test pressure that is higher than the minimum required in UG-99(b), is the

inspection described in UG-99(g) required to be at a pressure not less than


the actual test pressure divided by 1.3?

Reply: Yes.

Standard Designation: BPV Section VIII Div 1


Edition/Addenda: Latest (2013)
Para./Fig./Table No: UG-45 vs UW-13(h)
Subject Description: When can UW-13(h) over-ride UG-45
Date Issued: 01/12/2015
Record Number: 14-1797
Historical Interpretation numbers :
Question(s) and Reply(ies): Question (1): With reference to Figure UW-13.4 is it permitted to have a
nozzle neck thickness of t1 at any part of the nozzle neck that is away from
the weld preparation for the attached piping [see U-1(e)(1)(a)]?

Reply (1): No.

Question (2): With reference to Figure UW-13.4 is it allowed to have trn at


any part of the neck beyond that defined by the tapered transitions shown in
Fig. UW13.4?

Reply (2): No.

Standard Designation: BPV Section VIII Div 1


Edition/Addenda: 2013 edition
Para./Fig./Table No: UG-34 and UG-44
Subject Description: Design Calculations for Blind Flanges
Date Issued: 03/30/2015
Record Number: 14-1803
Historical Interpretation numbers :
Question(s) and Reply(ies): Question (1). If a B16.5 or B16.47 blind flange is modified in a manner that
is not covered by those standards, may pressure/temperature ratings of these
standards be used in accordance with UG-44?

Reply (1). No.

Question (2). In the situation described in Question 1, would calculations


using the design provisions of UG-34 and UG-39 be required?

Reply (2). Yes.

Standard Designation: BPV Section VIII Div 1


Edition/Addenda: 2013 Edition
Para./Fig./Table No: UW-2(a), UCL-34