Вы находитесь на странице: 1из 2

Gas-Insulated Transmission Lines (GIL)

Introduction The gas-insulated transmission line tech-


nique is a highly reliable system in terms
1 of mechanical and electrical failures. Once
For high-power transmission systems a system is commissioned and in service,
where overhead lines are not suitable, it runs reliably without any dielectrical or
alternatives are gas-insulated transmission mechanical failures as experience over the
lines (GIL). course of 20 years shows. For example,
The GIL exhibits the following differences one particular Siemens GIL will not under-
2 in comparison with cables: go its scheduled inspection after 20 years
of service, as there has been no indication
■ High power ratings
of any weak point.
(transmission capacity up to 3000 MVA
Fig. 57 shows the arrangement of six
per System)
phases in a tunnel.
■ High overload capability
3 ■ Suitable for long distances
(100 km and more without compensa- Basic design
tion of reactive power) In order to meet mechanical stability crite-
■ High short-circuit withstand capability ria, gas-insulated lines need minimum Fig. 57: GIL arrangement in the tunnel of the Wehr
(including internal arc faults) cross-sections of enclosure and conductor. pumped storage station
4 ■ Possibility of direct connection to gas- With these minimum cross-sections, high (4000 m length, in service since 1975)
insulated switchgear (GIS) and gas-insu- power transmission ratings are given.
lated arresters without cable entrance Due to the gas as insulating medium, low
fitting capacitive loads are given so that compen-
■ Multiple earthing points possible sation of reactive power is not needed,
even for long distances of 100 km and
5 ■ Non-flammable, no fire risk in case of
more.
failures
The innovations in the latest Siemens GIL
development are the considerable reduc-
tion of costs and the introduction of buried
laying technique for GIL for long-distance
6 power transmission.
SF6 has been replaced by a gas mixture
of SF6 and N2 as insulating medium.

Siemens experience
7
Back in the 1960s with the introduction of
sulphur hexafluoride (SF6) as an insulating
and switching gas, the basis was found for
the development of gas-insulated switch-
gear (GIS).
8 On the basis of GIS experience, Siemens
developed SF6 gas-insulated lines to trans-
mit electrical energy too. In the early 1970s
initial projects were planned and imple-
mented. Such gas-insulated lines were Fig. 58: Long-term test set-up at the IPH, Berlin
9 usually used within substations as busbars
Reduction of SF6 content
or bus ducts to connect gas-insulated The characteristics of N2/SF6 gas mixtures
switchgear with overhead lines, the aim Several tests have been carried out in show that with an SF6 content of only
being to reduce clearances in comparison Siemens facilities as well as in other test 15–25% and a slightly higher pressure,
to air-insulated overhead lines. laboratories world-wide since many years. the insulating capability of pure SF6 can be
Implemented projects include GIL laying in attained. Besides, the arcing behavior is
Results of these investigations show that
10 tunnels, in sloping galleries, in vertical
the bulk of the insulating gas for industrial improved through this mixture. Tests have
shafts and in open air installation. proven that there would be no external
projects involving a considerable amount
Flanging as well as welding has been ap- damage or fire caused by an internal fail-
of gas should be nitrogen, a nontoxic nat-
plied as jointing technique. ure.
ural gas.
However, another insulating gas should be The technical data of the GIL are shown in
added to nitrogen in order to improve the Fig. 59.
insulating capability and to minimize size
and pressure. A N2/SF6 gas mixture with
high nitrogen content (and sulphur hexa-
fluoride portion as low as possible) was
finally chosen as insulating medium.

2/38 Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition
Gas-Insulated Transmission Lines (GIL)

Technical data
1
Rated voltage up to 550 kV
Rated current lr 2000 – 4600 A
Transmission 1500 – 3000 MVA
capacity 2
Capacitance ≈ 60 nF/km
Typical length 1–100 km
Gas mixture SF6/N2 10%/90%
ranging from up to 35%/65% 3

D
Laying directly buried Fig. 60: GIL laying technique

in tunnels/ clean assembly and productivity is enhan- dures for power cables. The test proce-
sloping galleries/ ced by a high level of automation of the dure consisted of load cycles with doubled
voltage and increased current as well as
vertical shafts overall process.
frequently repeated high-voltage tests.
4
open air Anti-corrosion protection The assembly and repair procedures under
installation Directly buried gas-insulated transmission realistic site conditions were examined
lines will be safeguarded by a passive and too. The Siemens GIL is the first one in
Fig. 59: GIL technical data active corrosion protection system. The the world that has passed these tests,
passive corrosion protection system com- without any objection. Fig. 58 shows the 5
Jointing technique prises a PE or PP coating and assures at test setup arranged in a tunnel of 3 m di-
In order to improve the gas-tightness least 40 years of protection. The active cor- ameter, corresponding to the tunnel used
and to facilitate laying, flanges have been rosion protection system provides protec- in Berlin for installing a 420 kV transmis-
avoided as jointing technique. Instead, tion potential in relation to the aluminum sion link through the city.
welding has been chosen to join the vari- sheath. An important requirement taken
ous GIL construction units. into account is the situation of an earth
References 6
fault with a high current of up to 63 kA to Siemens has gathered experience with
The welding process is highly automated,
earth. gas-insulated transmission lines at rated
with the use of an orbital welding machine voltages of up to 550 kV and with system
to ensure high quality of the joints. This Testing lengths totalling more than 30 km.
orbital welding machine contributes to high
The GIL is already tested according to The first GIL stretch built by Siemens was 7
productivity in the welding process and
the report IEC 61640 (1998) “Rigid high- the connection of the turbine generator/
therefore speeds up laying. The reliability
voltage, gas-insulated transmission lines pumping motor of a pumped storage
of the welding process is controlled by an
for voltages of 72.5 kV and above.” station with the switchyard. The 420 kV
integrated computerized quality GIL is laid in a tunnel through a mountain
assurance system. Long-term performances and has a length of 4000 m (Fig. 57). This
Laying Besides nearly 25 years of field experience connection was commissioned in 1975 at 8
with GIL installations world wide, the long- the Wehr pumped storage station in the
The most recently developed Siemens term performance of the GIL for long-dis- Black Forest in Southern Germany.
GILs are scheduled for directly buried tance installations has been proven by the
laying. For further information please contact:
independent test laboratory IPH, Berlin,
The laying technique must be as compat- Fax: ++ 49-9131-7-3 44 98
ible as possible with the landscape and
Germany and the Berlin power utility 9
BEWAG according to long-term test proce- e-mail: evhgis@erls04.siemens.de
must take account of the sequence of
seasons. The laying techniques for pipe-
lines have been improved over many years
and they are applicable for GIL as a ”pipe-
line for electrical current“too. However, 10
the GIL needs slightly different treatment
where the pipeline technique has to be
adapted.The laying process is illustrated
in Fig. 60.
The assembly area needs to be protected
against dust, particles, humidity and other
environmental factors that might disturb
the dielectric system. Clean assembly
therefore plays an important role in setting
up cross-country GILs under normal envi-
ronmental conditions. The combination of Fig. 61: Siemens lab prototype for dielectric tests

Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition 2/39

Вам также может понравиться