Project: Camella Homes - Gensan

Location: Phase 2, Blk. 9 Lot 12, Camella Homes Gensan, San Isidro, GSC
Subject: Construction of Door Trellis
Date: March 9, 2017

Description Qty. Unit Unit Cost Total Cost


I. Steel Works
Welding Works
2 x 2 x 1.2mm Square Tube 7.50 lengths 430.50 3,228.75
2 x 2 x 1.5mm Square Tube 3.00 lengths 500.00 1,500.00
2 x 6 x 1.2mm Rectangular Tubing 2.00 lengths 600.00 1,200.00
Welding Rod, 2.5mm 6012 2.00 boxes 150.00 300.00
Cutting Disc, 4" 10.00 pcs. 75.00 750.00
Grinding Disc, 4" 1.00 pc. 85.00 85.00
Subtotal: 7,063.75
II. Painting Works
Epoxy Primer Red Oxide, Webber 1.00 gallon 656.00 656.00
Mayon Lacquer Thinner 1.00 gallon 397.00 397.00
White Enamel Paint, Boysen 2.00 gallon 650.00 1,300.00
Paint Brush 2" 2.00 pcs 15.00 30.00
Sandpaper, 120 5.00 pcs 18.00 90.00
Epox Joint Filler 1.00 can 300.00 300.00
Subtotal: 2,773.00

Material Cost: 9,836.75


Labor Cost: 6,000.00

Grand Total: 15,836.75

Prepared by:

Michael Jan de Celis


Project Engineer
Project: Camella Homes - Gensan
Location: Phase 2, Blk. 9 Lot 12, Camella Homes Gensan, San Isidro, GSC
Subject: Construction of Door Trellis
Date: March 29, 2017

Description Qty. Unit Unit Cost Total Cost


I. Steel Works
Welding Works
2 x 2 x 1.2mm Square Tube 7.50 lengths 430.50 3,228.75
2 x 2 x 1.5mm Square Tube 3.00 lengths 602.00 1,806.00
2 x 4 x 1.5mm Rectangular Tubing 2.00 lengths 871.00 1,742.00
Welding Rod, 2.5mm 6012 1.00 boxes 150.00 150.00
Cutting Disc, 4" pcs. 75.00 0.00
Grinding Disc, 4" pc. 85.00 0.00
Subtotal: 6,926.75
II. Painting Works
Epoxy Primer Red Oxide, Webber 1.00 gallon 656.00 620.00
Mayon Lacquer Thinner 1.00 gallon 397.00 400.00
White Enamel Paint, Boysen 1.00 quart 184.00 184.00
Paint Brush 2" 1.00 pcs 24.00 24.00
Sandpaper, 120 5.00 pcs 8.95 44.75
Epox Joint Filler can 300.00 0.00
Subtotal: 1,272.75

Material Cost: 8,199.50


Labor Cost: 6,000.00

Grand Total: 14,199.50

Prepared by:

Michael Jan de Celis


Project Engineer