Академический Документы
Профессиональный Документы
Культура Документы
PUBLIC ADMINISTRATION(GIMPA).
Progress Report
(LOT 1)
SUPERSTRUCTURE
WORKS
1
Ongoing fixing of
iii) Painting works 50 70 door frames
2
2. WORK PROGRESS FOR LOT 2
SUPERSTRUCTURE
WORKS
i)Blockworks 95 100
ii)Plastering works 60 65 80
Planned Progress
for Lot 2: 54 %
Actual Progress
for Lot 2: 54%
Forcast Progress
for Lot 2: 55%
3
3. Site Labour Force
Chinese Staff
Ghanaian Staff
Project Manager 1
1.Foremen 5
Site Manager 4
2.Masons 4
/
3.Carpenters 6
/
/ 4.Steel benders 3
/ 5.Plumbers 5
/ 6.Security 2
/ 7.Labourers 15
8.Driver/cook 2
Total: 5
Total 42
4
4. Materials on Site
2 Coarse Aggregate m³ 15
4 Timber(2x6) pcs 50
5 Timber(2x3) pcs 30
6 Timber(2x2) pcs 15
9 3” Nails boxes 2
12 Plywood pcs -
5
5. Health and Safety.
The site experienced no injury related issue.
6. The Weather
The site experienced no rains from 18th December,2018.
7. Progress Photos
LOT 1 & 2
Fixing of door frames at Lot.1 Roofing works at Lot 1 Plastering works at Lot1
Fig 1 Fig 2 Fig.3
Pillar-away wall works at Lot2 Fixing of door frames at Lot 2 Roofing works at Lot 2
Fig.4 Fig 5 Fig. 6
6
Endorsed by: George Dabi
……………………………
Clerk of works (GIMPA)
………………………………………......
Site Manager (China State)
………………………………………......