METHODOLOGY OF KERB CONSTRUCTION

OBJECTIVE
 The objective is to provide Kerb in Shoulder & Median portions.
SCOPE
 To provide Kerb Foundation in Median Portion of the Highway
 To provide Kerb & Kerb Channel in the median and shoulder portion.
REFERENCE
 agreement specification.
 MOSRT&H
 Drawing and Mix Design for Kerb Concrete
RESPONSIBILITY
 Highway Engineer and Quality Material Engineer
PROCEDURE
 As per the drawing and Mix Design for Kerb Concrete, laying of Kerb is carried out.
 Kerb Foundation is laid by suitably placing the side shuttering.
 Kerb is laid by Kerb Casting machine.
 The line and level shall be maintained and shall be within allowable tolerances.
DOCUMENTATION:

 Test results
 Check List
 Level Book
HEALTH, SAFETY AND ENVIRONMENT

All employees working within the limit of this project shall follow the guidelines / rules &
regulations as mentioned in HSE PLAN.

QUALITY ASSURANCE AND QUALITY CONTROL

Quality Assurance & Quality Control of this work shall be as per Quality Assurance Manual
and corresponding Quality Assurance Plan. All quality records as appended to this
procedure shall be maintained in appropriate formats.

MCL-4180-QAM Rev. R 0 Page 166


MCL-4180-QAM Rev. R 0 Page 166