing. Up
The rationale for increased planning is time increases by only 0.8%, which would
straight forward. More planning increases be imperceptible at the plant.
mechanic productivity. Higher productivi- The scheduling program fails because,
ty reduces the time to repair equipment in the base case, the plant is doing very
and increases equipment uptime. little Planned maintenance. Breakdown
Just as it was in maintenance at the maintenance, which is most of the work
plant sites, the result of adding planning in the base case, is by definition unpre-
in the model is disappointing. Uptime dictable and almost impossible to sched-
increases by only 0.5%, which would not ule. The scheduling policy does very little
be measurable in the plants. to improve the efficiency of Breakdown
There are two reasons why the plan- work.
Benefits continued on Page 3
2
Elimination of Vessel Draining During Jet Pump Tripping
At an Operations Excellence Game the actual cause of failure was not in collaboration with the production
workshop at BP Pakistan, an Action known but discovered three potential team carried out modifications through
Team addressed the problems with the solutions assigning a priority to each MOC (Management of Change) proce-
tripping of jet pumps resulting in the solution. 1.) Leakages on the surface dures to interlink the jet pump engine
complete draining of vessels. This low oil pressure security with the logic
defect required the refilling of vessels to of ESV’s (Emergency Shut down
bring the jet pumps back into operation. valves) installed on the casing return
These recurring failures were causing line and flow line. This modification
significant production losses that were was applied to more than 30 jet pumps
even higher for the jet pumps being based on production and tripping fre-
tripped during the night shift. Night quency. These modifications ensured
driving in the field is not allowed in BP actuation of ESV’s on jet pump tripping
Pakistan operations and these night-time and eliminated emptying out of the ves-
driving constraints made it necessary to from jet pump vessels or associated pip- sels.
wait until daylight to refill the vessel and ing. 2.) Vessel liquid going into the tub- While experiencing improved operat-
put the pump back in to operation ing, and 3.) Vessel liquid going into the ing efficiency, savings in maintenance
resulting in even greater losses. flow line. man-hours, and success in achieving
The team investigated the possible The team proposed remedial meas- 60% overall reduction in production
causes of these recurring trips by using ures. The Instrumentation & Electrical losses, the team is now devoting time to
an e-choke tool. They determined that section of the Maintenance Department investigating the root cause.

Benefits continued from Page 2 Premature Failures continued from Page 1


3. Predictive & Preventive 4. Synergy between Policies After consulting with the Quality and
Maintenance The analysis presented above suggests Uniformity group, the crew reduced the
In this policy, the frequency of equip- that there should be strong synergy pressure back to normal. The group was
ment inspections is increased, in the base between the maintenance policies. Model originally responsible for the increase. They
case, the frequency of inspections was simulations reveal this to be the case. The also followed up with the supplier to ensure
one every twenty weeks on average. In combination of planning, scheduling, and that progress was being made on eliminat-
the predictive and preventive program, predictive and preventive improves ing the design defect in a timely manner.
The action team truly performed as a
the frequency is increased to one every uptime by 4.1%. The combination of
team. The pressure limit control was hand-
two weeks. More inspections should these three policies with an improved
ed to the Dimension Change group who is
identify equipment defects before they maintenance materials supply process responsible for the initial setup of the
cause failures, fewer failures should direct- increases uptime by 5.1%. Clearly, it is the machine when a new tire line has to be
ly increase uptime. combination of the four policies that gen- built. Although it took somewhat longer
The predictive and preventive program erate the gains that were expected from a to have the supplier eliminate the design
is counterproductive as uptime falls by Planned maintenance process. defect, immediate benefits were experi-
2.4%. This surprising result is caused by Overall, the analysis of the model can enced. The membranes previously had
the interaction of several factors. First, be distilled down to two basic conclu- been failing once a week resulting in one
increased inspections draw manpower sions. First, a structural analysis of the hour of downtime. After reducing the
away from repair work. This would be maintenance system demonstrates that it pressure, the failures reduced to once every
fine if the inspections resulted in repairs is unlikely that maintenance programs will five weeks, which is the appropriate life of
the membrane. This was a huge gain in
that prevented breakdowns. Unfortun- be successful if they are implemented
throughput. There was also substantial sav-
ately, many of the inspections find defects separately. Second, there is a great deal of
ings in the reduced consumption of mem-
but, without an efficient scheduling sys- synergy between the policies. The combi- branes.
tem, the inspections do not result in nation of planning, scheduling, predictive It's amazing how a thorough root cause
equipment repairs and the equipment fails and preventive maintenance yield the analysis by a team truly working together
while it is waiting to be scheduled. The expected benefits of the Planned can eliminate a simple but very costly
man-hours spent on inspections are wast- Maintenance approach while the individ- problem.
ed for the lack of a good scheduling sys- ual components, taken individually, pro-
tem. Second, some of the inspections do duce small benefits in the long term.

♦ ♦
result in repairs but without a planning
system, the repairs are done inefficiently.
This increases the time to repair which
decreases uptime.
3
TMG
News
April 15, 2004 The Manufacturing Game®

7702 FM 1960 East, Ste. 226


Humble, TX 77346
(281) 812-4148
(281) 812-4149 Fax
Web site: http://www.manufacturinggame.com
email: info@manufacturinggame.com

TMG Public Workshop


May 6 - 7, 2004
Knoxville, TN
Don’t miss this exciting opportunity to
participate in a workshop first hand!
Register now to experience The Manu-
facturing Game® in action.
$600 per person registration fee includes all
workshop materials and lunch both days.
For more information, visit our website:
www.mfg-game.com/inaction.html
or call 281-812-4148

TMG News

Action Team Exhibits Fierce Determination in Eliminating Equipment Bug


At an Operations Excellence Game vendor to arrange for some training on The team then delved further in to
workshop held at BP in Trinidad recent- the operation of the turbine. They felt researching the valve with the help of
ly, an action team proved fierce determi- training would help them to better the vendor. They then discovered that
nation, dedication, and curiosity can get understand the equipment. The vendor the valve had been recalled. The vendor
to the root cause of a baffling equip- conducted two five-day training ses- immediately replaced the recalled valve
ment problem. The team was inspired sions. The sessions sparked the interest and lo and behold, the turbine worked,
by the slogan “don’t just fix it, improve of the team members and they became using the local liquid fuel.
it” and when faced with an unexplained extremely curious as to why the turbine The action team was thrilled to ulti-
problem with a new solar turbine, they would not work with the local fuel. mately conclude that the root cause of the
went into action. They continued researching the turbine problem was not the fuel quality at all.
The turbine, designed to run on both and went over the design drawings with This inspired a new team mantra "Trini
Fuel Good". The team's fierce determina-
liquid and gas fuels, was shipped to a fine toothcomb. They were frustrated
tion and "never say die" attitude demon-
Trinidad after it was successfully tested when they were still unable to determine
strated a best practice of getting to the
on both fuels in San Diego, California. the cause of the problem but the team source of a problem instead of just patch-
Once in Trinidad, the turbine did not pressed on. With the help of the ven- ing up a symptom. The team credits their
work when local liquid fuel was used. dor, they took a closer look at the tur- success in completing this action team to
The initial assumption was that there bine itself. When looking at the fuel their curiosity, which was inspired by the
was a problem with the quality of the diverter valve, they noticed some grit training they received in defect elimination.
local liquid fuel. The team began work and foreign matter in it, which they They feel that their commitment to re-
trying to resolve the problem by first, determined might have occurred during solve the problem led to a deepened com-
sending off a sample of the fuel for shipping from San Diego. The valve mitment to resolving a problem that they
testing. While waiting for the results then became the focus as a potential will carry over into future action teams.
from the test, the team contacted the source of the problem. ♦ ♦ ♦

Вам также может понравиться