Owner’s Engineer
Contractor
Sub-Supplier
CONTENTS
1 PREFACE............................................................................................................................. 2
2 REFERENCE ....................................................................................................................... 2
3 RESPONSIBILITIES .......................................................................................................... 2
4 MATERIALS ....................................................................................................................... 2
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 1 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
1. PREFACE
This Method Statement describes the steps that will be followed for the Plastering works within
the construction area in order to meet the technical standards and EHS requirements of Vinh Tan
4 Thermal..
This procedure shall be read in conjunction with contract specification where applicable. All
works shall be as per approved shop drawing.
• The objective of this method statement is to describe the methodology for the works
associated with the plastering works.
• Apply Plastering including Accessories as per required, Curing etc. and other required Works
for Plastering Works.
3. RESPONSIBILITIES
• EHS Manager will ensure coordination with Site Engineer that all measures/construction
taken shall be maintained till completion of job.
• The QC Inspector will ensure that the works are executed according to the requirements of
dossier are fulfilled
4. MATERIALS
Right approved plastering materials and accessories will be applied to the construction site.
• Water
Water shall be clean and fresh containing no Salt, Sulphur or other harmful substances.
• Cement
All materials required for plastering and pointing works shall be approved.
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 2 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
• Sand
Natural sand, white or light gray, washed and cleaned. Sand shall be hard, durable, clean and
free from adherent coatings and organic matter and shall not contain any appreciable amount
of silt, clay balls or pallets. Sand shall not contain impurities such as iron pyrites, coal pyrites,
lignite, mica shale etc.
• Ensure that material, samples and method statement have been submitted and approved.
• Surfaces to receive plastering shall be dry brushed to remove all loose particles, dust,
laitance, efflorescence, etc. and any projecting fins on concrete surfaces shall be hacked off.
• Where surfaces are out of line, they shall be brought to level by hacking or dubbing out prior
to commencement of finishing.
• All required openings for mechanical & electrical services, conduits pipes, plugs shall be
installed prior to plastering.
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 3 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
6.2 Workmanship
6.2.1 Surface Preparation and Installation of Plaster Accessories
• Surfaces to receive cement plaster shall be cleaned of all projections, dust loose particles,
grease and other foreign matter. Plaster shall not be applied directly to
(a) Concrete or masonry surfaces that have been coated with bituminous compound, Surfaces
that have been painted or previously plastered.
(b) Before the plaster work is started, masonry surfaces shall be wetted thoroughly with fog
spray of clean water to produce a uniformly moist condition. Accessories shall be checked
carefully for alignment before work is started
(c) All Accessories shall be prepared and installed in accordance to approved Standard
Drawings
• All undercoats shall be scratched to form an adequate key for the next coat.
• Level Guides shall be provided up to required thickness as per approved Drawings.
• Plastering shall proceed only when the masonry block works are completed.
• For plain face plasterwork to Interior wall, finished thickness shall unless otherwise stated be
15mm in accordance to approved Drawing.
• For Thickness as per approved Drawing, mortars will be used to make landmarks with
adequate size square and thickness as per requirement
• For external plaster, the plastering operations shall be started from the floor and carried
downwards.
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 4 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
• The internal plaster, the plastering may be started wherever the building frame, roofing and
brick work are ready.
• The rough plaster shall be started from top to bottom .It’s no needed smoothing surface but
the tight press up tile and allowed to dry sufficiently not rapidly.
• Curing shall be spraying with water as often as necessary to keep the plasterwork damp.
• Plaster work shall be level finished, plumbed, square and true within specified tolerance
without waves, cracks, blister pits, crazings, discolorations, projects or other imperfections.
Plaster work shall be formed carefully around angles contours, and well up to screeds. Special
care shall be taken to prevent sagging and consequent dropping of applications. There shall be
no visible junction marks in the finish coat where one day's work adjoint another.
2) Finish Coat - Shall not be applied until after brown coat has seasoned for 7 days. Just
before the application of the finish coat, brown coat shall again be evenly moistened with
fog spray. Finish coat shall be floated first to a true and even surface then troweled in a
manner that will force the sand particles down into the plaster. Plastered surfaces shall be
smooth and free from rough area, trowel marks, cracks and blemishes.
6.2.4 Smooth finished cement plaster
Finishing for Plaster Surface
The proportions of sand and cement shall be as specified and shall cover all irregularities,
undulations, depressions due to chasing etc. in the surface to be plastered. Straight edges shall be
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 5 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
freely used to ensure a perfectly even surface. The finished surface shall be true and even and
present uniform texture throughout and all joining marks shall be eliminated. All corners, edges
and angles shall be made perfectly to line, plane and plumb. All exposed angles and junctions of
walls, doors, windows, beams, slabs etc. shall be carefully finished so as to furnish a neat and
even surface.
Plastering items amongst all other things as described in various items also include
• Curing cement plaster by maintaining in a moist condition for one day following application.
Keep enclosed and fog spray (after initial set) as required to prevent dry-out. Preparation of
surfaces to receive the plaster, providing cement plaster of the specified average thickness and
proportions
• All labor, materials, scaffolding, use of tools and equipment to complete the plastering work
as per specifications.
• Curing as per Specification and requirement
• Cleaning the surface of doors, windows, floors or any other surfaces where plastering might
have splashed.
• Finishing the portion of plaster left above the terrazzo, plain cement tiles, iron or any type of
skirting work to be finished rounded or as directed by the Engineer separate operation after
laying of floor tiles skirting.
6.2.5 Plaster Accessories (shall be provided as per requirement and approved Drawing if
required)
• Strip metal lath centered over junctions of dissimilar backing materials and casing beads
terminations of plaster finish shall be installed.
• Corner and horizontal beads shall be level, vertical beads, plumb, straight and true, assuming
proper plaster thickness.
• Plaster Stop shall be used where called for or as required to stop plaster surface against a
dissimilar to form a neat and definite joint.
• At all control joint locations install back to back square nosed casing beads.
6.2.6 Cutting, Patching & Repairing
• Cut out & repair all damaged plaster and all fine cracks, pits, checks waves, blisters and other
defects which in the opinion of the Owner will impair the appearance and the life and
usefulness of the finish surfaces.
• Site will be kept clean and tidy during the works and all the debris / waste material will be
cleaned and carted away to approved dumping area.
6.2.8 Testing of Plaster Materials
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 6 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
7.3 Environmental
• Working area shall be clean, not slippery and free from any debris.
• Adequate water will be provided while using the cutting machine to reduce dust
emitting the environment.
First aid facility is always made available during working hours by a qualified fist aiders.
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 7 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 8 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
B.1a Use them only for the purpose for which they
are designed
B.1 Use of inferior
quality/electric tools with faulty
wirings/insulation
B.1b Keep them in a safe working condition.
Defective tools must not be used.
B.2 Motar splatters into the eyes B.2a Always wear safety PPE.
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 9 of 10
EVNGENCO3/VTTPM Vinh Tan 4 Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
Doc.No.VT4-DD09-P0ZEN-040043 Rev.B 10 of 10