VT4-DD09-P0ZEN-040060 Rev.C 1 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
1.0 PREFACE
The purpose of this Method Statement is to describe the method for Fire Fighting Pump
House and to details out the steps to be taken in meeting the technical standards and EHS
requirements
• Plant Project: VinhTan4 Thermal Power Plant
• Company/The Employer: Power Generation Corporation 3
Vinh Tan Thermal Power Project
Management Board
• Contractor : DMPP Consortium
2.0 APPLICATION
Application of this Method Statement is applicable to the implementation of concreting
works for Water Treatment Plant in VinhTan 4 Thermal Power Plant Project.
MANPOWER EQUIPMENT
Scaffolding worker 10
Common worker 15
VT4-DD09-P0ZEN-040060 Rev.C 2 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
Project Manager
Engineer
5.0 RESPONSIBILITIES
• It is overall responsibility of Project Manager to organize resources prior to perform
construction activities as per project specification in compliance with the quality, schedule
& safety requirements.
• EHS Manager will ensure in coordination with Site Engineer that all measure/construction
taken shall be maintained till completion of job.
• It is the responsibility of Site Manager/Site Engineer that construction activities are
executed according to the relevant project specification in compliance with the quality,
schedule & safety requirements.
• It will be ensure that all works are performed safely according to the attachment.
• The relevant Supervisor will ensure that the work is carried out in accordance with this
method statement and project specification.
• The QC Inspector will ensure that the work is executed according to the requirements of
quality dossier are fulfilled.
VT4-DD09-P0ZEN-040060 Rev.C 3 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
VT4-DD09-P0ZEN-040060 Rev.C 4 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
6.4 Concreting
• Lean concrete casting: Lean concrete has 50mm thickness. Lean concrete shall be
transported to site by mix-truck and flowed down to position by concrete pump. The
concrete surface shall be leveled by workers.
• Rebar and formwork shall be setting out follow design drawing by workers.
• Formwork shall be calculated to ensure stability during construction.
• Fresh concrete shall be transported to site by mix-truck and flowed down into formwork
by a concrete pump hose.
• In casting time, workers shall use vibrators to consolidate the fresh concrete and avoid
honeycomb.
• The concrete surface shall be leveled by workers.
VT4-DD09-P0ZEN-040060 Rev.C 5 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
VT4-DD09-P0ZEN-040060 Rev.C 6 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
VT4-DD09-P0ZEN-040060 Rev.C 7 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
For control quality during casting concrete such as : honeycomb surface, loose aggregates,
loss cement water, leaky, etc…
• Form corner and all fly wood connection point was applied silicon to ensure the cement
water is not loss during the concrete casting vibration and leaky water after concrete
curing time.
VT4-DD09-P0ZEN-040060 Rev.C 8 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
• At the point where the form touch the set concrete surface we will insert flexible filler and
then fill mortar to ensure the cement water is not loss during the concrete casting
vibration and leaky water after concrete curing time. (such as bottom of column)
• In case that concrete casting will not be completed at one time due to construction plan,
height and etc, the approved bonding agent(Sikadur 731) will be applied between old and
new concrete surface in accordance to actual site construction condition.
• Concrete casting height will be controlled to ensure concrete free fall is not over 1.5m and
every 30cm per layer and continues the next after enough vibrating.
• Construction joint for beam and slab (if required) we follow mention on DWG VT4-UV01-
P0ZEN-172001 (page 3 of 3) and apply the wire mesh at that point.
6.5 Curing
• Freshly placed concrete shall be protected from drying and extremes of temperature. After
it has hardened sufficiently to prevent damage thereby, suitable and adequate protection
shall be provided during the curing period against damage from shock and impact,
exposure to undesirable weather conditions including extremes of temperatures and loss
of moisture.
• The exposed surfaces of freshly placed concrete shall be kept in continuously moist
condition for a period of at least 7 days by the use of absorbent mats of burlap which
shall be wetted down as required to keep them in a continuously moist condition for the
duration of the curing period. To assist in maintaining the moist conditions, adequate
impervious sheets such as plastic film or its equivalent shall be used as cover.
• Immediately upon the removal of the side forms, absorbent mats or burlap shall be
draped down the sides a sufficient distance to completely cover the exposed surfaces and
kept in continuously moist condition for the required curing period.
• In order to control the cracking the following measure shall be applied:
- Immediately upon the completion of the concrete the top surface shall be covered
with polyethylene sheet with joints overlapping 50mm and sealed properly to prevent
evaporation of water from concrete.
- Subsequently the about are shall be covered with absorbent mats or burlap for
minimum of 7 days or curing compound shall be applied.
- In case of blinding concrete, the curing shall be for one day.
- Then the entire area is flooded with water to prevent evaporation loss.
VT4-DD09-P0ZEN-040060 Rev.C 9 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
- Where the concrete protective coating is applicable the area shall be cleaned
thoroughly and protective coating shall be applied in accordance with the approved
coating specification.
6.6 Removal of Forms
• Care shall be taken to ensure that during removal of form operations concrete edges are
protected from any possible chipping off.
• All embedded parts be cleaned thoroughly and made free from dust, cement and slurry
and covered with temporary protections.
• For easy de-shuttering the shutter surface in contact with concrete shall be treated with a
coat of demoulding oil.
• Minimum time allowed before de-shuttering is 12 hours.
6.9 Backfilling
• Backfilling work will be executed according to the approved MS for excavation and
backfilling work.
• Approved suitable excavated material from the site can be used for backfilling/general
filling. If the excavated material is of a poor quality, obtain fill material from approved
borrow pits or any other source able to provide material as per specifications.
VT4-DD09-P0ZEN-040060 Rev.C 10 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
• Filling soil shall be placed and spread in uniform layers not exceeding 300 mm before
compaction.
• Fill materials shall be laid, spread and leveled using manpower and compacted by using
roller compactor to the required levels.
• During compaction, maintain the moisture content of fill material usually +/- percent of
overall moisture content. If required, add clean water to the fill material in order to
maintain the necessary moisture content.
• Field density test (FDT) shall be carried out randomly on agreed area before proceed to
the next excavation site or layer.
6.11 Protection
• Provide barricades and restrict access as appropriate to prevent damage to work in place.
• DMPP shall be responsible for protection of work in place against displacement, damage,
or loss until Employer’s acceptance. Any work and subsequently damaged, lost or
displaced shall be repaired and replaced to the Employer’s satisfaction.
6.12 Cleaning
• Thoroughly clean, rake, wash, flush or sweep as required to clean adjacent improvements
of materials covered as part of this work to submitting for Employer’s acceptance.
• Contractor shall provide all labor, equipment, materials and other items as required to
perform clean up as required by the Employer.
VT4-DD09-P0ZEN-040060 Rev.C 11 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
All personnel should be aware of assembly points, escape routes, emergency contact numbers.
VT4-DD09-P0ZEN-040060 Rev.C 12 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
VT4-DD09-P0ZEN-040060 Rev.C 13 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
VT4-DD09-P0ZEN-040060 Rev.C 14 of 15
EVNGENCO3/VTTPMB Vinh Tan 4 Thermal Power Plant
DMPP Consortium
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing solutions that
control, minimize or eliminating hazards.
D. Concreting D.4 Electric shock due to D.4Set protective pipes around pump car
Works contact with high voltage boom and keep distance by dispatching
wire on pump car boom guidance.
D.5 Accident and skin D.5 Wear PPE like safety helmets, gloves and
irritation due to not wearing safety shoes.
safety helmets, gloves and
safety shoes
D.6 Breaking due to inferior D.6 Tightly set connections of concrete hose
connection of concrete hose and pipe.
and pipes.
D.7 Falling due to without D.7 Set cover on openings and safety rail on
safety measures on ready mix slab edge.
concrete placing nearby
openings or slab edge.
D.8 Electric shock due to D.8 Ground vibrator, connect circuit breaker
without ground and circuit and use motor driven vibrator rather than
breakers on vibrators. electric driven
E. E.1 Extreme environmental E.1a Implement safety procedures
Environmental condition such as high &guidelines on heat stress
Conditions temperature & humidity and E.1b Inspect excavation and adjacent areas
During strong wind for possible hazardous atmosphere and any
Excavation other condition that may present a hazard
Works E.1c Suspend / stop all operations during
extreme temperature & humidity and high
wind
F. Dewatering F.1 Pump equipment (Diesel F.1a Daily check of the equipment prior to
Engine) oil leakage during start of work
operation
F.1b Regular monitoring of the equipment
sin order to control and prevent oil leakage
and other engine trouble
F.2 Electric shock due to F.2a Provide adequate ground and circuit
without ground external box breakers
on pump station and circuit
F.2b Designate electrician/operator for the
breakers
pump equipment
G. Disposal of G. Collision between G.1 Prepare access for the equipment to be
Excavated/Exces equipment provided
s Materials
H. Dust Control H. Vehicle/equipment H.1 Spraying of water on the road as
transporting of excavated soil required to ensure no dust flying
to the disposal
VT4-DD09-P0ZEN-040060 Rev.C 15 of 15