HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINING CONTROL

Name of Job Department : Prepared By : Checked By :- Approved By :


LIFTING WORK (Cont'd) CONSTRUCTION

HAZARD IDENTIFICATION RISK ASSESSMENT Recommended


Action/Additional
Job Activity Hazard Hazard Character Current Risk Control Probability Severity Risk Control

Heat stroke from Workers wear hard hat; Workers


Near miss/ unsafe act/ Additional control shall be
prolonged exposure to encourage to take a short break 3 1 3
unsafe condition proposed when necessary
sunlight and dehydration. where applicable.

Allowed to carry only where


Sudden body injuries due Near miss/ unsafe act/ one's can; Required assistant Additional control shall be
3 1 3
to excessive lifting. unsafe condition when needed; Use crane or lifting proposed when necessary
Working
machinery.
environment
Physical injuries caused
Briefing By SHO on safety
by trip and fall during Minor injury/illness (M.C Safe working procedure; Closed
2 3 6 awareness. Additional control
lifting and carrying between 5 to 14 days) supervision. shall be made if necessary.
material.
Near miss/ unsafe act/ Training and proper planning of Additional control shall be
Space constraint. 3 1 3
unsafe condition work; Safe working procedure. proposed when necessary

Provide a proper PMA


Crane boom Fatality or permanent Briefing By SHO on safety
certificate; Signalman monitored
failure/collapse due to disability or 2 5 10 awareness. Additional control
lifting process; Close supervision; shall be made if necessary.
overloading. irreversible illness
Provide barrier and signage.

Crane topple due to Fatality or permanent Crane park at solid platform and Briefing By SHO on safety
overweight/unstable disability or outrigger support is fully used; 2 5 10 awareness. Additional control
Working with ground. irreversible illness Close supervision. shall be made if necessary.
lifting/hoisting
machinery. First aid cases/medical
Training and regular toolbox talk; Additional control shall be
Manual handling. treatment (M.C 2 2 4
Closed supervision. proposed when necessary
between 1 to 3 days),

Minor damage (No or


Material damage due to Provide safe handling Briefing By SHO on safety
less disruption, repair
falling/mishandling during procedure; Provide specific 2 3 6 awareness. Additional control
cost > RM1,000 and shall be made if necessary.
storage. storage room.
< RM10,000)