Construction Productivity Rates are very important to both Site Engineers, and Planning Engineers. It
could be used to monitor the labor performance, or to estimate the manpower required for a project for
planning and monitoring purposes or for cost estimations. In this article i will share with you civil works
production rates excel sheet where you can find all the civil works related items along with the average
productivity per profession.

Civil works is one of the important trades in any new project. This paper includes the civil works productivity
rates for the following items:

1. Form works
2. Plaster works
3. Block works
4. Concrete works
5. Reinforcement work
6. Tiles works
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
1. CARPENTRY

Item No. CREW SIZE Hourly Production


Production Rate Per 10 hrs.
SM
FW FORMWORK
FW01 Formw ork to footings 2 CARPENTERS, 1 HELPER 1.2 12
FW02 Formw ork to isolated footings 2 CARPENTERS, 1 HELPER 1.6 16
FW03 Formw ork to rafts 2 CARPENTERS, 1 HELPER 1.4 14
FW04 Formw ork to rafts D>0.75m 2 CARPENTERS, 1 HELPER 1.8 18
FW05 Formw ork to tie beams 2 CARPENTERS, 1 HELPER 1 10
FW06 Formw ork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 12
FW07 Formw ork to Neck Columns 2 CARPENTERS, 1 HELPER 4
FW08 Formw ork to U/G Water tank 2 CARPENTERS, 1 HELPER 6
FW09 Formw ork to basement retaining w alls 2 CARPENTERS, 1 HELPER 9
FW10 Formw ork to columns (small size) 2 CARPENTERS, 1 HELPER 7
FW11 Formw ork to Columns (large size) 2 CARPENTERS, 1 HELPER 9
FW12 Formw ork to D/S beam internal (shallow ) 2 CARPENTERS, 1 HELPER 6
FW13 Formw ork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 7
FW14 Formw ork to D/S beam external (Shallow ) 2 CARPENTERS, 1 HELPER 4
FW15 Formw ork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 6
FW16 Formw ork to lift w alls single core 2 CARPENTERS, 1 HELPER 6
FW17 Formw ork to lift w alls multi core 2 CARPENTERS, 1 HELPER 8
FW18 Formw ork to slab decking (10ft) hourdi 2 CARPENTERS, 1 HELPER 1.6 16
FW19 Formw ork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 12
FW20 Formw ork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.2 12
FW21 Formw ork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1 10
FW22 Formw ork to staircase (non spiral) 2 CARPENTERS, 1 HELPER 4
FW23 Formw ork to balcony parapets 2 CARPENTERS, 1 HELPER 6
FW24 Formw ork to roof parapets 2 CARPENTERS, 1 HELPER 8

D = DEPTH
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
FW 25 shutter Manufacture for pile caps 1 CARPENTER + 1 HELPER 2.00 20
FW 26 shutter Fix for pile caps I CARPENTER + 1 HELPER 1.50 30
FW 27 Deshutter footings/pile caps 1 HELPER 6.00 60
FW 28 Shutter make column necks 1 CARPENTER + 1 HELPER 1.50 15
FW 29 Shutter fix column necks 1 CARPENTER + 1 HELPER 1.20 12
FW 30 Deshutter Column necks 1 HELPER 4.80 48
FW 31 Shutter make tie beams 1 CARPENTER + 1 HELPER 1.20 12
FW 32 shutter fix tie beams 1 CARPENTER + 1 HELPER 1.00 10
FW 33 Column shutter making 1 CARPENTER + 1 HELPER 1.20 12
FW 34 Column shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 35 Column deshuttering 1 HELPER 4.00 40
FW 36 Walls shutter making 1 CARPENTER + 1 HELPER 1.50 15
FW 37 Walls shutter fixing 1 CARPENTER + 1 HELPER 0.80 80
FW 38 De shutter Tie beam shutter 1 HELPER 4.00 40
FW 39 Wall formw ork deshuttering 1 HELPER 3.20 32
FW 40 Staircase formw ork making 1 CARPENTER + 1 HELPER 0.80 8
FW 41 staircase formw ork fixing 1 CARPENTER + 1 HELPER 0,8 8
FW 42 Staircase formw ork deshuttering 1 HELPER 1,6 16
FW 43 Drop beams formw ork making 1 CARPENTER + 1 HELPER 1.00 10
FW 44 Drop beams formw ork fixing 1 CARPENTER + 1 HELPER 0.80 8
FW 45 Drop beams formw ork stipping 1 HELPER 3.20 32
FW 46 suspended slab formw ork fixing 1 CARPENTER + 1 HELPER 1.20 12
FW 47 suspended slab formw ork deshutter 1 HELPER 5.00 50
FW 48 Formw ork fixing for sunshades 1 CARPENTER + 1 HELPER 0.70 7
FW 49 Parapet formw ork making 1 CARPENTER + 1 HELPER 1.20 12
FW 50 Parapets formw ork fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 51 Parapets formw ork stripping 1 HELPER 4.00 40
FW 53 Fixing of lintle formw ork 1 CARPENTER + 1 HELPER 0.50 5
FW 54 Deshutter lintle formw ork 1 HELPER 2.00 20
FW 55 Deck formw ork fixing 1 CARPENTER + 1 HELPER 1.50 15
FW 56 Deck Formw ork deshuttering 1 HELPER 6.00 60
FW 57 Pipe scaffolding erection for slab 1 SCAFFOLDER 0.85 85
FW 58 inverted beam shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 59 De-Shuttering Manholes, square - circular (Timber) 1 CARPENTER + 1 HELPER 4m2 40m2
FW 60 Manhole Shutter erection - square or circular(Timber) 1 CARPENTER + 1 HELPER 1,5 m2 15m2
2
FW 61 Metal Shutter for Manholes 1 CARPENTER + 1 HELPER 1m 10m2
2
FW 62 Metal Shutter for Precast Beams 2 CARPENTERS + 2 HELPERS 3M 30M2
2
FW 63 Metal Shutter for Pile caps 2 CARPENTERS + 2 HELPERS 3M 27M2
FW 64 Metal Shutters for Pile cap Beams 2 CARPENTERS + 2 HELPERS 3M2 30M2
2. Block work-Plastering
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
M MASONARY WORKS
MBW 01 Hollow Blockw ork (100, 150 & 200 mm)
1 MASON, 1 HELPER 12 Nos 120 NR
MBW 02 Hollow Blockw ork (large panels) 1 MASON, 1 HELPER 14 Nos. 140 NR
MBW 03 Solid blockw ork 1 MASON, 1 HELPER 9,5 95 NR
MBW 04 Solid Blockw ork as Raft forms 1 MASON, 1 HELPER 11 110 NR
MPL PLASTERWORK 1.2
MPL 01 Plaster (internal), w alls final coat 1 MASON, 1 HELPER 1.6 16 SM
MPL 02 Plaster (internal), w alls rush coat 2 HELPER 1.4 150 SM
MPL 03 Plaster (internal), w alls mesh 1 HELPER 1.8 100 SM
MPL 04 Plaster (internal), w alls hacking 1 HELPER 1 100 SM
MPL 05 Plaster (internal), w alls guide point 1 MASON, 1 HELPER 1.2 100 SM
MPL 06 Plaster (internal), w alls corner beads1 MASON, 1 HELPER 10 SM 100 SM
MPL 07 Plaster (external), w alls w ith grooves
1 MASON, 1 HELPER 10 SM 10 SM
MPL 08 Plaster (external), w alls w ithout grooves
1 MASON, 1 HELPER 1,2 12 SM
MPL 09 Plaster (external), w alls rush coat 2 HELPER 15 SM 150 SM
MPL 10 Plaster (external), w alls mesh 1 HELPER 10 SM 100 SM
MPL 11 Plaster (external), w alls hacking 1 HELPER 10 SM 100 SM
MPL 12 Plaster (external), w alls guide points1 MASON, 1 HELPER 10 SM 100 SM
MPL 13 Plaster (external), w alls corner beads
1 MASON, 1 HELPER 10 SM 100 SM
MPL 14 Plastering of Arches/Mullians 1 MASON, 1 HELPER 0.8 80
MPL 15 Floor screed 50mm thick 1 MASON, 1 HELPER 2 20
MPL 16 Roof screed 100 mm thick 1 MASON, 1 HELPER 1.5 15
MPL 17 Mosiac floor Tiles fixing 1 MASON, 1 HELPER 1.6 1.5
MPL 18 Floor Screed 25mm thick 1 Mason + 1 Helper 0,6 6
MCR CERAMIC WORKS
MCR 01 Ceramic tiles to w alls by mortar 1 MASON, 1 HELPER 1.2 8 SM
MCR 02 Ceramic tiles to w alls, mortar to corridors
1 MASON, 1 HELPER 1 9 SM
MCR 03 Ceramic tiles to w alls, cut pieces 1 MASON 2 20 SM
MCR 04 Ceramic tiles to w alls grouting 1 HELPER 5 50 SM
MCR 05 Ceramic tiles to w alls, by glue 1 MASON, 1 HELPER 1,2 12 SM
MCR 06 Ceramic tiles to w alls, corridors, by glue
1 MASON, 1 HELPER 1,3 13 SM
MCR 07 Ceramic tiles to w alls, by glue, cut pieces
1 MASON 2 20 SM
MCR 08 Ceramic tiles to w alls, by glue, grouting
1HELPER 5 50 SM
MCR 09 Ceramic tiles to floors 1 MASON, 1 HELPER 1 10 SM
MCR 10 Ceramic tiles to floors in halls 1 MASON, 1 HELPER 1,2 12 SM
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60
3. Masonry
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
MCR CERAMIC WORKS
MCR 13 Ceramic skirting by glue 1 MASON, 1 HELPER 2,5 M 25 METRE
MCR 14 Ceramic skirting by glue to halls, corridors 1 MASON, 1 HELPER 3M 30 METRE
MTW TILING WORKS
MTW 01 Mosiac / Terrazo tiles to roofs 1 MASON, 1 HELPER 1,6 16 SM
MTW 02 Mosiac / Terrazo tiles to floors 1 MASON, 1 HELPER 1,4 14 SM
MTW 03 Mosiac skirting to halls 1 MASON, 1 HELPER 2,5 25 METRE
MTW 04 Mosiac skirting flush / recessed 1 MASON, 1 HELPER 1,4 14 METRE
MTW 05 Grouting / sealing to roof / floor tiles 1 HELPER 2,5 25 METRE
MKP KERBING / BLOCK PAVING WORKS
MKP00 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE
MKP01 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE
MKP02 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 METRE
MKP03 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 METRE
MKP04 Interlock paving on pre prepared sub - base 1 MASON, 1 HELPER 2 SM
MKP05 Screed w orks including preparation 1 MASON, 1 HELPER 1,5 15 SM
MKP06 Haunching ot Kerb Base (Mixing Truck) 1 MASON, 1 HELPER 10 M 100M
DRW MANHOLE/ DRAINAGE CONSTRUCTION
DRW 01 Excavation for drains / manholes 1 HELPER 5 CM
DRW 02 Backfill to drains / manholes 1 HELPER 10 CM
DRW 03 Blockw ork to manholes 1 MASON, 1 HELPER 2 NOS
DRW 04 Plaster to manholes 1 MASON, 1 HELPER 2 NOS
DRW 05 Benching to manholes 1 MASON, 1 HELPER 4 NOS
DRW 06 Fix covers to manholes 1 MASON, 1 HELPER 2 NOS
DRW 07 Fix gulley traps 1 MASON, 1 HELPER 1 NO
DRW 08 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240M
MLW MISCELLANEOUS LABOUR WORKS
MLW01 Bitumen paint to concrete blockw ork surfaces 1 HELPER 4 40 SM
MLW02 Bitumin painting Bases / piles 1 HELPER 7.00 70
MLW03 Hacking of concrete surfaces 1 HELPER 5 50 SM
MLW04 fixing of flexcell sheets 1 HELPER 6 SM
MLW05 pile cutting/dressing 1 HELPER 1 NO
MLW06 pile cutting/dressing (small diameter) 1 HELPER 2 NOS
MLW07 Vertical sealant (12 mm) 1 HELPER 2,5 25 METRE
MLW08 Horizontal sealant (12 mm) 1 HELPER 5 50 EMTRE
MLW09 Roof preparation for lw concrete 1 MASON, 1 HELPER 5 50 SM
MLW10 Angle fillet fixing 1 MASON, 1 HELPER 4 40 EMTE
MLW11 Hourdi block shifting and fixing to slab 2 HELPER 20 200 NOS
MLW12 Polythene sheet fixing 1 HELPER 3m 30
MLW13 Shaping of Soil Blinding 1 MASON + 1 HELPER 1M 10M
MLW14 Protection Board installation 1 CARPENTER + 1 HELPER 8M2 80M2
MCW MISCELLANEOUS CARPENTARY WORKS
MCW 01 A/C subframe manufacture / fixing 1 CARPENTER 5 NOS
MCW 02 Door subframe manufacture / fixing 1 CARPENTER 4 NOS
MCW 03 Water bar fixing 1 CARPENTER 2M 20 METRE
4. Concreting
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
CPW CONCRETE PLACEMENT WORKS
CPW01 Concrete to pile caps by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
Standard rate 1 man 1 hr. 10m3
CPW02 Concrete to PCC blinding (100 mm thick) 1 MASON, 10 HELPERS 27 CM
CPW03 Concrete to slabs/beams, by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
CPW04 Concrete to slabs / beams by crane 1 MASON, 6 HELPERS, 0.5 OPERATOR 8,10 27 CM
CPW05 Concrete to w alls / columns, by pump 4 MASONS, 16 HELPERS, 2 CARPENTERS 1.2 81 CM
CPW06 Concrete by site mix 1 MASON, 12 HELPERS , 0.5 CARPENTER 1.6 9 CM
CPW07 Concrete Columns 8 HELPERS 1.40 10
CPW08 Concrete suspended slab (pump) 3 MASONS + 6 HELPERS 1.80 150
CPW09 Concrete parapets/staircases 8 HELPERS 1.00 7
CPW10 Blinding concrete 50 mm (readymix) 1 MASON + 4 HELPER 8,0 80
CPW11 Blinding concrete 50 mm (sitemix) 1 MASON + 8 HELPER 1.00 10
CPW12 Concrete footings & pile caps 1 MASON + 4 HELPER 12.00 120
CPW13 Concrete tiebeams, ground beams 1 MASON + 5 HELPER 6.00 60
CPW14 Concrete column necks 8 HELPER 1.50 15
CPW15 Concrete Ground slab 3 MASONS + 6 HELPER 1,5 15
CPW16 Concrete to precast slabs, beams 2 MASONS + 1 HELPER 3m3 30 M3
GLW GENERAL LABOUR WORKS
GLW01 Unloading reinforcement ((Flat Bed Truck) 4 HELPERS 2 Nos
GLW02 Loading reinforcement to slab (With Crane) 4 HELPERS (Flat Bed Truck loads) 40 Nos. 2 Nos
GLW03 Loading blockw ork to site (w ith Wheel Burrow ) 1 HELPER 400 Nos.
GLW04 Loading mortar to site location
GLW05 Mixing mortar for distribution 0, 3 L mixer 4 HELPER 6M3
GLW06 Site mixing of ready mix for distribution Hand mix 3M3
GLW07 Loading ready mix to site location
NTRA NON TARGET RELATED ACTIVITES
NTRA01 Stacking of formw ork 2 HELPERS
NTRA02 Curing of Substructure w orks 2 HELPERS
NTRA03 Curing of beams / slabs Hessiant Water 2 HELPERS
NTRA04 Curing of columns (Hessiant Water) 1 MASON + 2 HELPERS 1.6 (L.M) 36 M
NTRA05 Builders w ork make good chases 1.2 (L.M)
NTRA06 Site cleaning 1 HELPER 25 250 M2
NTRA07 Repairs to finished w orks 1

Item No. CREW SIZE NON MEASURABLE


NTRA08 Maintenance of site services 2 HELPERS
NTRA09 Operators for mixers 2/MIXER
NTRA10 Operators for compaction equipment 1 UNIT
NTRA11 Office boy ARABTEC 1 / CONSULTANT 1
NTRA12 Watchman 2 MIN
NTRA13 Storekeeper 1/SHIFT
5. Reinforcement
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit KG
RF REINFORCEMENT
RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 25 250
RF 02 Fix Rebar to w alls, columns, beams, solid slabs 1 STEEL FIXER 20 200
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 18 180 <16M
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15 50
RF 05 Fix rebar to hidden beams 1 STEEL FIXER 20 200

RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 78 780


RF 02 Fix Rebar to w alls, columns, beams, solid slabs 1 STEEL FIXER 38 380
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 35 350 > 16M
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15 150
RF 05 Fix rebar to hidden beams 1 STEEL FIXER 420

RFC 01 Steel cutting and bending 18.25 mm 1 STEEL FIXER 50.00 500
RFC 02 Steel cutting and bending 8 - 16 mm 1 STEEL FIXER 40.00 400

EXCAVATION
EX 1 Manual Excavation 1 HELPER 3M3
EX 2 Backfill + levelling 1HELPER 5 M3
Shaping of sloped earth for blinding for bases
EX 3 1 MASON + 2 HELPER 6 LM/Day
including compaction

6. Tilling
Size. (Cm s) Location Area Manpow er Production Rate Rem arks
(Sqm . Per day)

30 X 30 Floor Kitchen 1 Mason, 1 Helper 14 Residential Area by Sub-Contractor


30 X 30 Floor w ith pattern Corridor 1 Helper, 2 Masons 10 Residential Area by Sub-Contractor
40 X 40 Floor Bed room 1 Mason, 1 Helper 22-25 Residential Area by Sub-Contractor
20 X 20 Floor Store (small area) 1 Mason, 1 Helper 10 Residential Area by Sub-Contractor
30 X 60 Floor Bathroom 2 Mason, 1 Helper 6 Residential Area by Sub-Contractor
30 X 30 Floor + Wall Bathroom 2 Mason, 1 Helper 5
10 X 10 Wall Kitchen 1 Mason, 1 Helper 8-9 Residential Area by Sub-Contractor
30 X 60 Wall Corridor 1 Mason, 1 Helper 14-15 Residential Area by Sub-Contractor
30 X 30 Wall Bathroom 2 Mason, 1 Helper 7 Residential Area by Sub-Contractor
Residential Area by Sub-Contractor

Notes:

1. 1 Day = 10 hrs.

2. Gang Size:

1 Mason + 1 Helper for Kitchen and Bedroom.

2 Mason + 1 Helper for Bathroom.