Project Charter
Chris Egbedi
Jovica Riznic
Course
June 12 2017
PROJECT CHARTER 2
Table of Contents
Project Background...................................................................3
Introduction...........................................................................................................................................3
Background..............................................................................3
Project Purpose........................................................................5
Project Objective......................................................................5
High-Level Assumptions............................................................6
High-Level Constraints..............................................................7
High-Level Requirements..........................................................8
Deliverables.............................................................................8
Project Milestones....................................................................8
Project Stakeholders.................................................................9
Payment Schedule...................................................................10
PROJECT CHARTER 3
Project Background
Introduction
A project charter is a core document that explains the most important information
concerning a project, and it gives authorization of it. It provides an initial description of roles
and responsibilities, outlines the objectives of the project, singles out the main stakeholders,
and explain the project manager’s power. Project charter serves as a reference of
authorization for the future of the project. This means one gets to the point of being able to
relate to where they are heading, who might help them get there, why they need to get there,
who will be affected along the way and the major risks to be undertaken are also identified.
This applies to the process of building a dream home too whereby an individual need to make
a project charter that would be useful in achieving this goal. This project of building a dream
home will involve a lot of work including the landscaping which includes the beautifying of
the environment within the landscape, entire construction of the house including the work
done inside the house of fixing the ceiling boards as well as the floor, management activities,
fixing the infrastructures like the electricity and plumbing and also the milestones and the
inspections.
Background
This project charter is being documented for a project to build a dream home for me
on the Lakefront property. The house construction will be a double story built on a two-acre
land that is adjacent to Lake. The house will accommodate only one family, and no part of it
may even be rented out. In this project charter, everything will be reported including the
purpose of the project, the objectives, the out of scope, high-level assumptions, high-level
payment schedule and even the approval document. This project charter will also state the
starting date of the project which will be from 30th August 2017 and will be expected to be
over by 30th September 2018. The timeframe set is enough to meet all the process of the
This project has a scope that is within the budget of $300,000. This project charter
will help in giving guidelines of how to break down the budget as well as help in meeting all
the requirements. Every stage involved in the process of building the dream home will have
to be met on time because a plan is being laid down. The land will have to be purchased, and
all the land permits and approvals acquired to ensure it is lawfully owned then the
construction of the house will be initiated together with the landscaping, exterior and interior
decorations. The budget is expected to Carter for everything about the project of the house
and from the time the project is initiated; the prices are expected to also remain the same or
not to change with more than ten percent of the total price so that everything may meet the
budget as planned. The weather conditions are also expected to remain favorable for the
There is a lot of trending new technology that has emerged in the last few years, and it
is advantageous due to its minimal consumption of the energy, and it will be utilized in this
project too. The house will be constructed with the latest building materials and even with the
latest design that confidently gives an individual a sense of belonging and ownership. The
L&L Construction Company will be in control of ensuring the dream home is secured to one's
needs by overseeing and managing the work at the site. They are a leading construction
company known to be reliable and active for the last twenty-two years. One of their recent
customers Mr. Bach recommended them and everyone witnesses that the work done by this
construction company is tremendous and their prices are reasonable as well. They have
PROJECT CHARTER 5
supported many people to dwell in their paradise, and this company will well achieve this
dream home.
Project Purpose
The purpose of this project is to come up with an establishment of one’s dream home
in a new location and to examine the process of building the dream home as well as the
management of the process of its building up. The purpose of this project charter is also to
ensure the project on home building get to be completed on time which is scheduled to be not
later than 30th September 2018 and have the family move in the new home once all the work
is done.
Project Objective
This project is scheduled to be completed no later than 30th September 2018, and this
means the goal of achieving this dream home have to be put in place to encourage every
partaker to remain focused in the achievement of this project’s end results. And the objectives
include:
2) To learn what it takes in order to meet the dream of having a home of own.
3) To be able to learn how to plan well and carefully within one's budget.
the project and its products, and there are some things that may be excluded from the work.
PROJECT CHARTER 6
The scope of this project charter states that within the total budget of $300,000 the property
will involve the landscaping which includes the excavation, foundation, grading, and
driveway, it will also involve the main house construction, infrastructure, management,
interior work as well as the milestones and the inspection of the entire construction The
building up of a dream house may attract more changes which will require extra cost and this
done and the individual may also wish to take the photos of the fully furnished house.
This will cost some extra cash as this is an activity that is not within the scope and it
High-Level Assumptions
The making up of assumptions in the project management is an avoided activity, and when it
comes to building a dream home, this will still take part. The assumptions are essential in
explaining the scope and the risks in relation to the estimated time and costs. This high-level
If the dream homeowner needs all work is done within one year, the builder may opt
to make an assumption of one more month because there may be setbacks and delays
High-Level Constraints
This is the regarded restrictions or limitations of the project from achieving the goal, and the
dream homeowner may feel disappointed. These high-level constraints may be either internal
or external. The internal constraints are those found within the system and are under control
while the external constraints are outside the system with no control. The external constraints
include:
The land must be leveled before the taking the place of the excavation during the
1) There is a high possibility that the project will not be accomplished in due time and the
2) There may also be a problem in finding knowledgeable specialists to carry out the
project as most experienced and savvy individuals are rarely found in the market as they are
easily booked for other projects, and this applies to the L & L construction company which
3) The team working at the site will have an issue in the adopting the new technology and
4) It will also be risky to leave the building materials outside overnight, and this calls for a
High-Level Requirements
The building up of a dream home will generally require a certain budgeted amount of
money which is identified to be $300,000, building materials, labor, vehicles for transporting
the materials to the site, authorized documents that gives a go-ahead for the building of a
home and the team of members that help in the planning process and even the engineer’s
certification. Then the L & L construction company will be able to initiate the project to reach
its completion.
Deliverables
The main deliverables in this project is a dream home with fully furnished main house
that has upstairs and which is a four bedroomed house with a two door garage as per the
architectural design drawing plan. Every bedroom will have a bathroom and a toilet and will
also contain a big living room area as well as an open windowed dining room with besides a
beautiful surrounding that offers a perfect view of the lake and the city as well. The landscape
should also be met with a flat and grassy terrain as well as a recreational area.
Project Milestones
Milestones are tools used in project management to symbolize certain points along the
timeline of the projects. Every progress in milestones has to be recorded, and this may
include:
PROJECT CHARTER 9
Project Stakeholders
The three stakeholders involved in this project are the project manager, contractor and
the supplier. The project manager is Bagda Kamir who will closely work with myself and the
construction company to oversee the whole project including the progress of the project and
ensure resources are well utilized, and delivery meets time and also ensure the result are to
the intended satisfaction. The project manager is distinguished to ensure the project remains
within the budget along with its specifications and the manage the other project stakeholders
as well to ensure the project is successfully met through the initiation, the planning process,
and the execution of the project. The contractor company will be the L & L Construction
company considering its good reputation and their experience in taking part in construction
and landscaping to ensure the outcome is in line with what is expected and ensure they
deliver good outcome while the supplier or the vendor will be the Gild suppliers who will
ensure that all the materials needed at the site are delivered on time upon payment. The L&L
PROJECT CHARTER 10
construction company and the Gild suppliers both are answerable to project manager who
Payment Schedule
Document Approval
This undersigned document acknowledges the review of the project charter and thereby
authorized and funded to carry on the project. The undersigned persons will still approve this
Signature……………………………………
Title………………………………………....
Role………………………………………….
Date………………………………………….
Signature……………………………………
Title………………………………………....
PROJECT CHARTER 11
Role………………………………………….
Date………………………………………….
Signature……………………………………
Title………………………………………....
Role………………………………………….
Date………………………………………….
Signature……………………………………
Title………………………………………....
Role………………………………………….
Date………………………………………….