Вы находитесь на странице: 1из 4

Date: 21-8-2019

Ref. No.: G.I./05/0801989-V02


To: A&A .Co
Dear Eng. Qais Abdallah

Subject: Quotation for Geotechnical Investigation for Almak Nimer Bridge Approach Khartoum.

Thank you for your invitation to carry out soil study at the above mentioned site. ESD will mobilize one soil
mechanic drilling rig and personnel to site. ESD will drill Two (2) boreholes down to 40.0m depth as per
requsted.

Disturbed soil samples (DS) will be taken each one meter from auger cuttings. Undisturbed soil samples
(UDS) will be taken each 1.5 meter from cohesive soil whenever soil conditions allowed. Standard penetration
test (SPT) will be conducted in cohesinless soil strata at 1.5 meter intervals and whenever it is difficulties to
get UDS samples. ESD will run laboratory tests on the soil samples, these tests will include classification tests,
strength tests, and chemical tests.
The geotechnical report will be produced, and will include analysis of the field and laboratory data and
foundations recommendations.
The cost of this job is Lump Sum SDG 161,548 only
(Only One Hundred, Sixty One Thousand & Five Hundred and Forty eight Sudanese Geneh Without VAT ).

Payments should be made as follows


Description % of total Amount SDG Due date
1. Advance Payment 50% 80,773.75 On signing contract
2. Intermediate Payment 30% 48,464.25 On completion of field work
3. Final Payment 20% 32,309.50 On submiton of final report

Notes:

The client will be responsible of the accessibilty to site and preparation of the location of boreholes to allow standing of drilling rigs
The standby rate will be applied if any delays are caused by the client
The estimated time for finishing this job is about 2 to 3 weeks
This offer is valid for Two weeks only.

Eng. Omer Babiker Alhaj


Projects Manager
ESD
Rate Cost
Item No. Description Unit Quantity
SDG SDG

1 Mobilisation and Demobilisation L.S 1 10,000 10,000

2 Field Work L.S 1 105,750 105,750

3 Laboratory tests L.S 1 34,300 34,300

Preparation of a final report with bore hole logs, test


4 reports, laboratory results and Foundation L.S 1 20,000 20,000
recommendations

5 Standby for rig and staff per day Day Rate only 5,000

Sub-total 170,050

Discount 5% 8,503

Grand Total 161,548

2
Rate Cost
Item No. Description Unit Quantity
SDG SDG
1 Mobilisation and Demobilisation LS 1 10,000.00 10,000.00
2 Movement between Offshore boreholes No. rate only 2000
3 Movement between Onshore boreholes No. rate only 750
4 Gedetic Survey for boreholes No. rate only 250.00
5 Onshore Rotary drilling in soil,90° from horizontal,
full core recovery, including setting and removal of
casing
5.1 to a depth of 10 m(90°) m 20 500.00 10,000.00
5.2 to a depth between 10 and 20 m(90°) m 20 600 12,000.00
5.3 to a depth > 20m(90°) m 10 750 7,500.00
6 Onshore rotary drilling in bedrock, 90° from
horizontal, core recovery, beneath a soil cover,
including setting and removal of casing, core
sampling, core boxes
6.1 to a depth between 0 and 30 m(90°) m 10 1500 15000
6.2 to a depth between 30 and 60 m(90°) m 20 2000 40000
7 SPT and or UDS No. 53 250.00 13,250.00
8 Excavation of Test Pit No. rate only 4000
12 Geophyical Test
12.01 Electrical Resistivity No 0 15000
9 Foundation Settement Observation Month rate only 67000
10 Sampling of soil
10.1 Taking disturbed soil samples (weight 2 kg) including
NO 80 100.00 8,000.00
storing and transport to the local laboratory.
10.2 Taking disturbed soil samples (weight 20 kg) including NO rate only 50.00
storing and transport to the local laboratory.
10.3 Taking undisturbed block samples (150 x 150 x 100mm)
from soil including storing and transport to the local NO rate only 300.00
laboratory.
11 Laboratory tests of rock samples
11.1 Moisture content NO rate only 30.00
11.2 Porosity NO rate only 60.00
11.3 Density NO rate only 30.00
11.4 Absorption test NO rate only 60.00

3
Rate Cost
Item No. Description Unit Quantity
SDG SDG
11.5 Point load test on rock core samples and on irregular
NO rate only 500
rock fragments.
11.6 Unconfined compression test on rock core samples NO rate only 1000
11.7 (Ratio of sample
Los Angeles test.height to diameter >2) NO rate only 200.00
11.8 Magnesium sulphate soundness test. NO rate only 600.00
11.9 Potential reactivity test (Accelerated Method). NO rate only 1,000.00
11.10 Potential reactivity test (Mortar-Bar Method). NO rate only 1,000.00
11.11 Petrographic and X-ray analyses. NO rate only 1,500.00
11.12 Wetting-drying test. NO rate only 80.00
11.13 Rock shear test. NO rate only 200.00
11.14 Brasilian test NO rate only 400.00
11.15 Cerchar abrasivity test NO rate only 700.00
11.16 Swelling test NO rate only 500.00
11.17 Shape index NO rate only 100.00
12 Laboratory tests of soil samples
12.1 Grain size by sieving NO 53 200.00 10,600.00
12.2 Grain size by sieving and sedimentation NO rate only 200.00
12.3 Natural water content NO rate only 100
12.4 Specific gravity NO rate only 50.00
12.5 Organic matter NO rate only 400.00
12.6 Atterberg limits. NO 53 200.00 10,600.00
12.7 UU-triaxial test (specimen diameter 38- 76 mm). Set 2 1,800.00 3,600.00
12.8 CU-triaxial test (specimen diameter 38 mm - 76mm). Set rate only 2,000.00
12.9 CD-triaxial test (specimen diameter 38mm - 76mm). Set rate only 2,500.00
12.10 Swelling Pressure test NO 2 1,500.00 3,000.00
12.11 Consolidation Test NO 2 2,000.00 4,000.00
12.12 Permeability test on cohesive soil. NO rate only 250.00
12.13 Permeability test on cohesionless soil. NO rate only 100.00
12.14 X — ray investigations and DTA of clay minerals NO rate only 1,200.00
12.15 Direct shear test, slow (specimen size 50 x 50 mm or
Set rate only 1,000.00
100 x 100 mm).
12.16 Direct shear test, fast (specimen size 50 x 50 mm or 100 rate only
Set 250.00
X 100 mm).
12.17 Chemical evaluation of dispersivibility NO rate only 200.00
12.18 Pinhole test NO rate only 100.00
12.19 Crumb test NO rate only 200.00
12.2 Swelling test NO rate only 200.00
12.21 Shrinkage test NO rate only 100.00
12.22 Chemical analysis of soil. NO 1 2,500.00 2,500.00
13 Chemical analysis of water samples including NO rate only 1,500.00
sampling and transport
14 Standby rate Day rate only 4,000.00
15 Preparation of a final report with bore hole logs, test
reports, laboratory results and Foundation No 1 20,000.00 20,000.00
recommendations
Grand Total
170,050.00