Академический Документы
Профессиональный Документы
Культура Документы
Atlanta, GA USA
17-18 November, 2008
Abstract – This work employs the Double Synchronous strategy of the WT’s power converter.
Reference Frame PLL (DSRF-PLL) as an effective method for There are two main approaches to detect the positive
grid synchronization of WT’s power converters in the presence of sequence component of the utility voltage. The first one
transient faults in the grid. The DSRF-PLL exploits a dual
synchronous reference frame voltage characterization, adding a assumes that the frequency of the utility is a constant and
decoupling network to a standard SRF-PLL in order to effectively well-known magnitude, and is usually based on i)
separate the positive- and negative-sequence voltage components instantaneous symmetrical components (ISC) [5], ii) on space
in a fast and accurate way. Experimental evaluation of the vector filters (SVF) [6], or on iii) the recursive weighted
proposed grid synchronization method and simulations regarding least-square estimation algorithm (WLSE) [7]. The second
its application to ride through transient faults verify and validate approach assumes that the utility frequency is not constant,
the excellent behavior of the DSRF-PLL in the grid
and uses closed-loop adaptive methods in order to render the
synchronization of WT’s power converters under unfavorable grid
conditions. detection algorithm insensitive to input frequency variations.
The use of a phase-locked loop (PLL) is indeed the most
representative example of such frequency adaptive methods.
I. INTRODUCTION In three-phase systems, the PLL’s are usually based on the
synchronous reference frame (SRF) [8] and, under ideal
Wind power stands out as one of the most attractive utility conditions, the SRF-PLL yields good results. But under
renewable sources in a future sustainable energy scenario. voltage unbalance however, the overall performance of the
However, the increasing penetration of wind power SRF-PLL makes it unacceptable for the detection of short
generation in the power system has made necessary to design duration events, i.e., voltage sags [9]. An alternative
new grid code requirements (GCR) for wind power [1]. In technique for achieving a frequency adaptive detection
those countries with high share of decentralized wind power algorithm uses a single-phase enhanced phase-locked loop
generation, the new GCR impose the wind turbines (WT) to (EPLL) for each phase of the three-phase system [10]. The
stay connected to the grid (ride-through) under severe EPLL provides at its output a set of two orthogonal signals
operating conditions originated by transient faults [2]. Each synchronized with the phase-voltage. These signals are
GCR proposes a voltage tolerance curve (VTC) in which the processed using the instantaneous symmetrical components
voltage sag to be withstood by the WT is quantified by its (ISC) method to calculate the positive-sequence component
‘magnitude’ and its duration. Although this voltage of the utility voltage. Another solution to obtain a set of
characterization method could be reasonable for three-phase quadrature signals is to use a generalized integrator. A
faults, it is indeed insufficient for single- and two-phase faults positive-sequence detection system based on a dual second
since the phase-angle jump and the voltage imbalance are order generalized integrator (DSOGI-PLL) is presented in
neglected. In this sense, a three-phase balanced fault may [11]. This system applies a SRF-PLL on the calculated
affect the WT in a very different way from a single-phase positive-sequence signal to estimate the utility frequency.
fault, even if they have the same ‘magnitude’ and duration. In This work presents the ‘Double Synchronous Reference
last years, WT’s manufacturers have oriented their interest Frame PLL’ (DSRF-PLL) as an alternative detection method,
toward the search of new solutions to stay connected during which can be used for the grid synchronization of WT’s
the fault time and to ensure the stability of the wind power power converters in the presence of transient faults. The
generation system once the fault is cleared [3][4]. Taking into proposed technique expresses the voltage vector on the DSRF
account that behavior of the WT immediately after the fault is in order to accurately detect its positive- and negative-
very much related to the behavior during the fault, it is sequence components. This is accomplished by studying the
necessary to accurately detect the components of interest of relationships between the transformed signals on the DSRF-
the grid voltage during and after the fault. In this sense, the axes, which combined with the design of a proper decoupling
fast and precise detection of the amplitude and phase of the network enables a fast and precise estimation of the positive-
fundamental-frequency positive- and negative-sequence and negative-sequence voltage components.
voltage components is a crucial issue in the design of control
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.
II. THE DOUBLE SYNCHRONOUS REFERENCE FRAME PLL vd m vqm
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.
ω̂ θˆ
k p + ki ∫ ∫
vd +1 vd +1 ≡ vˆ +1
v*
d +1 + 1 +1* d +1
[T ]
dq +1
vq+1
q +1
DC d
− 1 vq*+1
LPF
vq+1
+1*
−1 q LPF
θˆ d −1 q
v ( abc ) v (αβ )
[Tαβ ]
vd −1 vd −1
vd* −1
d −1
[T ]
dq −1
vq−1
q −1
d +1 q +1
− 1 v*
d −1*
LPF
vq−1
DC q −1* q −1 LPF
θˆ + 1
The block diagram of the DSRF-PLL is shown in Fig. 3. 50µs. In addition, the faulty grid has been replaced by a three-
This PLL, as shown in the figure, is based on a conventional phase programmable AC source, being the prefault voltage
three-phase SRF-PLL structure [9]. Its performance set to V pf = 100V 50Hz . Moreover, the tuning parameters for
improvement comes from the added DN which has been the DSRF-PLL were set to ω f = 2π 25 rad/s , k p = 2.22 and
configured here for insolating the fundamental-frequency ki = 246.7 .
positive- and negative-sequence components, i.e., with In a first experiment, a sag type C was programmed in the
n = +1 and m = −1 . The DN cancels out the double frequency AC source [13]. In this unbalanced sag, G the characteristic
oscillations at 2ωin vq*+1 ; therefore, there is no need to reduce remaining complex voltage was set toGVrcv = 0.6 −20º and the
the PLL bandwidth and the real amplitude of the positive positive-negative factor was set to V pnf = 0.9 −10º , both of
sequence voltage component is indeed effectively detected. them expressed in p.u. respect to the perfectly balanced pre-
fault voltage v pf = 1 0º [14]. Fig. 4 shows the plots resulting
III. EXPERIMENTAL VALIDATION OF THE DSRF-PLL from this experiment. For a second experiment, a sag type D
was programmed in the AC source using the same voltage
In order to experimentally evaluate the behavior of the characteristics parameters that earlier. The plots resulting
DSRF-PLL its discrete algorithm were implemented in a from this second experiment are shown in Fig. 5.
dSpace DS1103 DSP board with a sampling time equal to
v ( abc ) θˆ +1 θˆ −1
vd+1
vˆ (+abc
1
)
vq−1 vd−1
vq+1
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.
v ( abc ) θˆ +1 θˆ −1
+1
vd+1
vˆ ( abc )
+1
vd−1 vq−1
v q
Figs. 4 and 5 show the excellent behavior of the DSRF- Secondly is the case of unbalanced grid faults and particular
PLL in the detection of the positive- and negative-sequence to this situation is the appearance of negative sequence which
components of unbalanced utility voltage when realistic has influence on the control of grid side converter. As was
voltage sags are considered. It is worth to notice that no presented in [15], different strategies can be applied to
oscillations are present in the DSRF-PLL output signals, calculate the current references for a three-phase grid
reaching their steady state in about one grid cycle. The connected converter delivering the same mean value of active
decoupled signals on the positive and negative are defining and reactive powers to an unbalanced grid. A brief revision of
the magnitude of the positive- and negative sequence the methods presented in [16] will be done in the following.
components, respectively. The action of the PLL makes
vq+1 = 0 , being the angular position of the positive reference
A. Instantaneous Active and Reactive Control (IARC)
frame equal to the phase-angle of the positive-sequence
The instantaneous active and reactive powers related to
voltage vector. To calculate the negative-sequence phase
generic voltage and current vectors, v and i, in a three-phase
angle will be necessary to take into account the relative angle
system can be written as:
between the voltage vector and the negative reference frame.
In the followings, the application of DSRF-PLL to a wind p = v⋅i , (3a)
turbine system connected to the utility network as Fig. 6
q = v × iq = v⊥ ⋅ iq , (3b)
illustrates is described. An introduction to the current
reference calculations using different sequences of the grid where v ⊥ is an 90-degrees leaded version of the voltage
voltage is firstly given. This plays an important role on the vector v. From (3), the active and reactive current references
delivered power quality during the fault. After that, three to deliver the powers P and Q to the grid are given by:
power delivery situations in the case of a grid fault in the
P
power system are presented and simulation results illustrate i*p = 2
v , (4a)
the characteristics of the delivered power in the three cases. v
As mentioned in § I, new GCR state that wind turbines From now on it will be assumed that the power references
have to ride-through severe operating conditions originated P and Q are constant throughout a grid period, T.
by transient faults [2]. Anyway, there is not a specific demand
about how the currents injected by the WT should be during B. Balanced Positive Sequence (BPS)
the grid fault. Depending on the grid fault type, i.e. balanced
or unbalanced, two main possibilities in controlling the grid When the quality of the currents injected in the grid plays a
side power converter arise. Firstly is the situation of balanced decisive role, the voltage vector in (4) can be substituted by
grid faults, when the operation of the grid side converter is its positive-sequence component and the current references
similar to in normal grid condition with the only difference are given by (5). The voltage vector v + in (5) is given by the
that the current in the grid side converter is increasing DSRF-PLL. Assuming that the current injected by the
because of the reduction of the grid voltage amplitude. inverter perfectly track the current references, the
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.
P Q
i*p =
+ 2
v+ , (5a) i*q =
+ 2 − 2
(v +
⊥ − v −⊥ ) (9b)
v v −v
z
VS
d⋅z (1− d ) ⋅ z
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.
1.5
1
(a) a practical implementation however, the bandwidth of the
0.5 power controller should be decreased in order to meet with
0
the electro-mechanical constrains that force smother changes
-0.5
-1 in the power of the wind generators. Moreover, the GCR
-1.5 regarding the output power variation rate of the WT after the
1.2
1
(b) fault should be considered.
0.8
0.6
v+ v+ A. Active Power Delivering (APD)
0.4
0.2
0
4
The aim of this strategy is to deliver only active power to
(c) the grid but without exceeding the nominal rating of the WT.
2
The control law in this situation can be written as:
0
-2
P* = 3 ⋅ V + I N , Q* = 0 , (11)
+
-4 where V is the rms value of the detected positive-sequence
3
q (d) voltage detected by the DSRF-PLL and IN is the rms nominal
1.5
current. A mentioned in § V, three different strategies for
0
p controlling the grid current can be applied. Simulation plots
-1.5
showing currents and powers are expressed in per unit (p.u.)
-3
0.2 0.5
t [s]
0.8 in respect to the nominal conditions. In the simulations, the
power obtained from the wind has been considered 75% of
Fig. 7. Response of the IG in the presence of a grid fault. (a) Utility the nominal power of the WT.
voltage, (b) Sequence components, (c) IG currents, (d) P and Q
As it can be observed in Fig. 8(a), the injected currents
significant reduction in both the electromagnetic torque and
1.5
the electric power delivered to the grid, see Fig. 7(c). Taking 1
(a)
into account that the aerodynamic torque can be considered 0.5
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.
1.5 1.5
1
(a) 1
(a)
0.5 0.5
0 0
-0.5 -0.5
-1 -1
-1.5 -1.5
1.5 1.5
1 (b) 1 (b)
0.5 0.5
0 0
-0.5 -0.5
-1
p q -1
p q
-1.5 -1.5
0.2 0.5 0.8 0.2 0.5 0.8
1.5 1.5
1
(c) 1
(c)
0.5 0.5
0 0
-0.5 -0.5
-1 -1
-1.5 -1.5
1.5 1.5
1 (d) 1 (d)
0.5 0.5
0 0
-0.5 -0.5
-1
p q -1
p q
-1.5 -1.5
0.2 0.5 0.8 0.2 0.5 0.8
1.5 1.5
1
(e) 1
(e)
0.5 0.5
0 0
-0.5 -0.5
-1 -1
-1.5 -1.5
1.5 1.5
1 (f) 1 (f)
0.5 0.5
0 0
-0.5 -0.5
-1 p q -1 p q
-1.5 -1.5
0.2 0.5 0.8 0.2 0.5 0.8
t [s] t [s]
Fig. 9. Simulation results for the GVS power delivery strategy. Fig. 10. Simulation results for the ARPD power delivery strategy.
Currents/powers applying: (a)/(b)-BPS, (c)/(d)-IARC, (e)/(f)-PNSC Currents/powers applying: (a)/(b)-BPS, (c)/(d)-IARC, (e)/(f)-PNSC
using the BPS strategy are sinusoidal and balanced, and P* = 0 , Q* = 3 ⋅ V + I N (12)
limited to the nominal value. Fig. 8(b) illustrates the power
oscillations according to (6). Fig. 8(c) shows the distorted The WT is switching between the normal control to the
currents injected using the IARC strategy. The pattern of the GVS mode when V + < 0.9VN , being VN the nominal grid
current waveform in this case is not easy to be determined voltage on normal operating conditions. The GVS mode is
since it is depending on the faulty grid voltage. It could give deactivated as soon as V + ≈ VN again.
rise to trip the over-current protection of the inverter when the The currents and power waveforms in the case of GVS
voltage sag is very deep. On the other hand however, as Fig. control are shown in Fig. 9. These waveforms are similar to
8(d) shows, this strategy causes no oscillations in the power the waveforms resulting from the earlier strategy, with the
delivered to the grid and cancels out the oscillation in the dc mention that the roles of the active and reactive powers are
bus voltage. Fig. 8(e) and (f) show the currents and powers swapped. In Fig. 9(f), it is interesting to remark that the PNSC
waveforms related to the PNSC strategy. In this case the strategy causes oscillations in the active power when reactive
currents are unbalanced sinusoidal but not distorted. However power is delivered to the grid.
the peak current value overpasses the nominal value and
depends on the sag deep. Moreover, there are not oscillations C. Active Reactive Power Delivering (ARPD)
in the dc bus voltage but there oscillations in the reactive
power are increased. This strategy gathers the main features from the two
previous ones by delivering active and reactive power to the
B. Grid Voltage Supporting (GVS) grid. According the guidelines provided in [17], the control
law in this strategy can be written as:
The aim of this strategy is to support the grid voltage by
V+
(3 ⋅V I N ) − ( Q* )
+ 2 2
controlling the reactive power delivered by the WT to the P* = , Q* = 6 ⋅ V + I N 1 − (13)
grid. The control law in this strategy is written in (12). VN
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.
As in the previous case, this strategy is triggered when REFERENCES
V + < 0.9VN and is disabled when V + ≈ VN .
[1] C. Jauch, J. Matevosyan, T. Ackermann, and S. Bolik, “International
Fig. 10 shows the current and power waveforms related to comparison of requirements for connection of wind turbines to power
the ARPD control strategy. From these waveforms, analogous systems,” Wind Energy, vol. 8, pp. 295-306, Jul. 2005.
conclusions to those obtained from the previous strategies can [2] S. Bolik, “Grid requirements challenges for wind turbines,” in Proc.Int.
be drawn. The most remarkable characteristic of this control Work. on Large-scale Integrat. of Wind Power and Transm. Netw. for
strategy is its capability to keep delivering active power while Offshore Wind Farms, Billund, 2003.
is supporting the grid voltage. [3] A. Peterson, S. Lundberg, and T. Thiringer, “A DFIG wind turbine
ride-through system. Influence on the energy production,” Wind
Fig. 11 shows the evolution of the positive sequence
Energy, vol. 8, pp. 251-263, Jul. 2005.
voltage at the IG terminal for the three previously presented [4] T. Sun, “Power Quality of Grid-Connected Wind Turbines with DFIG
power delivery strategies. This figure illustrates how the and their Interaction with the Grid,” Ph.D. dissertation, Aalborg
control strategies delivering reactive power from the SG’s University, Denmark, 2004.
power converter are contributing to sustain the grid voltage [5] A. Ghosh and A. Joshi, “A new algorithm for the generation of
during the postfault stage, helping hence to keep the IG reference voltages of a DVR using the method of instantaneous
connected to the grid. In this sense, the ARPD strategy symmetrical components,” IEEE Power Eng. Review, vol. 22, 2002,
pp. 63-65.
becomes particularly attractive because is contributing to both [6] J. Svensson, “Synchronisation methods for grid-connected voltage
the grid voltage supporting and the active power delivering. source converters,” in Proc. IEE Gener. Transm. and Distrib., vol. 148,
May 2001, pp. 229-235.
GVS [7] H. Song, H. Park, and K. Nam, “An instantaneous phase angle
1
detection algorithm under unbalanced line voltage condition,” in Proc.
IEEE Power Electron. Spec. Conf, vol. 1, 1999, pp. 533-537.
[8] V. Kaura and V. Blasco, “Operation of a phase locked loop system
ARPD under distorted utility conditions,” IEEE Trans. Ind. Applicat., vol. 33,
0.9
Jan./Feb. 1997, pp. 58-63.
APD [9] S. Chung, “A phase tracking system for three phase utility interface
inverters,” IEEE Trans. Power Electron., vol. 15, pp. 431-438, May
2000.
0.8
[10] M. Karimi-Ghartemani and M.R. Iravani, “A method for
synchronization of power electronic converters in polluted and
variable-frequency environments,” IEEE Trans. Power Systems,
vol.19, pp.1263-1270, Aug. 2004.
0.7 [11] P. Rodríguez, R. Teodorescu, I. Candela, A. Timbus, M. Liserre and F.
0.2 0.5 0.8
t [s] Blaabjerg, “New positive-sequence voltage detector for grid
synchronization of power converters under faulty grid conditions,” in
Fig. 11. Positive-sequence voltage for each power delivery strategy.
Proc. IEEE Power Electron. Spec. Conf, 2006, CD-ROM.
[12] P. Rodríguez, J. Pou, J. Bergas, I. Candela, R. Burgos, and D.
VI. CONCLUSION Boroyevich, “Double synchronous reference frame PLL for power
converters control,” in Proc. IEEE Power Electron. Spec. Conf, vol.1,
The study and experimental results presented in this work 2005, pp. 1415-1421.
evidence that the DSRF-PLL is a very suitable solution for [13] M.H.J. Bollen, G. Olguin and M. Martins, “Voltage dips at the
terminals of wind power installations,” Wind Energy, vol. 8, pp. 307-
detecting fundamental-frequency positive- and negative-
318, Jul. 2005.
sequence component of unbalanced utility voltages in [14] L.D. Zhang, M.H.J. Bollen, “Characteristic of voltage dips (sags) in
presence of grid faults. The information provided by the power systems,” IEEE Trans. Power delivery, vol. 15, pp. 827-832,
DSRF-PLL is used in the design of the current control Apr. 2000.
strategies of a WT front-end converter. Based on that, [15] A.V. Timbus, P. Rodriguez, R. Teodorescu, M. Liserre, and F.
different methods to ride through a grid fault have been Blaabjerg, “Control strategies for distributed power generation systems
achieved. Simulations results illustrating the currents and operating on faulty grid,” in Proc. IEEE Int. Symp. Ind. Electron.,
2006, CD-ROM.
power for different power delivery strategies are presented. [16] P. Rodriguez, A.V. Timbus, R. Teodorescu, M. Liserre, and F.
These results highlight that accurate detection of the sequence Blaabjerg, “Independent PQ control for distributed power generation
components of the utility voltage play a crucial role in systems under grid faults,” in Proc. IEEE Ind. Electron. Conf., 2006,
controlling the WT during and after the fault. CD-ROM.
[17] E.ON Netz GmbH: Grid Code for High and Extra High Voltage.
VII. ACKNOWLEDGMENT August 2003.
Authorized licensed use limited to: IEEE Xplore. Downloaded on March 13, 2009 at 05:56 from IEEE Xplore. Restrictions apply.