REGGIE BERT R. SINTOS B.S.

ARCHITECTURE 3-A BUILDING TECHNOLOGY 4

Column1 Column2 Column3 QTY. UNIT UNIT COST MATERIAL COST LABOR COST TOTAL COST
PROJECT: TWO STOREY RESIDENCE
SUBJECT: BILLS OF MATERIALS & COST ESTIMATE
I. EARTHWORKS QTY. UNIT UNIT COST MATERIAL COST LABOR COST TOTAL COST

A. EXCAVATION 117 CU.M PHP 300.00 PHP 35,100.00


B. SOIL POISONING (LENTREK) 1 LOT PHP 7,000.00 PHP 7,000.00
C. BACKFILL 46.8 CU.M PHP 250.00 PHP 11,700.00
PHP -
II. CONCRETE WORKS PHP -
CEMENT, PORTLAND 221.886 BAGS PHP 210.00 PHP 46,596.06
SAND, RIVER 49.9108 CU.M PHP 500.00 PHP 24,955.40
GRAVEL, 3/4"SCREENED 24.654 CU.M PHP 500.00 PHP 12,327.00
REBARS PHP -
10MMDIA X 6M RSB (DEF.) 1473 PCS. PHP 110.00 PHP 162,030.00
12MMDIA X 6M RSB (DEF.) 207 PCS. PHP 160.00 PHP 33,120.00
16MMDIA X 6M RSB (DEF.) 548 PCS. PHP 270.00 PHP 147,960.00
10MMDIA X 7.5M RSB (DEF.) PCS. PHP -
20MMDIA X 6M RSB (DEF.) PCS. PHP -
20MMDIA X 7.5M RSB (DEF.) PCS. PHP -
#16 G.I. TIE WIRE 323.4 KEGS PHP 85.00 PHP 27,489.00
PHP -
FORM PHP -
COCO-LUMBER B.F. PHP 18.00 PHP -
1/2"THK ORD. PLYWOOD PCS PHP 520.00 PHP -
CWN, ASSTD. BOXES PHP 1,600.00 PHP -
#16 G.I. TIE WIRE ROLLS PHP 2,800.00 PHP -
PHP -
III. MASONRY/WALL PHP -
FOR PLASTERING
CEMENT, PORTLAND 197 BAGS PHP 210.00 PHP 41,370.00
SAND,FINE,RIVER 16.36992 CU. M PHP 500.00 PHP 8,184.96
CEMENT, PORTLAND 242.94262 BAGS PHP 210.00 PHP 51,017.95
SAND, RIVER 20.24516 CU. M PHP 500.00 PHP 10,122.58
MIXED-GRAVEL 0 CU. M PHP 500.00 PHP -
#16 G.I. TIE WIRE 122.4 KEGS PHP 85.00 PHP 10,404.00
10MM DIA X 6M RSB (DEF.) 320 PCS. PHP 110.00 PHP 35,200.00
12MM DIA X 7.5 RSB (DEF.) PCS. PHP 160.00 PHP -
4"CHB PCS. PHP 7.00 PHP -
6"CHB 5920 PCS. PHP 10.00 PHP 59,200.00
PHP -
IV. SLAB ON FILL PHP -
CEMENT, PORTLAND 385.4 BAGS PHP 210.00 PHP 80,934.00
SAND, RIVER 32.125 CU. M PHP 500.00 PHP 16,062.50
MIXED-GRAVEL 34.625 CU. M PHP 500.00 PHP 17,312.50
#16 G.I TIE WIRE KEGS PHP 85.00 PHP -
PHP -
V. ROOF FRAMING PHP -
TRUSSES/PURLINS PHP -
PHP -
VI. ROOFING (APO) PHP -
DURA CURB 0.4 mm THK PHP -
DURA RIB 0.4 mm THK PHP -
#36 GUTTER/ PHP -
END FLASHING 0.5 mm THK PHP -
0.5mm THK. FOIL INSULATION PHP -
(1 SIDED) PHP -
POLYCARBONATE PHP -
SPANDREL w/ JOIST PHP -
VENTS MOULDING PHP -
PHP -
VII. CARPENTRY PHP -
PHP -
A. CELING PHP -
SINGLE FURRING CHANNEL (0.8MM) PHP -
3.5 HARDIFLEX PHP -
DOUBLE FURRING CHANNEL (0.8MM) PHP -
WALL ANGLE PHP -
CARRYING CHANNEL PHP -
BLIND RIVETS (5/32" X 5/8") PHP -
METAL W-CLIF PHP -
#16 G.I. TIE WIRE PHP -
SANDING PAPER # 100 PHP -
PHP -
B. STAIR, BALCONY w/ RAILINGS PHP -
PHP 35,000.00
VIII. FINISHING PHP -
A.PLASTERING PHP -
CEMENT, PORTLAND PHP -
SAND, RIVER PHP -
PHP -
B. TILEWORKS (MARIWASA) PHP -
(GROUND) PHP -
60X 60 CM UNGLAZED (WHITE) PHP -
40X 40 CM UNGLAZED PHP -
30X 30 CM UNGLAZED PHP -
(SECOND FLOOR) PHP -
60X 60 CM UNGLAZED (WHITE) PHP -
40X 40 CM UNGLAZED PHP -
30X 30 CM UNGLAZED PHP -
PHP -
C. T. & B TYPICAL PHP -
(@SECOND FLOOR BEDROOM) PHP -
20X20cm UNGLAZED PHP -
20X30cm GLAZED PHP -
7.5x 20cm BORDER TILES PHP -
PHP -
D. MASTER'S T&B PHP -
20X 20cm UNGLAZED TILES PHP -
20x 30cm GLAZED PHP -
7.5x 20cm LISTEL PHP -
PHP -
CEMENT PORTLAND PHP -
SAND PHP -
CEMENT GROUT PHP -
PHP -
IX. DOORS AND WINDOWS PHP -
DOOR w LOCKSET (DELTAWOOD) PHP -
DOCU FINISH (DOORS) PHP -
PDA 2.10 X .90 MAIN DOOR PHP -
PDD 2.1X 0.90 PHP -
PDD 2.1X 0.80 PHP -
2"X 6" DOOOR JAMB PHP -
PVC DOOR 0.90m.(MASTERS) PHP -
PVC FLUSHDOOR (.60M) PHP -
FLUSH DOOR PHP -
SLIDING DOOR (2.10mx 3.20)\ PHP -
ALUM. WINDOW (2.10mx 3.20m) PHP -
ALUM. WINDOW (2.10mx 2.40m) PHP -
ALUM. WINDOW (.80mx 2.40m) PHP -
ALUM. WINDOW (.80mx 1.20m) PHP -
ALUM. WINDOW (1.0mx 1.0m) PHP -
ALUM. WINDOW (.60mx 2.40m) PHP -
ALUM. WINDOW (.60mx 1.00m) PHP -
ALUM. WINDOW (.60mx .60m) PHP -
ALUM. WINDOW (3.00mx 2.40m) PHP -
ALUM. WINDOW (.26mx 1.00m) PHP -
ALUM. WINDOW (.80mx 1.20m) PHP -
WINDOW (NEW CENTURY)

TOTAL: PHP 838,085.95