ID Task Name Duration Month 2 Month 3 Month 4 Month 5

Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18
1 Construction of block of 2 compartments shower 44 days
room and 3 compartments of Latrines with zinc super
structure
2 Site mobilisation 4 days
3 Site setting out 2 days
4 SHOWER ROOMS 35 days
5 Excavation and Earth work 7 days
6 Sub-Structure 16 days
7 Reinforcement 4 days
8 Formwork 2 days
9 Laying of pipes 2 days
10 Slabs casting 3 days
11 Block work 4 days
12 Super-Structure 10 days
13 Walling 5 days
14 Doors installation 2 days
15 Finishes 3 days
16 LATRINES 25 days
17 Clearing of site 2 days
18 Sub-structure 16 days
19 Excavation and Earth work 7 days
20 Reinforcement 4 days
21 Formwork 2 days
22 Block Work 2 days
23 Superstructure(zinc) and Roofing 7 days
24 Walls cover and internal partition 5 days
25 Zinc doors installation 2 days
26 Roof installation 2 days
27 Construction a Block of 3 - in - 1 Stance Bathing Shower 29 days

28 SHOWER 29 days
29 Sub-Structure 19 days
30 Excavation and Earth work 7 days
31 Reinforced Concrete Works 4 days
32 Formwork 2 days
33 Laying of pipes 2 days
34 Slabs casting 3 days
35 Block work 4 days
36 Super-Structure 10 days
37 Walling 5 days
38 Doors installation 2 days
39 Finishes 3 days
40 Construction of Shared Single Pit VIP Household Latrines in 35 days
Dikwa, Ngala Damboa and Gwoza
41 SHOWER ROOMS 35 days
42 Clearing of site 2 days
43 Sub-Structure 19 days
44 Excavation and Earth work 7 days
45 Reinforcement 3 days
46 Formwork 7 days
47 Laying of pipes 2 days
48 Block Work 3 days
49 Slabs casting 3 days
50 Super-Structure 14 days
51 Walling 5 days
52 Doors 2 days
53 Finishes 3 days
54 Site clearing and Hand over 4 days