LISTA DE MATERIALES E INSUMOS

PROYECTO : CERCO PERIMETRICO Y LOSA DEPORTIVA COLCAWASI.


OBRA : CERCO PERIMETRICO Y LOSA DEPORTIVA. PROPIETARIO :
JUCA - AYACUCHO.

No. DESCRIPCIO N UNID. CANT. P.UNIT. P.PARCIAL.

A: MANO DE OBRA 8,884.00


01 OPERARIO hh 384.00 6.00 2,304.00
02 OFICIAL hh 405.00 4.00 1,620.00
03 PEON hh 1,600.00 3.10 4,960.00

B: MATERIALES DE CONSTRUCCION 27,088.50


01 ACERO DE REFUERZO DE 5/8". Varilla 30.00 43.20 1,296.00
02 ACERO DE REFUERZO DE 1/2". Varilla 20.00 28.50 570.00
03 ACERO DE REFUERZO DE 3/8". Varilla 15.00 16.20 243.00
04 ACERO DE REFUERZO DE 1/4". Varilla 10.00 7.20 72.00
05 ALAMBRE NEGRO # 8 kg 50.00 4.50 225.00
06 ALAMBRE NEGRO # 16 kg 50.00 4.50 225.00
07 ARCOS PARA FULBITO und 2.00 1,800.00 3,600.00
08 ARENA FINA m3 4.00 60.00 240.00
09 ARENA GRUESA m3 15.00 50.00 750.00
10 ASFALTO RC-250 gal 40.00 12.00 480.00
11 CEMENTO PORTLAND TIPO I (42.5 kg) bls 400.00 21.50 8,600.00
12 CLAVOS PARA MADERA CON CABEZA DE 3" kg 25.00 4.50 112.50
13 HORMIGON DE RIO m3 60.00 40.00 2,400.00
14 LADRILLO KING KONG DE ARCILLA 9 X 14 X 24 cm und 4,000.00 0.43 1,720.00
15 MADERA TORNILLO p2 300.00 3.80 1,140.00
16 PIEDRA CHANCADA DE 1/2" m3 15.00 70.00 1,050.00
17 PIEDRA GRANDE DE 8" m3 4.00 40.00 160.00
18 PIEDRA MEDIANA DE 4" m3 15.00 40.00 600.00
19 PINTURA TRANSITO gln 2.00 50.00 100.00
20 POSTE PARA NED DE FoGo DE 3" und 2.00 120.00 240.00
21 PUERTA METALICA CON PLANCHA m2 2.00 1,620.00 3,240.00
22 YESO EN BOLSAS DE 25 kg bls 5.00 5.00 25.00

C: EQUIPOS Y MAQUINARIAS: 4,027.50


01 ALQUILER DE ANDAMIO DE METAL Y TABLAS est 1.00 197.50 197.50
02 CARRETILLA TIPO BUGUIE unid 4.00 150.00 600.00
03 PALAS TIPO CUCHARA unid 6.00 25.00 150.00
04 CAMION VOLQUETE 12 m3 (Eliminación de Desmonte) dm 2.00 900.00 1,800.00
05 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP dm 10.00 50.00 500.00
06 MEZCLADORA DE CONCRETO DE 9 -11p3 dm 6.00 50.00 300.00
07 NIVEL DE INGENIERO dm 10.00 20.00 200.00
08 TEODOLITO dm 2.00 50.00 100.00
09 VIBRADOR DE CONCRETO 4 HP 1.50" dm 6.00 30.00 180.00
COSTO DIRECTO DE LA OBRA 40,000.00
GASTOS GENERALES (10%) 4,000.00
COSTO TOTAL DE LA OBRA: 44,000.00